890-892 N BUNDY DR 90049

Certificate Information: 890-892 N BUNDY DR 90049

Application / Permit
23014-10000-02869
Plan Check / Job No.
B23LA13255
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL AND ADDITION TO (E) SFD. NEW ADU ADDITION. ATTACHED ADU PER LAMC 12.22 A.33 (c) and (e). ADU WILL BE SPRINKLERED WITH NFPA 13D. **See comments. 1 OF 2
Permit Issued
Issued on 9/19/2024
Issuing Office
Metro
Current Status
Issued on 9/19/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/2/2023 APPLICANT
Assigned to Plan Check Engineer 8/17/2023 ADRIANA LOPEZ
Corrections Issued 8/30/2023 ADRIANA LOPEZ
Quality Review Completed 9/1/2023 KEN GILL
Building Plans Picked Up 9/14/2023 APPLICANT
Applicant returned to address corrections 11/27/2023 ADRIANA LOPEZ
Applicant returned to address corrections 1/11/2024 ADRIANA LOPEZ
Applicant returned to address corrections 1/29/2024 ADRIANA LOPEZ
Plan Check Approved 7/11/2024 ADRIANA LOPEZ
No Progress 7/15/2024 ADRIANA LOPEZ
Plan Check Approved 7/15/2024 ADRIANA LOPEZ
Issued 9/19/2024 APPLICANT

Permit Application Clearance Information

Miscellaneous Cleared 1/10/2024 DAVID URITA
Miscellaneous Cleared 1/10/2024 DAVID URITA
Address approval Cleared 4/17/2024 DINAH GARIN
BHO/Hillside ordinance Cleared 4/17/2024 DINAH GARIN
BHO/Hillside ordinance Cleared 4/17/2024 DINAH GARIN
BHO/Hillside ordinance Cleared 4/17/2024 DINAH GARIN
BHO/Hillside ordinance Cleared 4/17/2024 DINAH GARIN
BHO/Hillside ordinance Cleared 4/17/2024 DINAH GARIN
Low Impact Development (LID) Cleared 6/25/2024 MITESH PATEL
Eng Process Fee Ord 176,300 Cleared 6/26/2024 DIANA RENTERIA
Sewer availability Cleared 6/26/2024 DIANA RENTERIA
Roof/Waste drainage to street Cleared 6/27/2024 ANDREA SAINT-ANTONIN
Excavation more than 5-ft deep Cleared 7/2/2024 CALOSHA APPROVED
GPI Written Notices Cleared 7/11/2024 ADRIANA LOPEZ
Grading Pre-Inspection Cleared 7/11/2024 ADRIANA LOPEZ

Contact Information

Contractor Fort Multifamily Inc; Lic. No.: 1097435-B 2684 LACY ST APT 202      LOS ANGELES, CA 90031
Engineer Liu,, Haiyan Harry; Lic. No.: C81463 10855 BECKFORD AVE      NORTHRIDGE, CA 91326
Engineer Medina,, Ferdinand Casaclang; Lic. No.: C88007 1051 S HOLT AVE APT F      LOS ANGELES, CA 90035
Geologist Swiatek,, Mark; Lic. No.: EG1781 24203 VALLEY ST      NEWHALL, CA 91321

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/6/2024 Approved CARLOS MATAMOROS
Piling/Pier/Caisson 11/20/2024 Partial Approval CARLOS MATAMOROS
Deputy Reinf. Concrete 11/25/2024 Conditional Approval CARLOS MATAMOROS
Piling/Pier/Caisson 11/25/2024 Approved CARLOS MATAMOROS
Footing/Foundation/Slab 1/6/2025 Corrections Issued CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 1/10/2025 Corrections Issued CARLOS MATAMOROS
Footing/Foundation/Slab 1/10/2025 Not Ready for Inspection CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 1/27/2025 Corrections Issued CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 1/27/2025 Not Ready for Inspection CARLOS MATAMOROS
Footing/Foundation/Slab 1/27/2025 Not Ready for Inspection CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 2/4/2025 Corrections Issued CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 2/19/2025 Not Ready for Inspection CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 2/20/2025 Not Ready for Inspection CARLOS MATAMOROS
Footing/Foundation/Slab 2/20/2025 Not Ready for Inspection CARLOS MATAMOROS
Deputy Reinf. Concrete 3/4/2025 Conditional Approval CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 3/4/2025 Corrections Issued CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 3/10/2025 Partial Approval CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 3/10/2025 Conditional Approval CARLOS MATAMOROS
Footing/Foundation/Slab 3/27/2025 Approved CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 4/14/2025 Partial Approval STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 6/25/2025 Corrections Issued MEL KHACHATOURIAN
Drywall Nailing 7/30/2025 Not Ready for Inspection MICHAEL ALLEN
Green Building Rough 7/30/2025 Not Ready for Inspection MICHAEL ALLEN
HVAC-Rough 7/30/2025 Not Ready for Inspection MICHAEL ALLEN
PLUMBING-Rough 7/30/2025 Corrections Issued MICHAEL ALLEN
Verify Sprinkler Sign Off 8/12/2025 Corrections Issued CARLOS MATAMOROS
ELECTRICAL-Rough 8/27/2025 Approved CARLOS MATAMOROS
FLOOD-Proofing Certificate 9/26/2025 Approved CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 9/26/2025 Conditional Approval CARLOS MATAMOROS
PLUMBING-Rough 9/26/2025 Approved CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 10/20/2025 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 11/13/2025 Approved CARLOS MATAMOROS
BUILDING-Rough-Frame 1/16/2026 Approved EVAN COOPER
Green Building Rough 1/16/2026 Approved EVAN COOPER
Verify Sprinkler Sign Off 1/16/2026 Approved EVAN COOPER
Insulation 1/23/2026 Approved EVAN COOPER
Drywall Nailing 2/6/2026 Approved EVAN COOPER
Shower Pan 3/19/2026 Corrections Issued CHRISTOPHER WILSON
Shower Pan 4/1/2026 Approved CHRISTOPHER WILSON
Interior/Exterior Lathing 4/10/2026 Partial Approval EVAN COOPER
Service/Power Release 4/10/2026 Approved EVAN COOPER