2912 S BEACH AVE 90291

Certificate Information: 2912 S BEACH AVE 90291

Application / Permit
23014-10000-02999
Plan Check / Job No.
B23LA13867
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: (N) addition to (E) 1-story SFD
Permit Issued
Issued on 10/11/2023
Issuing Office
Current Status
CofO Issued on 5/4/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/27/2023 APPLICANT
Assigned to Plan Check Engineer 8/4/2023 CAROLEAN BASMA
Corrections Issued 8/8/2023 CAROLEAN BASMA
Applicant returned to address corrections 9/16/2023 CAROLEAN BASMA
Plan Check Approved 10/11/2023 VICTOR CHEN
Issued 10/11/2023 APPLICANT
CofO in Progress 4/30/2024 HERBERT GIRON
Permit Finaled 5/4/2024 DANIEL ORRANTE
CofO Issued 5/4/2024 DANIEL ORRANTE
Permit Finaled 5/4/2024 DANIEL ORRANTE

Permit Application Clearance Information

Miscellaneous Cleared 8/16/2023 SPENCER WEJROWSKI
Miscellaneous Cleared 8/16/2023 SPENCER WEJROWSKI
Miscellaneous Cleared 8/16/2023 SPENCER WEJROWSKI
Eng Process Fee Ord 176,300 Cleared 8/28/2023 ANTHONY MAINEZ
Coastal Zone Cleared 9/8/2023 MAXFIELD VERMY
Flood clearance Cleared 10/3/2023 MIGUEL RODRIGUEZ
Specific Plan Cleared 10/4/2023 LUIS LOPEZ

Contact Information

Architect Gibbs,, Kurt Robert; Lic. No.: C22275 3575 LONG BEACH BLVD      LONG BEACH, CA 90807
Contractor Gibbs Kurt R; Lic. No.: 1053572-B       ,
Engineer Kim,, Hong Kook; Lic. No.: C64529 3600 WILSHIRE BLVD STE 1903      LOS ANGELES, CA 90010

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/16/2023 Partial Approval HERBERT GIRON
Deputy Steel/Welding 11/27/2023 Conditional Approval RICHARD STEINBACH
Footing/Foundation/Slab 11/30/2023 Approved HERBERT GIRON
Deputy Reinf. Concrete 12/1/2023 Conditional Approval HERBERT GIRON
Deputy Drilled-In Anchors 12/7/2023 Conditional Approval HERBERT GIRON
BUILDING-Rough-Frame 12/8/2023 Partial Approval HERBERT GIRON
Deputy Steel/Welding 12/11/2023 Conditional Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 1/2/2024 Partial Approval BOBBY KEY
ELECTRICAL-Rough 1/5/2024 Corrections Issued HERBERT GIRON
HVAC-Rough 1/5/2024 Approved HERBERT GIRON
PLUMBING-Rough 1/5/2024 Approved HERBERT GIRON
ELECTRICAL-Rough 1/9/2024 Approved HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 1/9/2024 Corrections Issued HERBERT GIRON
Interior/Exterior Lathing 1/9/2024 Partial Approval HERBERT GIRON
PLUMBING-Rough 1/9/2024 Approved HERBERT GIRON
Shower Pan 1/9/2024 Approved HERBERT GIRON
Underground Mechanical 1/9/2024 Partial Approval HERBERT GIRON
Deputy Wood Construction 1/10/2024 Conditional Approval HERBERT GIRON
BUILDING-Rough-Frame 1/17/2024 Corrections Issued HERBERT GIRON
Green Building Rough 1/17/2024 Approved HERBERT GIRON
Interior/Exterior Lathing 1/17/2024 Partial Approval HERBERT GIRON
Insulation 1/22/2024 Approved TEMISTOCLES CAAL
Drywall Nailing 1/25/2024 Approved HERBERT GIRON
Insulation 1/25/2024 Approved HERBERT GIRON
Special/Order Compliance 2/16/2024 Corrections Issued HERBERT GIRON
HVAC-Final 4/3/2024 Approved HERBERT GIRON
PLUMBING-Final 4/3/2024 Corrections Issued HERBERT GIRON
BUILDING-Rough-Frame 4/29/2024 Approved HERBERT GIRON
ELECTRICAL-Final 4/29/2024 Approved HERBERT GIRON
Final 4/29/2024 OK to Issue CofO HERBERT GIRON
Green Building Final 4/29/2024 Approved HERBERT GIRON
HVAC-Final 4/29/2024 Approved HERBERT GIRON
PLUMBING-Final 4/29/2024 Approved HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 4/29/2024 SGSOV Approved HERBERT GIRON
Service/Power Release 4/29/2024 Approved HERBERT GIRON
Smoke Detectors 4/29/2024 Approved HERBERT GIRON