5377 E OAKLAND ST 90032

Certificate Information: 5377 E OAKLAND ST 90032

Application / Permit
23014-10000-02741
Plan Check / Job No.
B23LA12707
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
COVER (E) PORCH ON 1ST FLOOR AND GROUND FLOOR 2 STORY ADDITION
Permit Issued
Issued on 3/29/2024
Issuing Office
Current Status
Issued on 3/29/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/12/2023 APPLICANT
Assigned to Plan Check Engineer 7/27/2023 CARLOS MONTES
Corrections Issued 7/30/2023 CARLOS MONTES
Quality Review Completed 8/3/2023 GARO TELMI
Applicant returned to address corrections 10/19/2023 CARLOS MONTES
Applicant returned to address corrections 12/12/2023 CARLOS MONTES
Plan Check Approved 2/20/2024 CARLOS MONTES
Issued 3/29/2024 APPLICANT

Permit Application Clearance Information

Grading Pre-Inspection Cleared 10/12/2023 ALEXANDER HELFER
Roof/Waste drainage to street Cleared 10/12/2023 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 10/16/2023 WALLIE JONG
Sewer availability Cleared 10/16/2023 WALLIE JONG
GPI Written Notices Cleared 2/20/2024 CARLOS MONTES

Contact Information

Contractor Owner-Builder       ,
Engineer Chu,, Tien Manh; Lic. No.: NA72324       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/1/2024 Approved LILIANA PORTILLO
Footing/Foundation/Slab 5/1/2024 Corrections Issued LILIANA PORTILLO
Footing/Foundation/Slab 5/2/2024 Corrections Issued LILIANA PORTILLO
Deputy Drilled-In Anchors 5/10/2024 Conditional Approval LILIANA PORTILLO
BUILDING-Rough-Frame 10/30/2024 Corrections Issued LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 4/14/2025 Corrections Issued LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 10/16/2025 Approved LILIANA PORTILLO
ELECTRICAL-Rough 10/23/2025 Not Ready for Inspection LILIANA PORTILLO
PLUMBING-Rough 10/23/2025 No Access for Inspection LILIANA PORTILLO
BUILDING-Rough-Frame 5/4/2026 Not Ready for Inspection LILIANA PORTILLO
ELECTRICAL-Rough 5/4/2026 Approved LILIANA PORTILLO
HVAC-Rough 5/4/2026 Not Ready for Inspection LILIANA PORTILLO