557 W 113TH ST 90044
Certificate Information: 557 W 113TH ST 90044
- Application / Permit
- 23014-10000-02948
- Plan Check / Job No.
- B23LA13651
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Remodel (E) 1-story SFD and enclose the (E) covered side porch to expand (E) kitchen area.
- Permit Issued
- Issued on 7/31/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 7/3/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/25/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/25/2023 | MINA HABILI |
| Corrections Issued | 7/25/2023 | MINA HABILI |
| Issued | 7/31/2023 | APPLICANT |
| CofO in Progress | 6/24/2024 | JAMES CHAVEZ |
| Permit Finaled | 7/3/2024 | ANSON MAGLASANG |
| CofO Issued | 7/3/2024 | ANSON MAGLASANG |
| Permit Finaled | 7/3/2024 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 7/29/2023 | JEREMY CHOK |
| Eng Process Fee Ord 176,300 | Cleared | 7/31/2023 | JEREMY CHOK |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Cooke,, Conway Cecil; Lic. No.: S5524 | 34658 LINDA ROSEA RD TEMECULA, CA 92592 |
Inspector Information
| BEN MOLSTAD, (310) 732-4557 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/11/2023 | Conditional Approval | ANSON MAGLASANG |
| Footing/Foundation/Slab | 8/11/2023 | Approved | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 8/17/2023 | Partial Approval | JAMES CHAVEZ |
| Special/Order Compliance | 8/17/2023 | Corrections Issued | JAMES CHAVEZ |
| ELECTRICAL-Rough | 9/27/2023 | Corrections Issued | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 9/27/2023 | Approved | JAMES CHAVEZ |
| Footing/Foundation/Slab | 9/27/2023 | Corrections Issued | JAMES CHAVEZ |
| PLUMBING-Rough | 9/27/2023 | Approved | JAMES CHAVEZ |
| ELECTRICAL-Rough | 10/2/2023 | Corrections Issued | JOHN KLARIN |
| Interior/Exterior Lathing | 10/2/2023 | Approved | JOHN KLARIN |
| Wood Frame | 10/2/2023 | Corrections Issued | JOHN KLARIN |
| ELECTRICAL-Rough | 10/16/2023 | Approved | JAMES CHAVEZ |
| Wood Frame | 10/16/2023 | Corrections Issued | JAMES CHAVEZ |
| HVAC-Rough | 10/30/2023 | Approved | JAMES CHAVEZ |
| Insulation | 10/30/2023 | Approved | JAMES CHAVEZ |
| Drywall Nailing | 11/9/2023 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 11/9/2023 | Approved | JOHN KLARIN |
| Shower Pan | 11/9/2023 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 2/23/2024 | Approved | JAMES CHAVEZ |
| Final | 2/23/2024 | Corrections Issued | JAMES CHAVEZ |
| Smoke Detectors | 2/23/2024 | Not Ready for Inspection | JAMES CHAVEZ |
| Final | 5/13/2024 | Corrections Issued | JAMES CHAVEZ |
| Smoke Detectors | 5/13/2024 | Approved | JAMES CHAVEZ |
| Final | 6/17/2024 | Corrections Issued | BEN MOLSTAD |
| HVAC-Final | 6/17/2024 | Approved | BEN MOLSTAD |
| Final | 6/21/2024 | OK to Issue CofO | JAMES CHAVEZ |