6376 W 82ND ST 90045
Certificate Information: 6376 W 82ND ST 90045
- Application / Permit
- 23014-10000-02873
- Plan Check / Job No.
- B23LA13273
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition to add Master Bedroom and expand family room
- Permit Issued
- Issued on 1/19/2024
- Issuing Office
- Current Status
- CofO Issued on 3/21/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/18/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/20/2023 | MARCELA FRANQUEZ |
| Corrections Issued | 7/22/2023 | MARCELA FRANQUEZ |
| Quality Review Completed | 8/3/2023 | TU HUA |
| Plan Check Approved | 1/19/2024 | HERNAN ARREOLA |
| Issued | 1/19/2024 | APPLICANT |
| CofO in Progress | 2/27/2025 | ANDREW BEELI |
| Permit Finaled | 3/21/2025 | CLAUDIO MORENO |
| CofO Issued | 3/21/2025 | CLAUDIO MORENO |
| Permit Finaled | 3/21/2025 | CLAUDIO MORENO |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/20/2023 | DARIN LAM |
| Sewer availability | Cleared | 12/20/2023 | DARIN LAM |
| Low Impact Development (LID) | Cleared | 1/17/2024 | SAMUEL LINN |
| Roof/Waste drainage to street | Cleared | 1/18/2024 | DARIN LAM |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| ROBERT GARTH, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN MATTILLO, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PEDRO RIVERA, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| EUSEBIO GUZMAN, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PAUL REECE, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| ANDREW BEELI, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/25/2024 | Corrections Issued | ANDREW BEELI |
| Footing/Foundation/Slab | 2/13/2024 | Approved | ANDREW BEELI |
| BUILDING-Rough-Frame | 2/28/2024 | Not Ready for Inspection | ANDREW BEELI |
| Green Building Rough | 2/28/2024 | Not Ready for Inspection | ANDREW BEELI |
| SGSOV-Seismic Gas S/O Valve | 2/28/2024 | SGSOV Not Ready | ANDREW BEELI |
| Underground Mechanical | 3/13/2024 | Not Ready for Inspection | ANDREW BEELI |
| PLUMBING-Rough | 3/19/2024 | Corrections Issued | ANDREW BEELI |
| Underground Mechanical | 3/19/2024 | Not Ready for Inspection | ANDREW BEELI |
| Insulation | 3/20/2024 | Not Ready for Inspection | ANDREW BEELI |
| Sewer | 3/20/2024 | Approved | ANDREW BEELI |
| Underground Mechanical | 3/20/2024 | Approved | ANDREW BEELI |
| PLUMBING-Rough | 3/22/2024 | Partial Approval | ANDREW BEELI |
| BUILDING-Rough-Frame | 4/25/2024 | Not Ready for Inspection | ANDREW BEELI |
| Green Building Rough | 4/25/2024 | Not Ready for Inspection | ANDREW BEELI |
| PLUMBING-Rough | 4/25/2024 | Not Ready for Inspection | ANDREW BEELI |
| Underground Mechanical | 4/25/2024 | Approved | ANDREW BEELI |
| Interior/Exterior Lathing | 5/1/2024 | Corrections Issued | ANDREW BEELI |
| Wood Frame | 5/1/2024 | Not Ready for Inspection | ANDREW BEELI |
| ELECTRICAL-Rough | 5/21/2024 | Not Ready for Inspection | JOHN MATTILLO |
| Wood Frame | 5/21/2024 | Corrections Issued | JOHN MATTILLO |
| BUILDING-Rough-Frame | 5/23/2024 | Corrections Issued | JOHN MATTILLO |
| ELECTRICAL-Rough | 5/23/2024 | Not Ready for Inspection | JOHN MATTILLO |
| Green Building Rough | 5/23/2024 | Not Ready for Inspection | JOHN MATTILLO |
| PLUMBING-Rough | 5/23/2024 | Not Ready for Inspection | JOHN MATTILLO |
| BUILDING-Rough-Frame | 5/29/2024 | Partial Approval | JOHN MATTILLO |
| Green Building Rough | 5/29/2024 | Not Ready for Inspection | JOHN MATTILLO |
| ELECTRICAL-Rough | 5/30/2024 | Corrections Issued | JOHN MATTILLO |
| PLUMBING-Rough | 5/30/2024 | Corrections Issued | JOHN MATTILLO |
| BUILDING-Rough-Frame | 6/10/2024 | Not Ready for Inspection | ANDREW BEELI |
| ELECTRICAL-Rough | 6/10/2024 | Corrections Issued | ANDREW BEELI |
| Green Building Rough | 6/10/2024 | Approved | ANDREW BEELI |
| HVAC-Rough | 6/10/2024 | Not Ready for Inspection | ANDREW BEELI |
| PLUMBING-Rough | 6/10/2024 | Corrections Issued | ANDREW BEELI |
| ELECTRICAL-Rough | 6/11/2024 | Approved | ANDREW BEELI |
| PLUMBING-Rough | 6/11/2024 | Approved | ANDREW BEELI |
| BUILDING-Rough-Frame | 6/20/2024 | Approved | ANDREW BEELI |
| ELECTRICAL-Rough | 6/20/2024 | Approved | ANDREW BEELI |
| PLUMBING-Rough | 6/20/2024 | Approved | ANDREW BEELI |
| Drywall Nailing | 6/28/2024 | Not Ready for Inspection | JOHN MATTILLO |
| Drywall Nailing | 7/2/2024 | Approved | JOHN MATTILLO |
| Interior/Exterior Lathing | 7/9/2024 | Approved | ANDREW BEELI |
| PLUMBING-Rough | 7/9/2024 | Approved | ANDREW BEELI |
| Service/Power Release | 7/31/2024 | Approved | ANDREW BEELI |
| Final | 9/6/2024 | Not Ready for Inspection | ANDREW BEELI |
| Green Building Final | 9/6/2024 | Corrections Issued | ANDREW BEELI |
| SGSOV-Seismic Gas S/O Valve | 9/6/2024 | SGSOV Not Ready | ANDREW BEELI |
| Smoke Detectors | 9/6/2024 | Approved | ANDREW BEELI |
| Final | 2/27/2025 | OK to Issue CofO | ANDREW BEELI |
| Green Building Final | 2/27/2025 | Approved | ANDREW BEELI |
| SGSOV-Seismic Gas S/O Valve | 2/27/2025 | SGSOV Approved | ANDREW BEELI |