557 W 113TH ST 90044

Certificate Information: 557 W 113TH ST 90044

Application / Permit
23014-10000-02948
Plan Check / Job No.
B23LA13651
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Remodel (E) 1-story SFD and enclose the (E) covered side porch to expand (E) kitchen area.
Permit Issued
Issued on 7/31/2023
Issuing Office
Metro
Current Status
CofO Issued on 7/3/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/25/2023 APPLICANT
Assigned to Plan Check Engineer 7/25/2023 MINA HABILI
Corrections Issued 7/25/2023 MINA HABILI
Issued 7/31/2023 APPLICANT
CofO in Progress 6/24/2024 JAMES CHAVEZ
Permit Finaled 7/3/2024 ANSON MAGLASANG
CofO Issued 7/3/2024 ANSON MAGLASANG
Permit Finaled 7/3/2024 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 7/29/2023 JEREMY CHOK
Eng Process Fee Ord 176,300 Cleared 7/31/2023 JEREMY CHOK

Contact Information

Contractor Owner-Builder       ,
Engineer Cooke,, Conway Cecil; Lic. No.: S5524 34658 LINDA ROSEA RD      TEMECULA, CA 92592

Inspector Information

BEN MOLSTAD, (310) 732-4557 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/11/2023 Conditional Approval ANSON MAGLASANG
Footing/Foundation/Slab 8/11/2023 Approved JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 8/17/2023 Partial Approval JAMES CHAVEZ
Special/Order Compliance 8/17/2023 Corrections Issued JAMES CHAVEZ
ELECTRICAL-Rough 9/27/2023 Corrections Issued JAMES CHAVEZ
Floor/Roof Diaphrgm/Shear Wall 9/27/2023 Approved JAMES CHAVEZ
Footing/Foundation/Slab 9/27/2023 Corrections Issued JAMES CHAVEZ
PLUMBING-Rough 9/27/2023 Approved JAMES CHAVEZ
ELECTRICAL-Rough 10/2/2023 Corrections Issued JOHN KLARIN
Interior/Exterior Lathing 10/2/2023 Approved JOHN KLARIN
Wood Frame 10/2/2023 Corrections Issued JOHN KLARIN
ELECTRICAL-Rough 10/16/2023 Approved JAMES CHAVEZ
Wood Frame 10/16/2023 Corrections Issued JAMES CHAVEZ
HVAC-Rough 10/30/2023 Approved JAMES CHAVEZ
Insulation 10/30/2023 Approved JAMES CHAVEZ
Drywall Nailing 11/9/2023 Approved JOHN KLARIN
Interior/Exterior Lathing 11/9/2023 Approved JOHN KLARIN
Shower Pan 11/9/2023 Approved JOHN KLARIN
BUILDING-Rough-Frame 2/23/2024 Approved JAMES CHAVEZ
Final 2/23/2024 Corrections Issued JAMES CHAVEZ
Smoke Detectors 2/23/2024 Not Ready for Inspection JAMES CHAVEZ
Final 5/13/2024 Corrections Issued JAMES CHAVEZ
Smoke Detectors 5/13/2024 Approved JAMES CHAVEZ
Final 6/17/2024 Corrections Issued BEN MOLSTAD
HVAC-Final 6/17/2024 Approved BEN MOLSTAD
Final 6/21/2024 OK to Issue CofO JAMES CHAVEZ