1054 W 58TH ST 90037
Certificate Information: 1054 W 58TH ST 90037
- Application / Permit
- 23014-10000-03108
- Plan Check / Job No.
- B23LA14494
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ROOM ADDITION TO EXISTING SFD "COMPLY WITH DEPARTMENT ORDER effective date 06/26/2023. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 9/13/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/7/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/4/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/8/2023 | KHUONG TRUONG |
| Corrections Issued | 8/8/2023 | KHUONG TRUONG |
| Building Plans Picked Up | 8/9/2023 | APPLICANT |
| Plan Check Approved | 9/12/2023 | ADAM HEGAZI |
| Issued | 9/13/2023 | APPLICANT |
| CofO in Progress | 1/23/2024 | JEREMY TODD |
| Permit Finaled | 3/7/2024 | BRUCE TODD |
| CofO Issued | 3/7/2024 | BRUCE TODD |
| Permit Finaled | 3/7/2024 | BRUCE TODD |
Permit Application Clearance Information
| Historic Resource Verification | Cleared | 8/29/2023 | MAX LODER |
| Metro Rail approval | Cleared | 8/29/2023 | JENNIFER SU |
| Roof/Waste drainage to street | Cleared | 9/8/2023 | CHRISTINA BRACO |
| Eng Process Fee Ord 176,300 | Cleared | 9/12/2023 | CHRISTINA BRACO |
| Redevelopment Project Area | Cleared | 9/12/2023 | ELIZABETH GALLARDO |
| Sewer availability | Cleared | 9/12/2023 | CHRISTINA BRACO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Cooke,, Conway Cecil; Lic. No.: S5524 | 34658 LINDA ROSEA RD TEMECULA, CA 92592 |
Inspector Information
| JEREMY TODD, (213) 978-4495 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARVIN FONSECA, (213) 978-4495 | Office Hours: 7:00-8:00 AM MON-FRI |
| DANIEL GUEVARA, (213) 978-4495 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/11/2023 | Approved | JEREMY TODD |
| Floor/Roof Diaphrgm/Shear Wall | 11/9/2023 | Approved | JEREMY TODD |
| Floor/Roof Diaphrgm/Shear Wall | 11/28/2023 | Approved | JEREMY TODD |
| Insulation | 12/12/2023 | Approved | JEREMY TODD |
| Special/Order Compliance | 12/13/2023 | Approved | JEREMY TODD |
| Drywall Nailing | 12/14/2023 | Approved | DANIEL GUEVARA |
| BUILDING-Rough-Frame | 12/21/2023 | Approved | JEREMY TODD |
| ELECTRICAL-Final | 12/21/2023 | Corrections Issued | JEREMY TODD |
| Final | 12/21/2023 | Corrections Issued | JEREMY TODD |
| Green Building Final | 12/21/2023 | Approved | JEREMY TODD |
| Green Building Rough | 12/21/2023 | Approved | JEREMY TODD |
| SGSOV-Seismic Gas S/O Valve | 12/21/2023 | SGSOV Approved | JEREMY TODD |
| Smoke Detectors | 12/21/2023 | Approved | JEREMY TODD |
| ELECTRICAL-Final | 1/18/2024 | Approved | JEREMY TODD |
| PLUMBING-Final | 1/18/2024 | Approved | JEREMY TODD |
| Final | 1/23/2024 | OK to Issue CofO | JEREMY TODD |