2707 S OVERLAND AVE 90064

Certificate Information: 2707 S OVERLAND AVE 90064

Application / Permit
23014-10000-02881
Plan Check / Job No.
B23LA13284
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan***PROPOSED MAJOR REMODEL AND ADDITION TO SINGLE FAMILY DWELLING; FIRE SPRINKLER REQUIRED
Permit Issued
Issued on 1/25/2024
Issuing Office
Current Status
CofO Issued on 2/1/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/19/2023 APPLICANT
Assigned to Plan Check Engineer 7/20/2023 SINA KHOSRAVI
Corrections Issued 8/2/2023 SINA KHOSRAVI
Quality Review Completed 8/10/2023 YOUNG KIM
Applicant returned to address corrections 9/12/2023 SINA KHOSRAVI
Applicant returned to address corrections 10/16/2023 SINA KHOSRAVI
Plan Check Approved 1/17/2024 SINA KHOSRAVI
Plan Check Approved 1/24/2024 SINA KHOSRAVI
Issued 1/25/2024 APPLICANT
CofO in Progress 1/15/2025 MICHAEL PELHAM
CofO Issued 2/1/2025 RICHARD STEINBACH
Permit Finaled 2/1/2025 RICHARD STEINBACH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/31/2023 DARIN LAM
Grading Pre-Inspection Cleared 9/6/2023 VASIL MIHALEV
Specific Plan Cleared 9/12/2023 JAZMIN ROQUE
ZI Cleared 9/12/2023 JAZMIN ROQUE
Low Impact Development (LID) Cleared 10/13/2023 MELINEH AGHAKHABIAN
GPI Written Notices Cleared 10/16/2023 SINA KHOSRAVI
Roof/Waste drainage to street Cleared 10/16/2023 ANTHONY MAINEZ
Flood clearance Cleared 12/12/2023 MIGUEL RODRIGUEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Shahbander,, Mohamad Nabil; Lic. No.: C61250 2030 E 4TH ST D-209      SANTA ANA, CA 92705

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/29/2024 No Access for Inspection STEPHANIE SWANSON
Pre-Inspection 1/30/2024 Partial Inspection JESUS PINEDA
Pre-Inspection 2/1/2024 Partial Inspection JESUS PINEDA
Special/Order Compliance 2/1/2024 Partial Inspection MICHAEL PELHAM
Excavation/Setback/Form/Re-Bar 4/15/2024 Partial Inspection JESUS PINEDA
BUILDING-Rough-Frame 5/15/2024 Partial Approval SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 5/15/2024 Partial Approval SEAN HAUPT
PLUMBING-Rough 5/15/2024 Corrections Issued SEAN HAUPT
PLUMBING-Rough 5/16/2024 Partial Inspection KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 5/17/2024 Partial Approval KENNETH NAGLE
PLUMBING-Rough 5/17/2024 Partial Inspection KENNETH NAGLE
Deputy Wood Construction 6/5/2024 Conditional Approval JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 6/11/2024 Corrections Issued JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 7/24/2024 Approved JESUS PINEDA
PLUMBING-Rough 7/24/2024 Approved JESUS PINEDA
ELECTRICAL-Rough 7/31/2024 Approved JESUS PINEDA
HVAC-Rough 7/31/2024 Approved JESUS PINEDA
Interior/Exterior Lathing 7/31/2024 Partial Approval JESUS PINEDA
Underground Mechanical 7/31/2024 Approved JESUS PINEDA
BUILDING-Rough-Frame 8/8/2024 Partial Approval STEPHANIE SWANSON
Insulation 8/14/2024 Approved DANIEL VERA
Green Building Rough 8/26/2024 Not Ready for Inspection DANIEL VERA
Shower Pan 8/26/2024 Approved DANIEL VERA
Drywall Nailing 8/29/2024 Approved ARAM AVEDISIAN
Green Building Rough 8/29/2024 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 9/9/2024 Approved TEMISTOCLES CAAL
Enclosure/Fence 10/18/2024 Not Ready for Inspection KIRK SANDERS
Final 10/18/2024 Corrections Issued KIRK SANDERS
Underground Mechanical 10/18/2024 Conditional Approval KIRK SANDERS
ELECTRICAL-Final 12/2/2024 Conditional Approval DANIEL VERA
Special/Order Compliance 12/2/2024 Approved DANIEL VERA
BUILDING-Rough-Frame 12/23/2024 Conditional Approval DANIEL VERA
Final 12/23/2024 Corrections Issued DANIEL VERA
Footing/Foundation/Slab 12/23/2024 Approved DANIEL VERA
Green Building Final 12/23/2024 Not Ready for Inspection DANIEL VERA
SGSOV-Seismic Gas S/O Valve 12/23/2024 SGSOV Not Required DANIEL VERA
Smoke Detectors 12/23/2024 Approved DANIEL VERA
BUILDING-Rough-Frame 1/8/2025 Approved MICHAEL PELHAM
FLOOD-Proofing Certificate 1/8/2025 Approved MICHAEL PELHAM
Final 1/8/2025 Corrections Issued MICHAEL PELHAM
Green Building Final 1/8/2025 Approved MICHAEL PELHAM
Final 1/15/2025 OK to Issue CofO MICHAEL PELHAM