3468 W 71ST ST 90043
Certificate Information: 3468 W 71ST ST 90043
- Application / Permit
- 23014-10000-02823
- Plan Check / Job No.
- B23LA13079
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- eplan ePlan. Addition to existing 1-story single family dwelling (SFD) to create 5-unit 2-story apartment building.
- Permit Issued
- Issued on 12/19/2023
- Issuing Office
- Current Status
- CofO in Progress on 4/21/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/18/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/20/2023 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 7/28/2023 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 8/11/2023 | TU HUA |
| Plan Check Approved | 12/8/2023 | MAHNAZ NOURHASHEMI |
| Issued | 12/19/2023 | APPLICANT |
| CofO in Progress | 4/21/2026 | ALFREDO LOPEZ |
Permit Application Clearance Information
| Address approval | Cleared | 8/22/2023 | JEANIE LAM |
| Historic Resource Verification | Cleared | 8/23/2023 | MAX LODER |
| Eng Process Fee Ord 176,300 | Cleared | 8/28/2023 | JEANIE LAM |
| Sewer availability | Cleared | 8/28/2023 | JEANIE LAM |
| Redevelopment Project Area | Cleared | 9/12/2023 | YASMINE BASHIRI |
| Green Code | Cleared | 9/22/2023 | Rosendo Medina |
| DAS Clearance | Cleared | 9/26/2023 | Rosendo Medina |
| Low Impact Development (LID) | Cleared | 12/5/2023 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 12/6/2023 | JEANIE LAM |
Contact Information
| Architect | Poindexter,, John Roger; Lic. No.: NA9744 | , |
| Contractor | Choe Craig; Lic. No.: 867838-B | , |
| Engineer | Tzeng,, Charles Chau-Jyi; Lic. No.: NA34005 | , |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/5/2024 | Not Ready for Inspection | ALFREDO LOPEZ |
| Footing/Foundation/Slab | 3/18/2024 | Approved | DARRYL ARNOLD |
| FLOOD-Proofing Certificate | 5/6/2024 | Approved | DARRYL ARNOLD |
| Green Building Rough | 5/6/2024 | Approved | DARRYL ARNOLD |
| Wood Frame | 5/6/2024 | Conditional Approval | DARRYL ARNOLD |
| Interior/Exterior Lathing | 5/21/2024 | Not Ready for Inspection | DARRYL ARNOLD |
| Insulation | 7/3/2024 | Approved | ALFREDO LOPEZ |
| Drywall Nailing | 7/22/2024 | Conditional Approval | DARRYL ARNOLD |
| Interior/Exterior Lathing | 7/22/2024 | Conditional Approval | DARRYL ARNOLD |
| Green Building Final | 8/8/2024 | Conditional Approval | DARRYL ARNOLD |
| Pre-Inspection | 12/17/2024 | Partial Inspection | ALFREDO LOPEZ |
| Final | 3/11/2025 | OK to Issue CofO | ALFREDO LOPEZ |
| Green Building Final | 3/11/2025 | Approved | ALFREDO LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 3/11/2025 | SGSOV Approved | ALFREDO LOPEZ |
| Smoke Detectors | 3/11/2025 | Approved | ALFREDO LOPEZ |
| Wood Frame | 3/11/2025 | Approved | ALFREDO LOPEZ |