714 W 27TH ST 90731
Certificate Information: 714 W 27TH ST 90731
- Application / Permit
- 23014-10000-02699
- Plan Check / Job No.
- B23LA12483
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan** 1st story addition on the rear and uncovered deck above.
- Permit Issued
- Issued on 1/22/2024
- Issuing Office
- Current Status
- CofO Issued on 7/25/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/7/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/20/2023 | RAHEL BEYENE |
| Corrections Issued | 7/26/2023 | RAHEL BEYENE |
| Quality Review Completed | 8/15/2023 | MICHAEL PEREZ |
| Applicant returned to address corrections | 9/20/2023 | RAHEL BEYENE |
| Applicant returned to address corrections | 10/3/2023 | RAHEL BEYENE |
| Applicant returned to address corrections | 11/8/2023 | RAHEL BEYENE |
| Plan Check Approved | 11/15/2023 | RAHEL BEYENE |
| Issued | 1/22/2024 | APPLICANT |
| CofO in Progress | 7/25/2024 | EUGENE CASSIDY |
| CofO Issued | 7/25/2024 | ANSON MAGLASANG |
| Permit Finaled | 7/25/2024 | ANSON MAGLASANG |
Permit Application Clearance Information
| Specific Plan | Cleared | 8/21/2023 | WESTON PRINGLE |
| Roof/Waste drainage to street | Cleared | 8/22/2023 | KHAING AYE |
| Sewer availability | Cleared | 8/22/2023 | KHAING AYE |
| Eng Process Fee Ord 176,300 | Cleared | 8/28/2023 | KHAING AYE |
| Grading Pre-Inspection | Cleared | 10/3/2023 | RAHEL BEYENE |
Contact Information
| Contractor | Creative Home Remodeling Group Inc; Lic. No.: 943341-B | , |
| Engineer | Zhuang,, Wenbin; Lic. No.: S5236 | 205 S CHAPEL AVE #D-1 ALHAMBRA, CA 91801 |
Inspector Information
| JOSEPH MCGARRY, (310) 732-4559 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/9/2024 | Conditional Approval | ANSON MAGLASANG |
| Footing/Foundation/Slab | 2/12/2024 | Corrections Issued | JAMES CHAVEZ |
| Footing/Foundation/Slab | 2/27/2024 | Partial Approval | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 3/8/2024 | Corrections Issued | ANSON MAGLASANG |
| Green Building Rough | 3/8/2024 | Not Ready for Inspection | ANSON MAGLASANG |
| Floor/Roof Diaphrgm/Shear Wall | 3/11/2024 | Partial Approval | JAMES CHAVEZ |
| PLUMBING-Rough | 3/11/2024 | Partial Approval | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/13/2024 | Partial Approval | ANSON MAGLASANG |
| Floor/Roof Diaphrgm/Shear Wall | 4/9/2024 | Partial Approval | ANSON MAGLASANG |
| ELECTRICAL-Rough | 4/15/2024 | Approved | ANSON MAGLASANG |
| PLUMBING-Rough | 4/15/2024 | Approved | ANSON MAGLASANG |
| Underground Mechanical | 4/15/2024 | Partial Approval | ANSON MAGLASANG |
| Deputy Wood Construction | 4/18/2024 | Conditional Approval | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 4/22/2024 | Approved | ANSON MAGLASANG |
| Green Building Rough | 4/22/2024 | Approved | ANSON MAGLASANG |
| Insulation | 4/29/2024 | Approved | ANSON MAGLASANG |
| Interior/Exterior Lathing | 4/29/2024 | Partial Approval | ANSON MAGLASANG |
| Shower Pan | 4/29/2024 | Approved | ANSON MAGLASANG |
| Drywall Nailing | 5/6/2024 | Approved | JAMES CHAVEZ |
| Interior/Exterior Lathing | 5/6/2024 | Partial Approval | JAMES CHAVEZ |
| Deputy Drilled-In Anchors | 6/5/2024 | Conditional Approval | JAMES CHAVEZ |
| Footing/Foundation/Slab | 6/6/2024 | Corrections Issued | JAMES CHAVEZ |
| Footing/Foundation/Slab | 6/7/2024 | Approved | JAMES CHAVEZ |
| Final | 7/11/2024 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 7/11/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 7/11/2024 | SGSOV Approved | EUGENE CASSIDY |
| Smoke Detectors | 7/11/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 7/17/2024 | Conditional Approval | JAMES CHAVEZ |
| Green Building Final | 7/17/2024 | Approved | JAMES CHAVEZ |
| Smoke Detectors | 7/17/2024 | Approved | JAMES CHAVEZ |
| Final | 7/24/2024 | OK to Issue CofO | EUGENE CASSIDY |