1011 N HARTZELL ST 90272

Certificate Information: 1011 N HARTZELL ST 90272

Application / Permit
23014-10000-02871
Plan Check / Job No.
B23LA13266
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
major remodel and addition of 2nd floor to (e) single story single family dwelling NFPA 13D sprinklered throughout R3/U Occupancy
Permit Issued
Issued on 9/25/2023
Issuing Office
West Los Angeles
Current Status
CofO Issued on 12/3/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/18/2023 APPLICANT
Assigned to Plan Check Engineer 7/20/2023 KELVIN CHUONG
Corrections Issued 7/24/2023 KELVIN CHUONG
Quality Review Completed 7/25/2023 KEN GILL
Building Plans Picked Up 7/26/2023 APPLICANT
Applicant returned to address corrections 8/24/2023 KELVIN CHUONG
Applicant returned to address corrections 9/7/2023 KELVIN CHUONG
Plan Check Approved 9/14/2023 KELVIN CHUONG
Issued 9/25/2023 APPLICANT
CofO in Progress 11/27/2024 JESUS RODRIGUEZ
Permit Finaled 12/3/2024 RICHARD STEINBACH
CofO Issued 12/3/2024 RICHARD STEINBACH
Permit Finaled 12/3/2024 RICHARD STEINBACH

Permit Application Clearance Information

Trees in Parkway Cleared 8/8/2023 ADALBERTO VERA
Low Impact Development (LID) Cleared 8/17/2023 SAMUEL LINN
Hydrant and Access approval Cleared 8/18/2023 GILBERT URREA
Eng Process Fee Ord 176,300 Cleared 8/23/2023 DARIN LAM
Permit Cleared 8/23/2023 DARIN LAM
Roof/Waste drainage to street Cleared 8/23/2023 DARIN LAM
Sewer availability Cleared 8/23/2023 DARIN LAM
GPI Written Notices Cleared 9/14/2023 KELVIN CHUONG
Grading Pre-Inspection Cleared 9/14/2023 KELVIN CHUONG

Contact Information

Contractor Zepeda General Building; Lic. No.: 1028796-B 9525 HUNT AVE      SOUTH GATE W, CA 90280

Inspector Information

TEMISTOCLES CAAL, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI
JESUS PINEDA, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/14/2023 Partial Approval HERBERT GIRON
Footing/Foundation/Slab 11/30/2023 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 12/1/2023 Corrections Issued ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 12/27/2023 Conditional Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 1/29/2024 Partial Approval MEL KHACHATOURIAN
HVAC-Rough 3/12/2024 Corrections Issued BOBBY KEY
PLUMBING-Rough 3/12/2024 Partial Approval BOBBY KEY
ELECTRICAL-Rough 3/14/2024 Corrections Issued ARAM AVEDISIAN
HVAC-Rough 3/14/2024 Approved ARAM AVEDISIAN
ELECTRICAL-Rough 3/26/2024 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 3/28/2024 Partial Approval ARAM AVEDISIAN
Interior/Exterior Lathing 4/10/2024 Partial Approval ARAM AVEDISIAN
BUILDING-Rough-Frame 4/16/2024 Approved KENNETH NAGLE
Green Building Rough 4/16/2024 Approved KENNETH NAGLE
Verify Sprinkler Sign Off 4/16/2024 Approved KENNETH NAGLE
Insulation 5/9/2024 Approved KENNETH NAGLE
Drywall Nailing 5/17/2024 Approved EVAN COOPER
Interior/Exterior Lathing 6/20/2024 Approved EVAN COOPER
Shower Pan 6/20/2024 Approved EVAN COOPER
ELECTRICAL-Final 11/22/2024 Approved JESUS RODRIGUEZ
HVAC-Final 11/22/2024 Approved JESUS RODRIGUEZ
PLUMBING-Final 11/22/2024 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 11/22/2024 SGSOV Approved JESUS RODRIGUEZ
Service/Power Release 11/22/2024 Approved JESUS RODRIGUEZ
Final 11/26/2024 OK to Issue CofO JESUS RODRIGUEZ
Gas Test 11/26/2024 Approved JESUS RODRIGUEZ
Green Building Final 11/26/2024 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 11/26/2024 SGSOV Approved JESUS RODRIGUEZ
Smoke Detectors 11/26/2024 Approved JESUS RODRIGUEZ