1539 W 213TH ST 90501

Certificate Information: 1539 W 213TH ST 90501

Application / Permit
23014-10000-03067
Plan Check / Job No.
B23LA14234
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
**ePlan** ADDITION AND REMODEL TO (E) SFD
Permit Issued
Issued on 1/30/2024
Issuing Office
Current Status
CofO Issued on 8/23/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/4/2023 APPLICANT
Assigned to Plan Check Engineer 8/9/2023 EDWIN ESPIN
Corrections Issued 8/10/2023 EDWIN ESPIN
Applicant returned to address corrections 10/12/2023 CARLOS MONTES
Applicant returned to address corrections 10/24/2023 CARLOS MONTES
Applicant returned to address corrections 11/8/2023 CARLOS MONTES
Applicant returned to address corrections 12/11/2023 CARLOS MONTES
Applicant returned to address corrections 1/10/2024 EDWIN ESPIN
Applicant returned to address corrections 1/24/2024 EDWIN ESPIN
Plan Check Approved 1/30/2024 FERNANDO FLORES
Issued 1/30/2024 APPLICANT
CofO in Progress 8/22/2024 EUGENE CASSIDY
Permit Finaled 8/23/2024 ANSON MAGLASANG
CofO Issued 8/23/2024 ANSON MAGLASANG
Permit Finaled 8/23/2024 ANSON MAGLASANG

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/23/2023 HUGO LOPEZ
Roof/Waste drainage to street Cleared 10/6/2023 CHRISTINA BRACO
Sewer availability Cleared 10/12/2023 CHRISTINA BRACO
Low Impact Development (LID) Cleared 11/28/2023 ROGELIO CORTES

Contact Information

Contractor Owner-Builder       ,

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/2/2024 Partial Approval EUGENE CASSIDY
BUILDING-Rough-Frame 2/9/2024 Partial Approval EUGENE CASSIDY
Wood Frame 2/13/2024 Partial Approval EUGENE CASSIDY
Excavation/Setback/Form/Re-Bar 2/15/2024 Approved EUGENE CASSIDY
ELECTRICAL-Rough 2/22/2024 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Rough 2/22/2024 Corrections Issued EUGENE CASSIDY
Wood Frame 2/22/2024 Partial Approval EUGENE CASSIDY
ELECTRICAL-Rough 3/5/2024 Corrections Issued EUGENE CASSIDY
HVAC-Rough 3/5/2024 Approved EUGENE CASSIDY
Interior/Exterior Lathing 3/5/2024 Corrections Issued EUGENE CASSIDY
PLUMBING-Rough 3/5/2024 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 3/7/2024 Approved EUGENE CASSIDY
ELECTRICAL-Rough 3/7/2024 Approved EUGENE CASSIDY
Green Building Rough 3/7/2024 Approved EUGENE CASSIDY
Insulation 3/7/2024 Corrections Issued EUGENE CASSIDY
Interior/Exterior Lathing 3/7/2024 Partial Approval EUGENE CASSIDY
Drywall Nailing 3/11/2024 Corrections Issued EUGENE CASSIDY
Drywall Nailing 3/12/2024 Approved EUGENE CASSIDY
Shower Pan 3/26/2024 Approved EUGENE CASSIDY
Interior/Exterior Lathing 4/2/2024 Approved EUGENE CASSIDY
Final 4/29/2024 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 4/29/2024 Approved EUGENE CASSIDY
Green Building Final 4/29/2024 Not Ready for Inspection EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 4/29/2024 SGSOV Approved EUGENE CASSIDY
Smoke Detectors 4/29/2024 Approved EUGENE CASSIDY
Final 5/3/2024 Corrections Issued EUGENE CASSIDY
Green Building Final 5/3/2024 Approved EUGENE CASSIDY
ELECTRICAL-Final 8/22/2024 Approved EUGENE CASSIDY
Final 8/22/2024 OK to Issue CofO EUGENE CASSIDY
HVAC-Final 8/22/2024 Approved EUGENE CASSIDY
PLUMBING-Final 8/22/2024 Approved EUGENE CASSIDY