890-892 N BUNDY DR 90049
Certificate Information: 890-892 N BUNDY DR 90049
- Application / Permit
- 23014-10000-02869
- Plan Check / Job No.
- B23LA13255
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL AND ADDITION TO (E) SFD. NEW ADU ADDITION. ATTACHED ADU PER LAMC 12.22 A.33 (c) and (e). ADU WILL BE SPRINKLERED WITH NFPA 13D. **See comments. 1 OF 2
- Permit Issued
- Issued on 9/19/2024
- Issuing Office
- Metro
- Current Status
- Issued on 9/19/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/2/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/17/2023 | ADRIANA LOPEZ |
| Corrections Issued | 8/30/2023 | ADRIANA LOPEZ |
| Quality Review Completed | 9/1/2023 | KEN GILL |
| Building Plans Picked Up | 9/14/2023 | APPLICANT |
| Applicant returned to address corrections | 11/27/2023 | ADRIANA LOPEZ |
| Applicant returned to address corrections | 1/11/2024 | ADRIANA LOPEZ |
| Applicant returned to address corrections | 1/29/2024 | ADRIANA LOPEZ |
| Plan Check Approved | 7/11/2024 | ADRIANA LOPEZ |
| No Progress | 7/15/2024 | ADRIANA LOPEZ |
| Plan Check Approved | 7/15/2024 | ADRIANA LOPEZ |
| Issued | 9/19/2024 | APPLICANT |
Permit Application Clearance Information
| Miscellaneous | Cleared | 1/10/2024 | DAVID URITA |
| Miscellaneous | Cleared | 1/10/2024 | DAVID URITA |
| Address approval | Cleared | 4/17/2024 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 4/17/2024 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 4/17/2024 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 4/17/2024 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 4/17/2024 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 4/17/2024 | DINAH GARIN |
| Low Impact Development (LID) | Cleared | 6/25/2024 | MITESH PATEL |
| Eng Process Fee Ord 176,300 | Cleared | 6/26/2024 | DIANA RENTERIA |
| Sewer availability | Cleared | 6/26/2024 | DIANA RENTERIA |
| Roof/Waste drainage to street | Cleared | 6/27/2024 | ANDREA SAINT-ANTONIN |
| Excavation more than 5-ft deep | Cleared | 7/2/2024 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 7/11/2024 | ADRIANA LOPEZ |
| Grading Pre-Inspection | Cleared | 7/11/2024 | ADRIANA LOPEZ |
Contact Information
| Contractor | Fort Multifamily Inc; Lic. No.: 1097435-B | 2684 LACY ST APT 202 LOS ANGELES, CA 90031 |
| Engineer | Liu,, Haiyan Harry; Lic. No.: C81463 | 10855 BECKFORD AVE NORTHRIDGE, CA 91326 |
| Engineer | Medina,, Ferdinand Casaclang; Lic. No.: C88007 | 1051 S HOLT AVE APT F LOS ANGELES, CA 90035 |
| Geologist | Swiatek,, Mark; Lic. No.: EG1781 | 24203 VALLEY ST NEWHALL, CA 91321 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/6/2024 | Approved | CARLOS MATAMOROS |
| Piling/Pier/Caisson | 11/20/2024 | Partial Approval | CARLOS MATAMOROS |
| Deputy Reinf. Concrete | 11/25/2024 | Conditional Approval | CARLOS MATAMOROS |
| Piling/Pier/Caisson | 11/25/2024 | Approved | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 1/6/2025 | Corrections Issued | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 1/10/2025 | Corrections Issued | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 1/10/2025 | Not Ready for Inspection | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 1/27/2025 | Corrections Issued | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 1/27/2025 | Not Ready for Inspection | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 1/27/2025 | Not Ready for Inspection | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 2/4/2025 | Corrections Issued | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 2/19/2025 | Not Ready for Inspection | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 2/20/2025 | Not Ready for Inspection | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 2/20/2025 | Not Ready for Inspection | CARLOS MATAMOROS |
| Deputy Reinf. Concrete | 3/4/2025 | Conditional Approval | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 3/4/2025 | Corrections Issued | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 3/10/2025 | Partial Approval | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 3/10/2025 | Conditional Approval | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 3/27/2025 | Approved | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 4/14/2025 | Partial Approval | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/25/2025 | Corrections Issued | MEL KHACHATOURIAN |
| Drywall Nailing | 7/30/2025 | Not Ready for Inspection | MICHAEL ALLEN |
| Green Building Rough | 7/30/2025 | Not Ready for Inspection | MICHAEL ALLEN |
| HVAC-Rough | 7/30/2025 | Not Ready for Inspection | MICHAEL ALLEN |
| PLUMBING-Rough | 7/30/2025 | Corrections Issued | MICHAEL ALLEN |
| Verify Sprinkler Sign Off | 8/12/2025 | Corrections Issued | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 8/27/2025 | Approved | CARLOS MATAMOROS |
| FLOOD-Proofing Certificate | 9/26/2025 | Approved | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 9/26/2025 | Conditional Approval | CARLOS MATAMOROS |
| PLUMBING-Rough | 9/26/2025 | Approved | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 10/20/2025 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 11/13/2025 | Approved | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 1/16/2026 | Approved | EVAN COOPER |
| Green Building Rough | 1/16/2026 | Approved | EVAN COOPER |
| Verify Sprinkler Sign Off | 1/16/2026 | Approved | EVAN COOPER |
| Insulation | 1/23/2026 | Approved | EVAN COOPER |
| Drywall Nailing | 2/6/2026 | Approved | EVAN COOPER |
| Shower Pan | 3/19/2026 | Corrections Issued | CHRISTOPHER WILSON |
| Shower Pan | 4/1/2026 | Approved | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 4/10/2026 | Partial Approval | EVAN COOPER |
| Service/Power Release | 4/10/2026 | Approved | EVAN COOPER |