1732 N GARDNER ST 90046

Certificate Information: 1732 N GARDNER ST 90046

Application / Permit
23014-10000-02876
Plan Check / Job No.
B23LA13283
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan CONVERT EXISTING DETACHED GARAGE TO ADU WITH ADDITION PER ORDINANCE see comment
Permit Issued
Issued on 9/6/2023
Issuing Office
Current Status
Issued on 9/6/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/18/2023 APPLICANT
Assigned to Plan Check Engineer 7/27/2023 MINA HABILI
Corrections Issued 7/28/2023 MINA HABILI
Applicant returned to address corrections 8/23/2023 MINA HABILI
Plan Check Approved 9/6/2023 JOSEPH RAFOLS
Issued 9/6/2023 APPLICANT

Permit Application Clearance Information

Address approval Cleared 7/31/2023 NEIL TUANO
Roof/Waste drainage to street Cleared 7/31/2023 NEIL TUANO
Sewer availability Cleared 7/31/2023 NEIL TUANO
Eng Process Fee Ord 176,300 Cleared 8/1/2023 NEIL TUANO
Grading Pre-Inspection Cleared 8/7/2023 SERGIO VALENZUELA

Contact Information

Contractor Owner-Builder       ,
Engineer Kashe,, Andrew; Lic. No.: C94117 984 SILVERTIP DR      DIAMOND BAR, CA 91765

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/8/2024 Partial Approval BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 7/15/2024 Partial Approval BRIAN SULLIVAN
Footing/Foundation/Slab 8/5/2024 Partial Approval BRIAN SULLIVAN
Deputy Drilled-In Anchors 8/6/2024 Conditional Approval RAUL BARAJAS
Deputy Drilled-In Anchors 8/8/2024 Approved BRIAN SULLIVAN
Footing/Foundation/Slab 8/8/2024 Partial Approval BRIAN SULLIVAN
PLUMBING-Rough 8/14/2024 Partial Approval BRENDAN MORELLI
Footing/Foundation/Slab 8/16/2024 Approved BRIAN SULLIVAN
Deputy Drilled-In Anchors 10/18/2024 Conditional Approval BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 2/11/2025 Partial Approval CRAIG VAUGHAN
ELECTRICAL-Rough 3/5/2025 Approved ROY SPAULDING
PLUMBING-Rough 3/5/2025 Approved ROY SPAULDING
Interior/Exterior Lathing 4/1/2025 Approved ROY SPAULDING
BUILDING-Rough-Frame 4/24/2025 Approved ROY SPAULDING
Green Building Rough 4/24/2025 Approved ROY SPAULDING
HVAC-Rough 4/24/2025 Approved ROY SPAULDING
Insulation 5/28/2025 Approved ROY SPAULDING
Drywall Nailing 6/12/2025 Approved BRENDAN MORELLI
Shower Pan 6/25/2025 Approved JOSH MEISTER
Interior/Exterior Lathing 6/30/2025 Approved ROY SPAULDING