17201 W LUVERNE PL 91316

Certificate Information: 17201 W LUVERNE PL 91316

Application / Permit
23014-10000-03017
Plan Check / Job No.
B23LA13959
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan GROUND FLOOR ADDITION TO (E) 2-STORY SFD WITH INT. STR. REMODEL AND NEW ATT. TRELLIS
Permit Issued
Issued on 12/5/2023
Issuing Office
Current Status
CofO in Progress on 1/6/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/28/2023 APPLICANT
Assigned to Plan Check Engineer 8/10/2023 MAHNAZ NOURHASHEMI
Corrections Issued 8/21/2023 MAHNAZ NOURHASHEMI
Quality Review Completed 8/29/2023 TU HUA
Plan Check Approved 12/4/2023 MAHNAZ NOURHASHEMI
Issued 12/5/2023 APPLICANT
CofO in Progress 7/15/2024 THOMAS FINNILA
No Progress 1/6/2025 SEAN WIRCH
CofO in Progress 1/6/2025 SEAN WIRCH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/11/2023 TAL SHEMEN
ZA Case Cleared 9/11/2023 MAXFIELD VERMY
ZA Case Cleared 9/11/2023 MAXFIELD VERMY
Grading Pre-Inspection Cleared 9/15/2023 MICHAEL TEMPLE
Roof/Waste drainage to street Cleared 11/6/2023 TAL SHEMEN

Contact Information

Architect Di, Zitti, Fernando; Lic. No.: NA24587       ,
Contractor Mandrake Construction Co Inc; Lic. No.: 832756-B       ,

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 12/7/2023 Partial Approval SEAN HAUPT
Deputy Drilled-In Anchors 12/7/2023 Approved SEAN HAUPT
ELECTRICAL-Rough 12/7/2023 Partial Approval SEAN HAUPT
Excavation/Setback/Form/Re-Bar 12/7/2023 Partial Approval SEAN HAUPT
Footing/Foundation/Slab 12/7/2023 Partial Approval SEAN HAUPT
HVAC-Rough 12/7/2023 Partial Approval SEAN HAUPT
PLUMBING-Rough 12/7/2023 Partial Approval SEAN HAUPT
ELECTRICAL-Rough 12/12/2023 Partial Approval VINCENT HANLEY
Insulation 12/12/2023 Partial Approval VINCENT HANLEY
Drywall Nailing 12/19/2023 Approved VINCENT HANLEY
Interior/Exterior Lathing 12/19/2023 Approved VINCENT HANLEY
ELECTRICAL-Rough 1/4/2024 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 1/4/2024 Approved VINCENT HANLEY
HVAC-Rough 1/4/2024 Approved VINCENT HANLEY
Reinforced Masonry Frame 1/4/2024 Approved VINCENT HANLEY
Wood Frame 1/4/2024 Approved VINCENT HANLEY
Light Gage Steel Frame 1/9/2024 Partial Inspection KRISTEN CAUSEY
Interior/Exterior Lathing 1/12/2024 Partial Approval VINCENT HANLEY
Insulation 1/18/2024 Approved VINCENT HANLEY
Drywall Nailing 1/24/2024 Approved VINCENT HANLEY
BUILDING-Rough-Frame 4/15/2024 Corrections Issued VINCENT HANLEY
Final 4/15/2024 Corrections Issued VINCENT HANLEY
Footing/Foundation/Slab 4/15/2024 Corrections Issued VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 4/15/2024 SGSOV Approved VINCENT HANLEY
Smoke Detectors 4/15/2024 Approved VINCENT HANLEY
BUILDING-Rough-Frame 6/21/2024 Not Ready for Inspection THOMAS FINNILA
Final 6/21/2024 Not Ready for Inspection THOMAS FINNILA
Footing/Foundation/Slab 6/21/2024 Not Ready for Inspection THOMAS FINNILA
BUILDING-Rough-Frame 6/28/2024 Approved THOMAS FINNILA
Final 6/28/2024 Not Ready for Inspection THOMAS FINNILA
Footing/Foundation/Slab 6/28/2024 Approved THOMAS FINNILA
Final 7/12/2024 OK to Issue CofO THOMAS FINNILA