305-307 E 115TH ST 90061

Certificate Information: 305-307 E 115TH ST 90061

Application / Permit
23014-10000-02662
Plan Check / Job No.
B23LA12270
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan Convert (E) Attached garage to 400 SF ADU. Per CA Govt. Code 65852.2(e)(1)(A). "COMPLY WITH DEPARTMENT ORDER effective date 06/16/2023. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE". CEIS Case Number is 988330.
Permit Issued
Issued on 5/24/2024
Issuing Office
Metro
Current Status
CofO Issued on 6/3/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/17/2023 APPLICANT
Assigned to Plan Check Engineer 7/24/2023 ALFREDO JARA
Corrections Issued 7/25/2023 ALFREDO JARA
Plan Check Approved 5/24/2024 ALEXANDER JOO
Issued 5/24/2024 APPLICANT
CofO in Progress 12/31/2025 KEITH EDGHILL
Permit Finaled 6/3/2026 CLAUDIO MORENO
Permit Finaled 6/3/2026 CLAUDIO MORENO
CofO Issued 6/3/2026 CLAUDIO MORENO

Permit Application Clearance Information

Address approval Cleared 7/27/2023 ABEL CASILLAS
Roof/Waste drainage to street Cleared 7/27/2023 ABEL CASILLAS
Sewer availability Cleared 7/27/2023 ABEL CASILLAS
ZI Cleared 7/28/2023 MAXFIELD VERMY
Eng Process Fee Ord 176,300 Cleared 8/3/2023 ANA SORIANO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

KELLY WARNER, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI
PAUL BECKER, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI
KEITH EDGHILL, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI
DANIEL GONZALEZ, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/28/2024 Approved BEN MOLSTAD
Deputy Drilled-In Anchors 9/26/2024 Conditional Approval BARRY HACHE
Footing/Foundation/Slab 9/26/2024 Corrections Issued BARRY HACHE
PLUMBING-Rough 9/26/2024 Not Ready for Inspection BARRY HACHE
PLUMBING-Rough 9/30/2024 Approved BEN MOLSTAD
Footing/Foundation/Slab 10/2/2024 Approved BARRY HACHE
ELECTRICAL-Rough 10/17/2024 Approved KEITH EDGHILL
Floor/Roof Diaphrgm/Shear Wall 10/17/2024 Approved KEITH EDGHILL
Gas Test 10/17/2024 Approved KEITH EDGHILL
PLUMBING-Rough 10/17/2024 Approved KEITH EDGHILL
Wood Frame 10/17/2024 Conditional Approval KEITH EDGHILL
Deputy Wood Construction 10/18/2024 Approved KEITH EDGHILL
Insulation 10/29/2024 Approved KEITH EDGHILL
Interior/Exterior Lathing 10/29/2024 Conditional Approval KEITH EDGHILL
Drywall Nailing 11/22/2024 Approved KEITH EDGHILL
Shower Pan 11/22/2024 Approved KEITH EDGHILL
Interior/Exterior Lathing 12/12/2024 Approved KEITH EDGHILL
BUILDING-Rough-Frame 9/18/2025 Conditional Approval KEITH EDGHILL
Final 9/18/2025 Corrections Issued KEITH EDGHILL
MERV13>=Final 9/18/2025 Not Required KEITH EDGHILL
MERV13>=Rough 9/18/2025 Not Required KEITH EDGHILL
SGSOV-Seismic Gas S/O Valve 9/18/2025 SGSOV Not Ready KEITH EDGHILL
Service/Power Release 9/18/2025 Approved KEITH EDGHILL
Smoke Detectors 9/18/2025 Approved KEITH EDGHILL
BUILDING-Rough-Frame 12/30/2025 Approved KEITH EDGHILL
ELECTRICAL-Final 12/30/2025 Approved KEITH EDGHILL
Final 12/30/2025 OK to Issue CofO KEITH EDGHILL
PLUMBING-Final 12/30/2025 Approved KEITH EDGHILL
SGSOV-Seismic Gas S/O Valve 12/30/2025 SGSOV Approved KEITH EDGHILL
Wood Frame 12/30/2025 Approved KEITH EDGHILL