5019 N DONNA AVE 91356

Certificate Information: 5019 N DONNA AVE 91356

Application / Permit
23014-10000-03070
Plan Check / Job No.
B23LA14279
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR REMODEL AND FIRST FLOOR ADDITION (637 SQ. FT.)
Permit Issued
Issued on 11/2/2023
Issuing Office
Metro
Current Status
CofO Issued on 3/28/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/2/2023 APPLICANT
Assigned to Plan Check Engineer 8/3/2023 NGHI SU
Corrections Issued 8/8/2023 NGHI SU
Quality Review Completed 8/9/2023 KEN GILL
Building Plans Picked Up 8/10/2023 APPLICANT
Plan Check Approved 10/31/2023 NGHI SU
Issued 11/2/2023 APPLICANT
CofO in Progress 2/12/2025 JOHN KIDWELL
CofO in Progress 3/10/2025 SEAN WIRCH
Permit Finaled 3/28/2025 JOHN JANSON
CofO Issued 3/28/2025 JOHN JANSON
Permit Finaled 3/28/2025 JOHN JANSON

Permit Application Clearance Information

Low Impact Development (LID) Cleared 9/18/2023 ERNEST TSE
BHO/Hillside ordinance Cleared 9/21/2023 ROMAN GUTIERREZ
BHO/Hillside ordinance Cleared 9/21/2023 ROMAN GUTIERREZ
BHO/Hillside ordinance Cleared 9/21/2023 ROMAN GUTIERREZ
BHO/Hillside ordinance Cleared 9/21/2023 ROMAN GUTIERREZ
BHO/Hillside ordinance Cleared 9/21/2023 ROMAN GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 9/21/2023 ROMAN GUTIERREZ
Roof/Waste drainage to street Cleared 9/21/2023 ROMAN GUTIERREZ
Sewer availability Cleared 9/21/2023 ROMAN GUTIERREZ
GPI Written Notices Cleared 10/5/2023 NGHI SU
Grading Pre-Inspection Cleared 10/5/2023 NGHI SU
Hydrant and Access approval Cleared 10/22/2023 JOHN CONNEALLY

Contact Information

Contractor Owner-Builder       ,
Engineer Korganyan,, Karen; Lic. No.: L8510 5642 ETIWANDA AVE 9      TARZANA, CA 91356
Engineer Oruncakciel,, Sayat; Lic. No.: C77182 15445 VENTURA BLVD 25      SHERMAN OAKS, CA 91403

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/20/2023 Approved SEAN HAUPT
Deputy Drilled-In Anchors 12/8/2023 Approved SEAN HAUPT
Underground Mechanical 12/14/2023 Partial Approval JOHN KIDWELL
Excavation/Setback/Form/Re-Bar 12/19/2023 Not Ready for Inspection SEAN HAUPT
Footing/Foundation/Slab 12/19/2023 Corrections Issued SEAN HAUPT
Excavation/Setback/Form/Re-Bar 12/21/2023 Approved SEAN HAUPT
Footing/Foundation/Slab 12/21/2023 Approved SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 1/31/2024 Approved SEAN HAUPT
BUILDING-Rough-Frame 4/1/2024 Not Ready for Inspection GEVORK IPCHYAN
ELECTRICAL-Rough 4/1/2024 Not Ready for Inspection GEVORK IPCHYAN
Green Building Rough 4/1/2024 Not Ready for Inspection GEVORK IPCHYAN
HVAC-Rough 4/1/2024 Not Ready for Inspection GEVORK IPCHYAN
PLUMBING-Rough 4/1/2024 Partial Approval GEVORK IPCHYAN
Wood Frame 4/1/2024 Not Ready for Inspection GEVORK IPCHYAN
Deputy Wood Construction 4/2/2024 Partial Approval JOHN KIDWELL
Gas Test 4/2/2024 Partial Approval JOHN KIDWELL
Sewer 4/2/2024 Approved JOHN KIDWELL
BUILDING-Rough-Frame 4/4/2024 Approved JOHN KIDWELL
Green Building Rough 4/4/2024 Approved JOHN KIDWELL
Rough-Elec/Plmb/HVAC 4/4/2024 Approved JOHN KIDWELL
Gas Test 4/9/2024 Partial Approval JOHN KIDWELL
Insulation 5/15/2024 Approved JOHN KIDWELL
Interior/Exterior Lathing 5/15/2024 Partial Approval JOHN KIDWELL
Drywall Nailing 5/28/2024 Approved JOHN KIDWELL
Shower Pan 6/21/2024 Approved JOHN KIDWELL
Interior/Exterior Lathing 6/27/2024 Approved JOHN KIDWELL
ELECTRICAL-Final 9/20/2024 Not Ready for Inspection JOHN KIDWELL
Final 12/16/2024 Corrections Issued SEAN WIRCH
Green Building Final 12/16/2024 Not Ready for Inspection SEAN WIRCH
SGSOV-Seismic Gas S/O Valve 12/16/2024 SGSOV Not Ready SEAN WIRCH
Smoke Detectors 12/16/2024 Approved SEAN WIRCH
Final 1/27/2025 Not Ready for Inspection JOHN KIDWELL
Green Building Final 1/27/2025 Not Ready for Inspection JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 1/27/2025 SGSOV Not Ready JOHN KIDWELL
Final 2/12/2025 OK to Issue CofO JOHN KIDWELL
Green Building Final 2/12/2025 Approved JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 2/12/2025 SGSOV Approved JOHN KIDWELL