3312 W LONDON ST 90026
Certificate Information: 3312 W LONDON ST 90026
- Application / Permit
- 23014-10000-02669
- Plan Check / Job No.
- B23LA12338
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING DETACHED GARAGE WITH ADDTION TO ADU (1,200 SF max per Ordinance, LAMC 12.22 A.33 (c)-(d))
- Permit Issued
- Issued on 11/29/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/23/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/5/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/6/2023 | AUNG SOE |
| Corrections Issued | 7/10/2023 | AUNG SOE |
| Building Plans Picked Up | 7/17/2023 | APPLICANT |
| Applicant returned to address corrections | 10/6/2023 | NEHEMIAS RAMOS |
| Applicant returned to address corrections | 10/24/2023 | CRISTINA SALAZAR |
| Plan Check Approved | 11/3/2023 | NEHEMIAS RAMOS |
| Issued | 11/29/2023 | APPLICANT |
| CofO in Progress | 4/23/2025 | FREDDIE RIVERA |
| CofO Issued | 4/23/2025 | DEROLD HAUFF |
| Permit Finaled | 4/23/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/31/2023 | CHRISTINA BRACO |
| Eng Process Fee Ord 176,300 | Cleared | 8/2/2023 | CHRISTINA BRACO |
| Sewer availability | Cleared | 8/2/2023 | CHRISTINA BRACO |
| Grading Pre-Inspection | Cleared | 9/20/2023 | RUSSELL BONVOULOIR |
| Low Impact Development (LID) | Cleared | 9/28/2023 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 9/29/2023 | CHRISTINA BRACO |
Contact Information
| Contractor | The Fix Inc; Lic. No.: 1049919-B | 1509 W SUNSET BLVD #B LOS ANGELES, CA 90026 |
| Engineer | Manoukian,, Krikor Kerop; Lic. No.: C87010 | 2310 W MAGNOLIA BLVD STE A BURBANK, CA 91506 |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/12/2024 | Corrections Issued | FREDDIE RIVERA |
| PLUMBING-Rough | 1/12/2024 | Partial Approval | FREDDIE RIVERA |
| Footing/Foundation/Slab | 3/19/2024 | Corrections Issued | FREDDIE RIVERA |
| METHANE-Barrier | 3/19/2024 | Approved | FREDDIE RIVERA |
| METHANE-Subgrade | 3/19/2024 | Conditional Approval | FREDDIE RIVERA |
| Deputy Wood Construction | 4/18/2024 | Conditional Approval | FREDDIE RIVERA |
| ELECTRICAL-Rough | 7/29/2024 | Not Ready for Inspection | FREDDIE RIVERA |
| HVAC-Rough | 7/29/2024 | Not Ready for Inspection | FREDDIE RIVERA |
| Underground Mechanical | 7/29/2024 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Rough | 8/12/2024 | Approved | FREDDIE RIVERA |
| HVAC-Rough | 8/12/2024 | Corrections Issued | FREDDIE RIVERA |
| PLUMBING-Rough | 8/12/2024 | Corrections Issued | FREDDIE RIVERA |
| Wood Frame | 8/12/2024 | Partial Inspection | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 9/3/2024 | Approved | LUIS CASTRO |
| Green Building Rough | 9/3/2024 | Approved | LUIS CASTRO |
| HVAC-Rough | 9/3/2024 | Approved | LUIS CASTRO |
| MERV13>=Rough | 9/3/2024 | Approved | LUIS CASTRO |
| METHANE-Rough | 9/3/2024 | Approved | LUIS CASTRO |
| PLUMBING-Rough | 9/3/2024 | Approved | LUIS CASTRO |
| Wood Frame | 9/3/2024 | Not Ready for Inspection | LUIS CASTRO |
| Insulation | 9/18/2024 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 9/18/2024 | Partial Approval | FREDDIE RIVERA |
| Drywall Nailing | 10/4/2024 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 10/4/2024 | Partial Approval | FREDDIE RIVERA |
| Shower Pan | 10/4/2024 | Corrections Issued | FREDDIE RIVERA |
| Shower Pan | 10/18/2024 | Approved | BRENDAN MORELLI |
| ELECTRICAL-Final | 2/13/2025 | Partial Approval | FREDDIE RIVERA |
| Final | 2/13/2025 | Corrections Issued | FREDDIE RIVERA |
| Footing/Foundation/Slab | 2/13/2025 | Approved | FREDDIE RIVERA |
| Green Building Final | 2/13/2025 | Approved | FREDDIE RIVERA |
| HVAC-Final | 2/13/2025 | Approved | FREDDIE RIVERA |
| MERV13>=Final | 2/13/2025 | Approved | FREDDIE RIVERA |
| METHANE-Subgrade | 2/13/2025 | Approved | FREDDIE RIVERA |
| PLUMBING-Final | 2/13/2025 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 2/13/2025 | SGSOV Not Required | FREDDIE RIVERA |
| Smoke Detectors | 2/13/2025 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Final | 3/24/2025 | Approved | FREDDIE RIVERA |
| Final | 3/24/2025 | OK to Issue CofO | FREDDIE RIVERA |
| HVAC-Final | 3/24/2025 | Approved | FREDDIE RIVERA |
| PLUMBING-Final | 3/24/2025 | Approved | FREDDIE RIVERA |