6506 W 83RD ST 90045
Certificate Information: 6506 W 83RD ST 90045
- Application / Permit
- 23014-10000-03014
- Plan Check / Job No.
- B23LA13958
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN 2ND STORY ADDITION AND LAUNDRY ROOM ADDITION AND CONVERSION OF (E) GARAGE AND RECREATION ROOM INTO A 2 STORY DETACHED ACCESSORY DWELLING UNI PER 12.22 A.33(c)-(d).
- Permit Issued
- Issued on 4/5/2024
- Issuing Office
- Current Status
- CofO Issued on 2/20/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/29/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/10/2023 | MINA HABIB |
| Corrections Issued | 8/15/2023 | MINA HABIB |
| Quality Review Completed | 8/16/2023 | RODOLFO ARIAS |
| Applicant returned to address corrections | 10/3/2023 | MINA HABIB |
| Applicant returned to address corrections | 10/16/2023 | MINA HABIB |
| Applicant returned to address corrections | 12/28/2023 | MINA HABIB |
| Applicant returned to address corrections | 1/17/2024 | MINA HABIB |
| Applicant returned to address corrections | 3/4/2024 | MINA HABIB |
| Applicant returned to address corrections | 3/11/2024 | MINA HABIB |
| Applicant returned to address corrections | 3/14/2024 | MINA HABIB |
| Applicant returned to address corrections | 3/21/2024 | MINA HABIB |
| Plan Check Approved | 3/29/2024 | MINA HABIB |
| Issued | 4/5/2024 | APPLICANT |
| CofO in Progress | 2/20/2025 | TEMISTOCLES CAAL |
| Permit Finaled | 2/20/2025 | RICHARD STEINBACH |
| CofO Issued | 2/20/2025 | RICHARD STEINBACH |
| Permit Finaled | 2/20/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 8/22/2023 | NEIL TUANO |
| Specific Plan | Cleared | 8/28/2023 | FREDDY GARCIA |
| Construction near power lines | Cleared | 10/23/2023 | OSCAR CASTRO |
| Construction within easement | Cleared | 10/23/2023 | OSCAR CASTRO |
| Address approval | Cleared | 11/1/2023 | NEIL TUANO |
| Eng Process Fee Ord 176,300 | Cleared | 11/1/2023 | NEIL TUANO |
| Sewer availability | Cleared | 11/1/2023 | NEIL TUANO |
| Green Code | Cleared | 3/14/2024 | MINA HABIB |
Contact Information
| Architect | Ribeiro, De Moura, Ricardo Jorge; Lic. No.: NA38075 | , |
| Contractor | Rocka Builders Inc; Lic. No.: 1050219-B | , |
| Engineer | Karapetian,, Arbi; Lic. No.: NA79953 | , |
| Engineer | Manepalli,, Pavan S; Lic. No.: C72416 | 15742 57TH PLACE NORTH PLYMOUTH, MN 55446 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/6/2024 | Conditional Approval | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 5/7/2024 | Partial Approval | TEMISTOCLES CAAL |
| Special/Order Compliance | 5/7/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Special/Order Compliance | 5/7/2024 | Partial Inspection | HERBERT GIRON |
| Underground Mechanical | 5/7/2024 | Partial Approval | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 5/9/2024 | Partial Approval | TEMISTOCLES CAAL |
| Special/Order Compliance | 5/9/2024 | Partial Inspection | HERBERT GIRON |
| Footing/Foundation/Slab | 5/17/2024 | Partial Approval | TEMISTOCLES CAAL |
| Deputy Drilled-In Anchors | 5/20/2024 | Approved | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 5/20/2024 | Approved | TEMISTOCLES CAAL |
| PLUMBING-Rough | 5/20/2024 | Partial Approval | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 6/5/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Special/Order Compliance | 6/5/2024 | Partial Inspection | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 7/24/2024 | Partial Approval | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 8/5/2024 | Not Ready for Inspection | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 8/5/2024 | Approved | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 8/5/2024 | Not Ready for Inspection | TEMISTOCLES CAAL |
| HVAC-Rough | 8/5/2024 | Approved | TEMISTOCLES CAAL |
| PLUMBING-Rough | 8/5/2024 | Approved | TEMISTOCLES CAAL |
| Special/Order Compliance | 8/5/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Insulation | 8/7/2024 | Partial Approval | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 8/21/2024 | Approved | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 8/21/2024 | Approved | TEMISTOCLES CAAL |
| Green Building Rough | 8/21/2024 | Approved | TEMISTOCLES CAAL |
| Insulation | 8/21/2024 | Approved | TEMISTOCLES CAAL |
| Drywall Nailing | 8/27/2024 | Approved | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 8/27/2024 | Partial Approval | TEMISTOCLES CAAL |
| Sewer | 9/25/2024 | Approved | TEMISTOCLES CAAL |
| Underground Mechanical | 9/26/2024 | Partial Approval | TEMISTOCLES CAAL |
| Underground Mechanical | 9/27/2024 | Not Ready for Inspection | TEMISTOCLES CAAL |
| Shower Pan | 9/30/2024 | Approved | TEMISTOCLES CAAL |
| Underground Mechanical | 9/30/2024 | Approved | TEMISTOCLES CAAL |
| Gas Test | 11/15/2024 | Approved | MICHAEL ALLEN |
| ELECTRICAL-Final | 2/13/2025 | Approved | TEMISTOCLES CAAL |
| Final | 2/13/2025 | OK to Issue CofO | TEMISTOCLES CAAL |
| Green Building Final | 2/13/2025 | Approved | TEMISTOCLES CAAL |
| HVAC-Final | 2/13/2025 | Approved | TEMISTOCLES CAAL |
| PLUMBING-Final | 2/13/2025 | Approved | TEMISTOCLES CAAL |
| SGSOV-Seismic Gas S/O Valve | 2/13/2025 | SGSOV Approved | TEMISTOCLES CAAL |
| Smoke Detectors | 2/13/2025 | Approved | TEMISTOCLES CAAL |