8571 1/2 W AIRDROME ST 90035

Certificate Information: 8571 1/2 W AIRDROME ST 90035

Application / Permit
23014-10000-02805
Plan Check / Job No.
B23LA12990
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan - addition of 1-story ADU to (e) 1-story detached garage per GCS 65852.2 (e)(1)(B) nad LAMC 12.22 A.33 (c)(d)(g) R3/U occupancy
Permit Issued
Issued on 8/5/2024
Issuing Office
Metro
Current Status
CofO Issued on 3/15/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/3/2023 APPLICANT
Assigned to Plan Check Engineer 8/10/2023 KELVIN CHUONG
Corrections Issued 8/15/2023 KELVIN CHUONG
Quality Review Completed 8/21/2023 RODOLFO ARIAS
Applicant returned to address corrections 11/7/2023 KELVIN CHUONG
Applicant returned to address corrections 12/13/2023 KELVIN CHUONG
Applicant returned to address corrections 4/10/2024 KELVIN CHUONG
Plan Check Approved 6/14/2024 KELVIN CHUONG
Issued 8/5/2024 APPLICANT
CofO in Progress 3/13/2025 EVAN COOPER
Permit Finaled 3/15/2025 RICHARD STEINBACH
CofO Issued 3/15/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 8/23/2023 CHRISTINA BRACO
Tenant Habitability Plan Cleared 12/19/2023 ISMAEL HERNANDEZ
Construction near power lines Cleared 2/21/2024 RIDWAN HARDY
Low Impact Development (LID) Cleared 4/10/2024 SAMUEL LINN
Roof/Waste drainage to street Cleared 4/16/2024 CHRISTINA BRACO
Eng Process Fee Ord 176,300 Cleared 6/7/2024 CHRISTINA BRACO
Sewer availability Cleared 6/7/2024 CHRISTINA BRACO

Contact Information

Contractor Ram Construction & Electrical; Lic. No.: 1064340-B       ,
Contractor The Contractor Gal; Lic. No.: 1064340-B       ,

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

METHANE-Barrier 8/13/2024 Not Ready for Inspection SEAN HAUPT
METHANE-Rough 8/13/2024 Not Ready for Inspection SEAN HAUPT
METHANE-Subgrade 8/13/2024 Approved SEAN HAUPT
Underground Mechanical 8/13/2024 Approved SEAN HAUPT
Excavation/Setback/Form/Re-Bar 8/19/2024 Not Ready for Inspection KIRK SANDERS
Footing/Foundation/Slab 8/19/2024 Corrections Issued KIRK SANDERS
METHANE-Barrier 8/19/2024 Corrections Issued KIRK SANDERS
Excavation/Setback/Form/Re-Bar 8/20/2024 Approved SEAN HAUPT
Footing/Foundation/Slab 8/20/2024 Approved SEAN HAUPT
METHANE-Barrier 8/20/2024 Approved SEAN HAUPT
METHANE-Rough 8/20/2024 Approved SEAN HAUPT
Deputy Methane Barrier 8/27/2024 No Access for Inspection MEL KHACHATOURIAN
ELECTRICAL-Rough 9/17/2024 Not Ready for Inspection ARAM AVEDISIAN
PLUMBING-Rough 9/17/2024 Not Ready for Inspection ARAM AVEDISIAN
ELECTRICAL-Rough 9/18/2024 Corrections Issued STEPHANIE SWANSON
PLUMBING-Rough 9/18/2024 Approved STEPHANIE SWANSON
ELECTRICAL-Rough 9/20/2024 Approved ARAM AVEDISIAN
HVAC-Rough 10/1/2024 Corrections Issued ARAM AVEDISIAN
HVAC-Rough 10/2/2024 Not Ready for Inspection MEL KHACHATOURIAN
BUILDING-Rough-Frame 10/18/2024 No Access for Inspection MEL KHACHATOURIAN
Green Building Rough 10/18/2024 No Access for Inspection MEL KHACHATOURIAN
HVAC-Rough 10/18/2024 No Access for Inspection MEL KHACHATOURIAN
BUILDING-Rough-Frame 10/21/2024 Not Ready for Inspection MEL KHACHATOURIAN
Floor/Roof Diaphrgm/Shear Wall 10/21/2024 Approved MEL KHACHATOURIAN
HVAC-Rough 10/21/2024 Approved MEL KHACHATOURIAN
BUILDING-Rough-Frame 10/28/2024 Approved MEL KHACHATOURIAN
Green Building Rough 10/28/2024 Approved MEL KHACHATOURIAN
Interior/Exterior Lathing 10/28/2024 Partial Approval MEL KHACHATOURIAN
Insulation 10/31/2024 Approved MEL KHACHATOURIAN
Interior/Exterior Lathing 10/31/2024 Partial Approval MEL KHACHATOURIAN
Shower Pan 10/31/2024 Approved MEL KHACHATOURIAN
Drywall Nailing 11/4/2024 Approved MEL KHACHATOURIAN
Interior/Exterior Lathing 11/4/2024 Approved MEL KHACHATOURIAN
ELECTRICAL-Final 2/6/2025 Not Ready for Inspection MEL KHACHATOURIAN
HVAC-Final 2/6/2025 Approved MEL KHACHATOURIAN
PLUMBING-Final 2/6/2025 Corrections Issued MEL KHACHATOURIAN
ELECTRICAL-Final 2/28/2025 Approved EVAN COOPER
Final 2/28/2025 Corrections Issued EVAN COOPER
Green Building Final 2/28/2025 Approved EVAN COOPER
HVAC-Final 2/28/2025 Approved EVAN COOPER
PLUMBING-Final 2/28/2025 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 2/28/2025 SGSOV Approved EVAN COOPER
Service/Power Release 2/28/2025 Approved EVAN COOPER
Smoke Detectors 2/28/2025 Approved EVAN COOPER
Final 3/13/2025 OK to Issue CofO EVAN COOPER