6506 W 83RD ST 90045

Certificate Information: 6506 W 83RD ST 90045

Application / Permit
23014-10000-03014
Plan Check / Job No.
B23LA13958
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN 2ND STORY ADDITION AND LAUNDRY ROOM ADDITION AND CONVERSION OF (E) GARAGE AND RECREATION ROOM INTO A 2 STORY DETACHED ACCESSORY DWELLING UNI PER 12.22 A.33(c)-(d).
Permit Issued
Issued on 4/5/2024
Issuing Office
Current Status
CofO Issued on 2/20/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/29/2023 APPLICANT
Assigned to Plan Check Engineer 8/10/2023 MINA HABIB
Corrections Issued 8/15/2023 MINA HABIB
Quality Review Completed 8/16/2023 RODOLFO ARIAS
Applicant returned to address corrections 10/3/2023 MINA HABIB
Applicant returned to address corrections 10/16/2023 MINA HABIB
Applicant returned to address corrections 12/28/2023 MINA HABIB
Applicant returned to address corrections 1/17/2024 MINA HABIB
Applicant returned to address corrections 3/4/2024 MINA HABIB
Applicant returned to address corrections 3/11/2024 MINA HABIB
Applicant returned to address corrections 3/14/2024 MINA HABIB
Applicant returned to address corrections 3/21/2024 MINA HABIB
Plan Check Approved 3/29/2024 MINA HABIB
Issued 4/5/2024 APPLICANT
CofO in Progress 2/20/2025 TEMISTOCLES CAAL
Permit Finaled 2/20/2025 RICHARD STEINBACH
CofO Issued 2/20/2025 RICHARD STEINBACH
Permit Finaled 2/20/2025 RICHARD STEINBACH

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 8/22/2023 NEIL TUANO
Specific Plan Cleared 8/28/2023 FREDDY GARCIA
Construction near power lines Cleared 10/23/2023 OSCAR CASTRO
Construction within easement Cleared 10/23/2023 OSCAR CASTRO
Address approval Cleared 11/1/2023 NEIL TUANO
Eng Process Fee Ord 176,300 Cleared 11/1/2023 NEIL TUANO
Sewer availability Cleared 11/1/2023 NEIL TUANO
Green Code Cleared 3/14/2024 MINA HABIB

Contact Information

Architect Ribeiro, De Moura, Ricardo Jorge; Lic. No.: NA38075       ,
Contractor Rocka Builders Inc; Lic. No.: 1050219-B       ,
Engineer Karapetian,, Arbi; Lic. No.: NA79953       ,
Engineer Manepalli,, Pavan S; Lic. No.: C72416 15742 57TH PLACE NORTH      PLYMOUTH, MN 55446

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/6/2024 Conditional Approval TEMISTOCLES CAAL
Footing/Foundation/Slab 5/7/2024 Partial Approval TEMISTOCLES CAAL
Special/Order Compliance 5/7/2024 Corrections Issued TEMISTOCLES CAAL
Special/Order Compliance 5/7/2024 Partial Inspection HERBERT GIRON
Underground Mechanical 5/7/2024 Partial Approval TEMISTOCLES CAAL
Footing/Foundation/Slab 5/9/2024 Partial Approval TEMISTOCLES CAAL
Special/Order Compliance 5/9/2024 Partial Inspection HERBERT GIRON
Footing/Foundation/Slab 5/17/2024 Partial Approval TEMISTOCLES CAAL
Deputy Drilled-In Anchors 5/20/2024 Approved TEMISTOCLES CAAL
Footing/Foundation/Slab 5/20/2024 Approved TEMISTOCLES CAAL
PLUMBING-Rough 5/20/2024 Partial Approval TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 6/5/2024 Corrections Issued TEMISTOCLES CAAL
Special/Order Compliance 6/5/2024 Partial Inspection HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 7/24/2024 Partial Approval TEMISTOCLES CAAL
BUILDING-Rough-Frame 8/5/2024 Not Ready for Inspection TEMISTOCLES CAAL
ELECTRICAL-Rough 8/5/2024 Approved TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 8/5/2024 Not Ready for Inspection TEMISTOCLES CAAL
HVAC-Rough 8/5/2024 Approved TEMISTOCLES CAAL
PLUMBING-Rough 8/5/2024 Approved TEMISTOCLES CAAL
Special/Order Compliance 8/5/2024 Corrections Issued TEMISTOCLES CAAL
Insulation 8/7/2024 Partial Approval TEMISTOCLES CAAL
BUILDING-Rough-Frame 8/21/2024 Approved TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 8/21/2024 Approved TEMISTOCLES CAAL
Green Building Rough 8/21/2024 Approved TEMISTOCLES CAAL
Insulation 8/21/2024 Approved TEMISTOCLES CAAL
Drywall Nailing 8/27/2024 Approved TEMISTOCLES CAAL
Interior/Exterior Lathing 8/27/2024 Partial Approval TEMISTOCLES CAAL
Sewer 9/25/2024 Approved TEMISTOCLES CAAL
Underground Mechanical 9/26/2024 Partial Approval TEMISTOCLES CAAL
Underground Mechanical 9/27/2024 Not Ready for Inspection TEMISTOCLES CAAL
Shower Pan 9/30/2024 Approved TEMISTOCLES CAAL
Underground Mechanical 9/30/2024 Approved TEMISTOCLES CAAL
Gas Test 11/15/2024 Approved MICHAEL ALLEN
ELECTRICAL-Final 2/13/2025 Approved TEMISTOCLES CAAL
Final 2/13/2025 OK to Issue CofO TEMISTOCLES CAAL
Green Building Final 2/13/2025 Approved TEMISTOCLES CAAL
HVAC-Final 2/13/2025 Approved TEMISTOCLES CAAL
PLUMBING-Final 2/13/2025 Approved TEMISTOCLES CAAL
SGSOV-Seismic Gas S/O Valve 2/13/2025 SGSOV Approved TEMISTOCLES CAAL
Smoke Detectors 2/13/2025 Approved TEMISTOCLES CAAL