5316-5316 1/2 N ARGUS DR 90041
Certificate Information: 5316-5316 1/2 N ARGUS DR 90041
- Application / Permit
- 23014-10000-02719
- Plan Check / Job No.
- B23LA12566
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT EXISTING ATTACHED GARAGE TO STORAGE ROOM AND ACCESSORY DWELLING UNIT WITH 9'-0" X 10'-0" ADDITION PER LAMC 12.22 A.33(c) AND (e)
- Permit Issued
- Issued on 9/18/2023
- Issuing Office
- Current Status
- CofO Issued on 5/10/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/10/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/14/2023 | ALEC MOUSAKHANIAN |
| Corrections Issued | 7/17/2023 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 8/26/2023 | ALEC MOUSAKHANIAN |
| Issued | 9/18/2023 | APPLICANT |
| CofO in Progress | 5/9/2025 | CHARLES BOGHOSKHAN |
| Permit Finaled | 5/10/2025 | DEROLD HAUFF |
| CofO Issued | 5/10/2025 | DEROLD HAUFF |
| Permit Finaled | 5/10/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/8/2023 | HUGO LOPEZ |
| Roof/Waste drainage to street | Cleared | 8/8/2023 | HUGO LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/22/2023 | HUGO LOPEZ |
| Sewer availability | Cleared | 8/22/2023 | HUGO LOPEZ |
| Grading Pre-Inspection | Cleared | 8/26/2023 | ALEC MOUSAKHANIAN |
Contact Information
| Contractor | Christopher Williams; Lic. No.: 711380-B | , |
| Contractor | Williams Christopher; Lic. No.: 711380-B | , |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/8/2023 | Approved | CRAIG VAUGHAN |
| PLUMBING-Rough | 12/19/2023 | Approved | ROY SPAULDING |
| Floor/Roof Diaphrgm/Shear Wall | 1/9/2024 | Partial Approval | CRAIG VAUGHAN |
| Rough-Elec/Plmb/HVAC | 1/22/2024 | Approved | ROY SPAULDING |
| Wood Frame | 1/22/2024 | Approved | ROY SPAULDING |
| Insulation | 1/29/2024 | Corrections Issued | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 2/1/2024 | Approved | JOSH MEISTER |
| Drywall Nailing | 2/6/2024 | Approved | CRAIG VAUGHAN |
| Insulation | 2/6/2024 | Approved | CRAIG VAUGHAN |
| PLUMBING-Rough | 2/6/2024 | Corrections Issued | CRAIG VAUGHAN |
| Shower Pan | 2/26/2024 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 3/11/2024 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 7/25/2024 | Approved | CRAIG VAUGHAN |
| Final | 7/25/2024 | Corrections Issued | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 7/25/2024 | SGSOV Approved | CRAIG VAUGHAN |
| Smoke Detectors | 7/25/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| Final | 8/14/2024 | Corrections Issued | CRAIG VAUGHAN |
| Smoke Detectors | 8/14/2024 | Approved | CRAIG VAUGHAN |
| Final | 2/24/2025 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Final | 4/7/2025 | No Access for Inspection | JEFFREY MEAD |
| Final | 4/17/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| Final | 5/8/2025 | OK to Issue CofO | CHARLES BOGHOSKHAN |