4366 N BAKMAN AVE 91602
Certificate Information: 4366 N BAKMAN AVE 91602
- Application / Permit
- 23014-10000-02814
- Plan Check / Job No.
- B23LA13043
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL AND ADDITION (435sqft) TO (E) 1-STORY SFD TO ADD MASTER BEDROOM WITH BATHROOM AND TRELLIS (327sqft) AT REAR
- Permit Issued
- Issued on 1/16/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/15/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/14/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/20/2023 | KHUONG TRUONG |
| Corrections Issued | 7/21/2023 | KHUONG TRUONG |
| Building Plans Picked Up | 7/28/2023 | APPLICANT |
| Applicant returned to address corrections | 9/1/2023 | FERNANDO FLORES |
| Applicant returned to address corrections | 12/22/2023 | MINA HABILI |
| Plan Check Approved | 1/8/2024 | KHUONG TRUONG |
| Issued | 1/16/2024 | APPLICANT |
| No Progress | 10/30/2024 | CHRISTOPHER ROJAS |
| CofO in Progress | 10/30/2024 | CHRISTOPHER ROJAS |
| CofO in Progress | 11/12/2024 | CHRISTOPHER ROJAS |
| CofO Issued | 11/15/2024 | DANIEL ORRANTE |
| Permit Finaled | 11/15/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 9/6/2023 | LEE GUILBEAUX |
| Sewer availability | Cleared | 9/6/2023 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 12/22/2023 | CHRISTINA BRACO |
Contact Information
| Contractor | Fleet Construction; Lic. No.: 868527-B | 4424 BEN AVENUE STUDIO CITY, CA 91607 |
| Engineer | Breaks,, Matthew Calvin; Lic. No.: S6028 | 5056 TUJUNGA AVE APT 17 NORTH HOLLYWOOD, CA 91601 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 2/15/2024 | Approved | CHRISTOPHE COCHRAN |
| Excavation/Setback/Form/Re-Bar | 2/29/2024 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 5/23/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 5/23/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Green Building Rough | 5/23/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| MERV13>=Rough | 5/23/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 5/23/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 5/30/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 5/30/2024 | Approved | CHRISTOPHER ROJAS |
| Green Building Rough | 5/30/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| MERV13>=Rough | 5/30/2024 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 5/30/2024 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 6/11/2024 | Partial Approval | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 6/11/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Green Building Rough | 6/11/2024 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 6/11/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Insulation | 6/18/2024 | Approved | CHRISTOPHER ROJAS |
| Drywall Nailing | 7/3/2024 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 7/30/2024 | Approved | CHRISTOPHER ROJAS |
| Shower Pan | 7/30/2024 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 10/23/2024 | Approved | CHRISTOPHER ROJAS |
| Final | 10/23/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Footing/Foundation/Slab | 10/23/2024 | Approved | CHRISTOPHER ROJAS |
| Green Building Final | 10/23/2024 | Approved | CHRISTOPHER ROJAS |
| MERV13>=Final | 10/23/2024 | Approved | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 10/23/2024 | SGSOV Approved | CHRISTOPHER ROJAS |
| Smoke Detectors | 10/23/2024 | Approved | CHRISTOPHER ROJAS |
| Final | 10/29/2024 | OK to Issue CofO | CHRISTOPHER ROJAS |
| Deputy Drilled-In Anchors | 10/30/2024 | Conditional Approval | JUAN VALENZUELA |