4366 N BAKMAN AVE 91602

Certificate Information: 4366 N BAKMAN AVE 91602

Application / Permit
23014-10000-02814
Plan Check / Job No.
B23LA13043
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL AND ADDITION (435sqft) TO (E) 1-STORY SFD TO ADD MASTER BEDROOM WITH BATHROOM AND TRELLIS (327sqft) AT REAR
Permit Issued
Issued on 1/16/2024
Issuing Office
Valley
Current Status
CofO Issued on 11/15/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/14/2023 APPLICANT
Assigned to Plan Check Engineer 7/20/2023 KHUONG TRUONG
Corrections Issued 7/21/2023 KHUONG TRUONG
Building Plans Picked Up 7/28/2023 APPLICANT
Applicant returned to address corrections 9/1/2023 FERNANDO FLORES
Applicant returned to address corrections 12/22/2023 MINA HABILI
Plan Check Approved 1/8/2024 KHUONG TRUONG
Issued 1/16/2024 APPLICANT
No Progress 10/30/2024 CHRISTOPHER ROJAS
CofO in Progress 10/30/2024 CHRISTOPHER ROJAS
CofO in Progress 11/12/2024 CHRISTOPHER ROJAS
CofO Issued 11/15/2024 DANIEL ORRANTE
Permit Finaled 11/15/2024 DANIEL ORRANTE

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 9/6/2023 LEE GUILBEAUX
Sewer availability Cleared 9/6/2023 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 12/22/2023 CHRISTINA BRACO

Contact Information

Contractor Fleet Construction; Lic. No.: 868527-B 4424 BEN AVENUE      STUDIO CITY, CA 91607
Engineer Breaks,, Matthew Calvin; Lic. No.: S6028 5056 TUJUNGA AVE APT 17      NORTH HOLLYWOOD, CA 91601

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 2/15/2024 Approved CHRISTOPHE COCHRAN
Excavation/Setback/Form/Re-Bar 2/29/2024 Approved KIRK SANDERS
BUILDING-Rough-Frame 5/23/2024 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Rough 5/23/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Green Building Rough 5/23/2024 Not Ready for Inspection CHRISTOPHER ROJAS
MERV13>=Rough 5/23/2024 Not Ready for Inspection CHRISTOPHER ROJAS
PLUMBING-Rough 5/23/2024 Not Ready for Inspection CHRISTOPHER ROJAS
BUILDING-Rough-Frame 5/30/2024 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Rough 5/30/2024 Approved CHRISTOPHER ROJAS
Green Building Rough 5/30/2024 Not Ready for Inspection CHRISTOPHER ROJAS
MERV13>=Rough 5/30/2024 Approved CHRISTOPHER ROJAS
PLUMBING-Rough 5/30/2024 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 6/11/2024 Partial Approval CHRISTOPHER ROJAS
ELECTRICAL-Rough 6/11/2024 Partial Approval CHRISTOPHER ROJAS
Green Building Rough 6/11/2024 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 6/11/2024 Partial Approval CHRISTOPHER ROJAS
Insulation 6/18/2024 Approved CHRISTOPHER ROJAS
Drywall Nailing 7/3/2024 Approved RYAN SALAZAR
Interior/Exterior Lathing 7/30/2024 Approved CHRISTOPHER ROJAS
Shower Pan 7/30/2024 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 10/23/2024 Approved CHRISTOPHER ROJAS
Final 10/23/2024 Corrections Issued CHRISTOPHER ROJAS
Footing/Foundation/Slab 10/23/2024 Approved CHRISTOPHER ROJAS
Green Building Final 10/23/2024 Approved CHRISTOPHER ROJAS
MERV13>=Final 10/23/2024 Approved CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 10/23/2024 SGSOV Approved CHRISTOPHER ROJAS
Smoke Detectors 10/23/2024 Approved CHRISTOPHER ROJAS
Final 10/29/2024 OK to Issue CofO CHRISTOPHER ROJAS
Deputy Drilled-In Anchors 10/30/2024 Conditional Approval JUAN VALENZUELA