2723 W PRISMO DR 90065

Certificate Information: 2723 W PRISMO DR 90065

Application / Permit
23014-10000-02928
Plan Check / Job No.
B23LA13485
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1) FRONT PATIO ENCLOSURe; 2) NEW ADDITION TO THE 1ST FLOOR; 3) INTERIOR REMODELING ON THE 1ST FLOOR; 4) NEW 2ND FLOOR ADDITION
Permit Issued
Issued on 4/17/2025
Issuing Office
Current Status
Issued on 4/17/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/24/2023 APPLICANT
Assigned to Plan Check Engineer 8/10/2023 SUNMIN LEE
Corrections Issued 8/16/2023 SUNMIN LEE
Quality Review Completed 8/16/2023 GARO TELMI
Applicant returned to address corrections 3/5/2024 SUNMIN LEE
Applicant returned to address corrections 4/16/2024 SUNMIN LEE
Applicant returned to address corrections 5/3/2024 SUNMIN LEE
Plan Check Approved 8/12/2024 SUNMIN LEE
Issued 4/17/2025 APPLICANT

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 8/28/2023 CHRISTINA BRACO
BHO/Hillside ordinance Cleared 8/28/2023 CHRISTINA BRACO
BHO/Hillside ordinance Cleared 8/28/2023 CHRISTINA BRACO
BHO/Hillside ordinance Cleared 8/28/2023 CHRISTINA BRACO
Eng Process Fee Ord 176,300 Cleared 9/12/2023 CHRISTINA BRACO
Sewer availability Cleared 9/12/2023 CHRISTINA BRACO
Low Impact Development (LID) Cleared 12/29/2023 MELINEH AGHAKHABIAN
Roof/Waste drainage to street Cleared 1/5/2024 AMBER CAMPBELL
BHO/Hillside ordinance Cleared 2/21/2024 ALBERT TAM
GPI Written Notices Cleared 3/5/2024 SUNMIN LEE
Grading Pre-Inspection Cleared 3/5/2024 SUNMIN LEE
Highway dedication Cleared 3/5/2024 ALBERT TAM

Contact Information

Contractor Yakov Design & Build; Lic. No.: 1067993-B       ,
Engineer Garciamontes,, Gerardo; Lic. No.: L9195 517 E WILSON AVENUE, STE. 102      GLENDALE, CA 91206
Engineer Sivushenka,, Mikita; Lic. No.: C87698 22814 DOLOROSA ST      WOODLAND HILLS, CA 91367

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/1/2025 Corrections Issued BRENDAN MORELLI
Deputy Drilled-In Anchors 5/2/2025 Conditional Approval DAVID WILLIAMS
Excavation/Setback/Form/Re-Bar 5/2/2025 Approved DAVID WILLIAMS
BUILDING-Rough-Frame 5/7/2025 Partial Approval DAVID WILLIAMS
MERV13>=Rough 5/7/2025 Approved DAVID WILLIAMS
Verify Sprinkler Sign Off 5/7/2025 Not Ready for Inspection DAVID WILLIAMS
Floor/Roof Diaphrgm/Shear Wall 5/12/2025 Partial Approval DAVID WILLIAMS
PLUMBING-Rough 5/12/2025 Not Ready for Inspection DAVID WILLIAMS
PLUMBING-Rough 5/15/2025 Partial Approval DAVID WILLIAMS
Floor/Roof Diaphrgm/Shear Wall 5/27/2025 Approved DAVID WILLIAMS
Floor/Roof Diaphrgm/Shear Wall 6/26/2025 Partial Approval REGINA MENDEZ
BUILDING-Rough-Frame 8/26/2025 Not Ready for Inspection DAVID WILLIAMS
ELECTRICAL-Rough 8/26/2025 Not Ready for Inspection DAVID WILLIAMS
Gas Test 8/26/2025 Approved DAVID WILLIAMS
HVAC-Rough 8/26/2025 Approved DAVID WILLIAMS
PLUMBING-Rough 8/26/2025 Approved DAVID WILLIAMS
Shower Pan 8/26/2025 Approved DAVID WILLIAMS
Verify Sprinkler Sign Off 8/26/2025 Not Ready for Inspection DAVID WILLIAMS
ELECTRICAL-Rough 9/3/2025 Approved ALIZAH MAYAGOITIA
Verify Sprinkler Sign Off 9/3/2025 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 9/16/2025 Approved DAVID WILLIAMS
Drywall Nailing 9/16/2025 Not Ready for Inspection DAVID WILLIAMS
Final 9/16/2025 Not Ready for Inspection DAVID WILLIAMS
Footing/Foundation/Slab 9/16/2025 Approved DAVID WILLIAMS
MERV13>=Final 9/16/2025 Not Ready for Inspection DAVID WILLIAMS
SGSOV-Seismic Gas S/O Valve 9/16/2025 SGSOV Not Ready DAVID WILLIAMS
Smoke Detectors 9/16/2025 Not Ready for Inspection DAVID WILLIAMS
Wood Frame 9/16/2025 Approved DAVID WILLIAMS
Insulation 10/2/2025 Approved DAVID WILLIAMS
Interior/Exterior Lathing 10/2/2025 Approved DAVID WILLIAMS
Drywall Nailing 12/3/2025 Approved RONNIE MEDINA