1732 N GARDNER ST 90046
Certificate Information: 1732 N GARDNER ST 90046
- Application / Permit
- 23014-10000-02876
- Plan Check / Job No.
- B23LA13283
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan CONVERT EXISTING DETACHED GARAGE TO ADU WITH ADDITION PER ORDINANCE see comment
- Permit Issued
- Issued on 9/6/2023
- Issuing Office
- Current Status
- Issued on 9/6/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/18/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/27/2023 | MINA HABILI |
| Corrections Issued | 7/28/2023 | MINA HABILI |
| Applicant returned to address corrections | 8/23/2023 | MINA HABILI |
| Plan Check Approved | 9/6/2023 | JOSEPH RAFOLS |
| Issued | 9/6/2023 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 7/31/2023 | NEIL TUANO |
| Roof/Waste drainage to street | Cleared | 7/31/2023 | NEIL TUANO |
| Sewer availability | Cleared | 7/31/2023 | NEIL TUANO |
| Eng Process Fee Ord 176,300 | Cleared | 8/1/2023 | NEIL TUANO |
| Grading Pre-Inspection | Cleared | 8/7/2023 | SERGIO VALENZUELA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Kashe,, Andrew; Lic. No.: C94117 | 984 SILVERTIP DR DIAMOND BAR, CA 91765 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/8/2024 | Partial Approval | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 7/15/2024 | Partial Approval | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 8/5/2024 | Partial Approval | BRIAN SULLIVAN |
| Deputy Drilled-In Anchors | 8/6/2024 | Conditional Approval | RAUL BARAJAS |
| Deputy Drilled-In Anchors | 8/8/2024 | Approved | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 8/8/2024 | Partial Approval | BRIAN SULLIVAN |
| PLUMBING-Rough | 8/14/2024 | Partial Approval | BRENDAN MORELLI |
| Footing/Foundation/Slab | 8/16/2024 | Approved | BRIAN SULLIVAN |
| Deputy Drilled-In Anchors | 10/18/2024 | Conditional Approval | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/11/2025 | Partial Approval | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 3/5/2025 | Approved | ROY SPAULDING |
| PLUMBING-Rough | 3/5/2025 | Approved | ROY SPAULDING |
| Interior/Exterior Lathing | 4/1/2025 | Approved | ROY SPAULDING |
| BUILDING-Rough-Frame | 4/24/2025 | Approved | ROY SPAULDING |
| Green Building Rough | 4/24/2025 | Approved | ROY SPAULDING |
| HVAC-Rough | 4/24/2025 | Approved | ROY SPAULDING |
| Insulation | 5/28/2025 | Approved | ROY SPAULDING |
| Drywall Nailing | 6/12/2025 | Approved | BRENDAN MORELLI |
| Shower Pan | 6/25/2025 | Approved | JOSH MEISTER |
| Interior/Exterior Lathing | 6/30/2025 | Approved | ROY SPAULDING |