4229 S CAMPBELL DR 90066
Certificate Information: 4229 S CAMPBELL DR 90066
- Application / Permit
- 23014-10000-02910
- Plan Check / Job No.
- B23LA13429
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION AND REMODEL FOR EXISTING 1 STORY SFD PER ENGINEER DESIGN.
- Permit Issued
- Issued on 8/24/2023
- Issuing Office
- Current Status
- CofO Issued on 1/22/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/20/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/27/2023 | AUNG SOE |
| Building Plans Picked Up | 8/3/2023 | APPLICANT |
| Corrections Issued | 8/16/2023 | AUNG SOE |
| Applicant returned to address corrections | 8/22/2023 | DANIEL SANJUAN |
| Plan Check Approved | 8/24/2023 | MICHAEL LANZONE |
| Issued | 8/24/2023 | APPLICANT |
| CofO in Progress | 1/19/2024 | JESUS RODRIGUEZ |
| Permit Finaled | 1/22/2024 | DANIEL ORRANTE |
| CofO Issued | 1/22/2024 | DANIEL ORRANTE |
| Permit Finaled | 1/22/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/22/2023 | ANTHONY MAINEZ |
| Hold | Cleared | 8/22/2023 | JESSICA WATSON |
| Roof/Waste drainage to street | Cleared | 8/22/2023 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 8/22/2023 | ANTHONY MAINEZ |
| Specific Plan | Cleared | 8/23/2023 | PEDRO AYALA |
| ZA Case | Cleared | 8/24/2023 | GEORGIA SMITH |
Contact Information
| Contractor | Bayview Construction Inc; Lic. No.: 667400-B | 2701 11TH ST SANTA MONICA, CA 90405 |
| Engineer | Jalalpour,, Mohammad; Lic. No.: S6696 | 152 DEERFIELD AVE IRVINE, CA 92606 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/31/2023 | Conditional Approval | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 9/1/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 9/5/2023 | Approved | JESUS RODRIGUEZ |
| Underground Mechanical | 9/5/2023 | Partial Approval | JESUS RODRIGUEZ |
| Wood Frame | 9/14/2023 | Partial Approval | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2023 | Approved | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 10/12/2023 | Partial Approval | JESUS RODRIGUEZ |
| Wood Frame | 10/12/2023 | Partial Approval | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 10/24/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 10/24/2023 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 10/24/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| HVAC-Rough | 10/24/2023 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 10/24/2023 | Approved | JESUS RODRIGUEZ |
| Wood Frame | 10/24/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 10/31/2023 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 11/3/2023 | Approved | HERBERT GIRON |
| ELECTRICAL-Rough | 11/3/2023 | Conditional Approval | HERBERT GIRON |
| Green Building Rough | 11/3/2023 | Approved | HERBERT GIRON |
| Insulation | 11/3/2023 | Approved | HERBERT GIRON |
| Shower Pan | 11/3/2023 | Approved | HERBERT GIRON |
| Shower Pan | 11/6/2023 | Partial Inspection | TEMISTOCLES CAAL |
| Drywall Nailing | 11/8/2023 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 11/8/2023 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 12/28/2023 | Approved | TEMISTOCLES CAAL |
| HVAC-Final | 12/28/2023 | Approved | TEMISTOCLES CAAL |
| PLUMBING-Final | 12/28/2023 | Approved | TEMISTOCLES CAAL |
| Service/Power Release | 1/4/2024 | Not Ready for Inspection | TEMISTOCLES CAAL |
| Final | 1/18/2024 | OK to Issue CofO | JESUS RODRIGUEZ |
| Green Building Final | 1/18/2024 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 1/18/2024 | SGSOV Approved | JESUS RODRIGUEZ |
| Service/Power Release | 1/18/2024 | Approved | JESUS RODRIGUEZ |
| Smoke Detectors | 1/18/2024 | Approved | JESUS RODRIGUEZ |