1025 S TREMAINE AVE 90019
Certificate Information: 1025 S TREMAINE AVE 90019
- Application / Permit
- 23014-10000-02768
- Plan Check / Job No.
- B23LA12844
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION OF 29'-4" x 13'-3" IRREGULAR SHAPED ADDITION TO (E) SFD. WORK DONE PER ENGINEERING. ** SEE COMMENTS
- Permit Issued
- Issued on 8/21/2023
- Issuing Office
- Current Status
- CofO Issued on 12/23/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/13/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/21/2023 | MIROOSH KHACHATOORIAN |
| Corrections Issued | 7/24/2023 | MIROOSH KHACHATOORIAN |
| Applicant returned to address corrections | 8/9/2023 | MIROOSH KHACHATOORIAN |
| Applicant returned to address corrections | 8/11/2023 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 8/19/2023 | ALEC MOUSAKHANIAN |
| Issued | 8/21/2023 | APPLICANT |
| CofO in Progress | 10/29/2024 | RONNIE MINDANAO |
| No Progress | 11/14/2024 | JOAQUIN GREENOUGH |
| CofO in Progress | 11/14/2024 | JOAQUIN GREENOUGH |
| Permit Finaled | 12/23/2024 | DEROLD HAUFF |
| CofO Issued | 12/23/2024 | DEROLD HAUFF |
| Permit Finaled | 12/23/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/15/2023 | NEIL TUANO |
| Roof/Waste drainage to street | Cleared | 8/15/2023 | NEIL TUANO |
| Sewer availability | Cleared | 8/15/2023 | NEIL TUANO |
Contact Information
| Architect | Gaudio,, Kristin Drews; Lic. No.: C35634 | 527 W 7TH ST #710 LOS ANGELES, CA 90014 |
| Architect | Gaudio,, Kristin Drews; Lic. No.: NA35634 | , |
| Contractor | Rebuilt Homes Inc; Lic. No.: 1063540-B | , |
| Contractor | Rebuilt; Lic. No.: 1063540-B | , |
| Engineer | Saleh,, Zouheir Toufic; Lic. No.: C42881 | 1304 CORTE MALTERA COSTA MESA, CA 92626 |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/5/2023 | Approved | ROY SPAULDING |
| Footing/Foundation/Slab | 9/5/2023 | Approved | ROY SPAULDING |
| METHANE-Barrier | 9/5/2023 | Approved | ROY SPAULDING |
| METHANE-Subgrade | 9/5/2023 | Approved | ROY SPAULDING |
| BUILDING-Rough-Frame | 9/25/2023 | Partial Approval | RICHARD DOCKUS |
| PLUMBING-Rough | 9/25/2023 | Partial Approval | RICHARD DOCKUS |
| Floor/Roof Diaphrgm/Shear Wall | 9/27/2023 | Partial Approval | JUSTIN HAWLEY |
| Insulation | 9/27/2023 | Partial Approval | JUSTIN HAWLEY |
| Floor/Roof Diaphrgm/Shear Wall | 10/11/2023 | Corrections Issued | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 11/8/2023 | Conditional Approval | RICHARD DOCKUS |
| HVAC-Rough | 11/30/2023 | Corrections Issued | RICHARD DOCKUS |
| PLUMBING-Rough | 11/30/2023 | Corrections Issued | RICHARD DOCKUS |
| ELECTRICAL-Rough | 12/1/2023 | Approved | RICHARD DOCKUS |
| PLUMBING-Rough | 12/1/2023 | Approved | RICHARD DOCKUS |
| HVAC-Rough | 12/4/2023 | Approved | RICHARD DOCKUS |
| PLUMBING-Rough | 12/4/2023 | Approved | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 1/8/2024 | Not Ready for Inspection | RICHARD DOCKUS |
| METHANE-Rough | 1/8/2024 | Approved | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 2/20/2024 | Corrections Issued | AMIR NAZARIAN |
| Green Building Rough | 2/20/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| BUILDING-Rough-Frame | 2/27/2024 | Approved | RICHARD DOCKUS |
| Green Building Rough | 2/27/2024 | Not Ready for Inspection | RICHARD DOCKUS |
| Deputy Drilled-In Anchors | 2/29/2024 | Conditional Approval | RICHARD DOCKUS |
| Interior/Exterior Lathing | 3/13/2024 | Partial Approval | JEFFREY MEAD |
| Pre-Inspection | 3/20/2024 | Partial Inspection | RONNIE MINDANAO |
| Insulation | 4/10/2024 | Corrections Issued | RONNIE MINDANAO |
| Insulation | 6/3/2024 | Approved | RONNIE MINDANAO |
| Drywall Nailing | 6/11/2024 | Approved | JOSEPH MCGARRY |
| Shower Pan | 6/13/2024 | Approved | AMY COLIN |
| Interior/Exterior Lathing | 6/21/2024 | Approved | RICHARD DOCKUS |
| Sewer | 6/21/2024 | Approved | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 7/30/2024 | Approved | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 7/30/2024 | Approved | RONNIE MINDANAO |
| Green Building Rough | 7/30/2024 | Approved | RONNIE MINDANAO |
| ELECTRICAL-Final | 10/3/2024 | Corrections Issued | RONNIE MINDANAO |
| PLUMBING-Final | 10/3/2024 | Corrections Issued | RONNIE MINDANAO |
| Smoke Detectors | 10/3/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| Final | 10/7/2024 | Corrections Issued | RONNIE MINDANAO |
| Green Building Final | 10/7/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 10/7/2024 | SGSOV Not Ready | RONNIE MINDANAO |
| Final | 10/10/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
| Green Building Final | 10/10/2024 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 10/10/2024 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 10/10/2024 | Approved | ENRIQUE MIRELES |
| Final | 10/17/2024 | Corrections Issued | RONNIE MINDANAO |
| ELECTRICAL-Final | 10/22/2024 | Corrections Issued | RONNIE MINDANAO |
| Final | 10/22/2024 | Corrections Issued | RONNIE MINDANAO |
| HVAC-Final | 10/22/2024 | Corrections Issued | RONNIE MINDANAO |
| PLUMBING-Final | 10/22/2024 | Corrections Issued | RONNIE MINDANAO |
| ELECTRICAL-Final | 10/24/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| Gas Test | 10/24/2024 | Approved | RONNIE MINDANAO |
| HVAC-Final | 10/24/2024 | Approved | RONNIE MINDANAO |
| PLUMBING-Final | 10/24/2024 | Approved | RONNIE MINDANAO |
| ELECTRICAL-Final | 10/25/2024 | Approved | JOSE MACIAS |
| Final | 10/25/2024 | Conditional Approval | RONNIE MINDANAO |
| Final | 10/28/2024 | OK to Issue CofO | RONNIE MINDANAO |