7712 S BELAND AVE 90045
Certificate Information: 7712 S BELAND AVE 90045
- Application / Permit
- 23014-10000-02692
- Plan Check / Job No.
- B23LA12440
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Ground floor addition and interior remodel to existing 2-story single family dwelling with attached garage. All work per engineer. **ePLAN**
- Permit Issued
- Issued on 8/7/2023
- Issuing Office
- Current Status
- Issued on 8/7/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/7/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/7/2023 | VICTOR CHEN |
| Corrections Issued | 7/7/2023 | VICTOR CHEN |
| Plan Check Approved | 8/3/2023 | KHUONG TRUONG |
| Issued | 8/7/2023 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/14/2023 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 7/14/2023 | DINAH GARIN |
| Specific Plan | Cleared | 8/4/2023 | PEDRO AYALA |
Contact Information
| Contractor | M G M W Remodeling Inc; Lic. No.: 1045515-B | , |
| Contractor | Mgmw Remodeling Inc; Lic. No.: 1045515-B | , |
| Engineer | Barakat,, Fouad Chafic; Lic. No.: C67449 | 11 CEDARWOOD DR POMONA, CA 91766 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/18/2023 | Corrections Issued | BOBBY KEY |
| BUILDING-Rough-Frame | 8/31/2023 | Partial Approval | HERBERT GIRON |
| Wood Frame | 8/31/2023 | Partial Approval | HERBERT GIRON |
| Deputy Wood Construction | 9/19/2023 | Partial Approval | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 9/26/2023 | Corrections Issued | BOBBY KEY |
| Rough-Elec/Plmb/HVAC | 9/26/2023 | Partial Approval | BOBBY KEY |
| BUILDING-Rough-Frame | 10/10/2023 | Approved | BOBBY KEY |
| Drywall Nailing | 10/10/2023 | Approved | BOBBY KEY |
| Green Building Rough | 10/10/2023 | Approved | BOBBY KEY |
| Insulation | 10/10/2023 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 10/10/2023 | Partial Approval | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 12/15/2023 | SGSOV Approved | TEMISTOCLES CAAL |
| Smoke Detectors | 12/15/2023 | Approved | TEMISTOCLES CAAL |
| Final | 1/12/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Green Building Final | 1/12/2024 | Approved | TEMISTOCLES CAAL |