1008-1010 S SHERBOURNE DR 90035
Certificate Information: 1008-1010 S SHERBOURNE DR 90035
- Application / Permit
- 23014-10000-03069
- Plan Check / Job No.
- B23LA14259
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan - conversion of and addition to (e) detached 1-story 5-car garage resulting in 1 ADU at ground floor 1 ADU at 2nd floor per GCS 65852.2(e)(1)(D) and LAMC 12.22 A.33 (c)(d)(g) R3 occupancy
- Permit Issued
- Issued on 12/27/2024
- Issuing Office
- Current Status
- Issued on 12/27/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/2/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/3/2023 | KELVIN CHUONG |
| Corrections Issued | 8/10/2023 | KELVIN CHUONG |
| Quality Review Completed | 8/17/2023 | RODOLFO ARIAS |
| Applicant returned to address corrections | 11/7/2023 | KELVIN CHUONG |
| Applicant returned to address corrections | 1/8/2024 | KELVIN CHUONG |
| Applicant returned to address corrections | 2/26/2024 | KELVIN CHUONG |
| Applicant returned to address corrections | 10/30/2024 | KELVIN CHUONG |
| Applicant returned to address corrections | 12/4/2024 | KELVIN CHUONG |
| Plan Check Approved | 12/17/2024 | KELVIN CHUONG |
| Issued | 12/27/2024 | APPLICANT |
Permit Application Clearance Information
| "Q" conditions | Cleared | 8/17/2023 | RYAN LY |
| Address approval | Cleared | 8/22/2023 | CHRISTINA BRACO |
| Eng Process Fee Ord 176,300 | Cleared | 8/22/2023 | CHRISTINA BRACO |
| Sewer availability | Cleared | 8/22/2023 | CHRISTINA BRACO |
| Address approval | Cleared | 11/14/2023 | CHRISTINA BRACO |
| Tenant Habitability Plan | Cleared | 2/1/2024 | HUGO GARRIDO GARZA |
| Low Impact Development (LID) | Cleared | 6/25/2024 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 6/27/2024 | CHRISTINA BRACO |
| Construction near power lines | Cleared | 12/11/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/22/2025 | Approved | EVAN COOPER |
| Pre-Inspection | 6/24/2025 | Approved | EVAN COOPER |
| Pre-Inspection | 6/27/2025 | Approved | EVAN COOPER |
| PLUMBING-Rough | 7/11/2025 | Partial Approval | EVAN COOPER |
| Excavation/Setback/Form/Re-Bar | 7/23/2025 | Corrections Issued | EVAN COOPER |
| Excavation/Setback/Form/Re-Bar | 7/29/2025 | Corrections Issued | EVAN COOPER |
| Deputy Steel/Welding | 8/7/2025 | Conditional Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 8/25/2025 | Conditional Approval | EVAN COOPER |
| ELECTRICAL-Rough | 9/15/2025 | Partial Approval | EVAN COOPER |
| PLUMBING-Rough | 9/15/2025 | Partial Approval | EVAN COOPER |
| Pre-Inspection | 9/26/2025 | Approved | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 10/3/2025 | Partial Approval | EVAN COOPER |
| PLUMBING-Rough | 10/15/2025 | Not Ready for Inspection | EVAN COOPER |
| Gas Test | 10/29/2025 | Partial Approval | EVAN COOPER |
| HVAC-Rough | 10/29/2025 | Corrections Issued | EVAN COOPER |
| PLUMBING-Rough | 10/29/2025 | Corrections Issued | EVAN COOPER |
| HVAC-Rough | 11/3/2025 | Approved | EVAN COOPER |
| PLUMBING-Rough | 11/3/2025 | Approved | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 11/6/2025 | Corrections Issued | EVAN COOPER |
| ELECTRICAL-Rough | 11/10/2025 | Corrections Issued | ANDREW NAVE |
| ELECTRICAL-Rough | 11/14/2025 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 11/14/2025 | Partial Approval | EVAN COOPER |
| BUILDING-Rough-Frame | 12/9/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| Green Building Rough | 12/9/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| METHANE-Rough | 12/9/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| Wood Frame | 12/9/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 12/12/2025 | Conditional Approval | EVAN COOPER |
| Green Building Rough | 12/12/2025 | Approved | EVAN COOPER |
| Insulation | 12/26/2025 | Corrections Issued | ASHLEY THOMPSON |
| Insulation | 1/2/2026 | Approved | WILBER ROSALES |
| Drywall Nailing | 1/13/2026 | Partial Approval | WILBER ROSALES |
| Drywall Nailing | 1/20/2026 | Approved | WILBER ROSALES |
| Interior/Exterior Lathing | 1/20/2026 | Not Ready for Inspection | WILBER ROSALES |
| Shower Pan | 1/20/2026 | Not Ready for Inspection | WILBER ROSALES |
| Underground Mechanical | 1/20/2026 | Partial Approval | WILBER ROSALES |
| Interior/Exterior Lathing | 1/29/2026 | Approved | WILBER ROSALES |
| Shower Pan | 1/29/2026 | Approved | WILBER ROSALES |
| Sewer | 2/12/2026 | Approved | WILBER ROSALES |
| Underground Mechanical | 2/12/2026 | Approved | WILBER ROSALES |
| Special/Order Compliance | 2/24/2026 | Partial Inspection | DAVID FEILER |
| Special/Order Compliance | 2/24/2026 | Partial Inspection | JUAN VALENZUELA |
| ELECTRICAL-Final | 6/1/2026 | Approved | WILBER ROSALES |
| HVAC-Final | 6/1/2026 | Corrections Issued | WILBER ROSALES |