149-149 1/2 W 111TH PL 90061

Certificate Information: 149-149 1/2 W 111TH PL 90061

Application / Permit
23014-10000-02647
Plan Check / Job No.
B23LA12223
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
***ePlan*** 1-story addition and converion to rear side of (e) single story SFD w./ att. garage to a attached ADU per LAMC 12.22 A.33(C) AND (E) ; add an attached patio cover to the rear side (84 sf) , COMPLY WITH DEPARTMENT ORDER effective date 03/04/2022. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
Permit Issued
Issued on 7/1/2025
Issuing Office
Current Status
Issued on 7/1/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/17/2023 APPLICANT
Assigned to Plan Check Engineer 7/25/2023 ALEC MOUSAKHANIAN
Corrections Issued 7/26/2023 ALEC MOUSAKHANIAN
Applicant returned to address corrections 11/29/2023 ALEC MOUSAKHANIAN
Plan Check Approved 8/29/2024 YASHAR EMAMI
Issued 7/1/2025 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 8/21/2023 CHRISTINA BRACO
Sewer availability Cleared 8/21/2023 CHRISTINA BRACO
Address approval Cleared 8/23/2023 CHRISTINA BRACO
Eng Process Fee Ord 176,300 Cleared 8/23/2023 CHRISTINA BRACO

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

JOHN PARKER, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
MICHAEL SERETTI, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
HECTOR RODRIGUEZ, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
BRUCE TODD, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
JAVIER RAMOS SR, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
MARIAN PODPORA, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 9/9/2025 Not Ready for Inspection MICHAEL SERETTI
Wood Frame 9/9/2025 Not Ready for Inspection MICHAEL SERETTI
BUILDING-Rough-Frame 9/16/2025 Approved MICHAEL SERETTI
Footing/Foundation/Slab 9/16/2025 Approved MICHAEL SERETTI
Insulation 9/18/2025 Approved MICHAEL SERETTI
Interior/Exterior Lathing 9/18/2025 Partial Approval MICHAEL SERETTI
Light Gage Steel Frame 9/18/2025 Approved MICHAEL SERETTI
ELECTRICAL-Rough 9/23/2025 Partial Approval MICHAEL SERETTI
Green Building Rough 9/23/2025 Approved MICHAEL SERETTI
PLUMBING-Rough 9/23/2025 Approved MICHAEL SERETTI
Special/Order Compliance 10/9/2025 Partial Approval MICHAEL SERETTI
BUILDING-Rough-Frame 10/21/2025 Approved MICHAEL SERETTI
Shower Pan 10/28/2025 Approved MICHAEL SERETTI
Drywall Nailing 11/13/2025 Approved MICHAEL SERETTI
Final 11/13/2025 Conditional Approval MICHAEL SERETTI
Green Building Final 11/13/2025 Approved MICHAEL SERETTI
SGSOV-Seismic Gas S/O Valve 11/13/2025 SGSOV Approved MICHAEL SERETTI
Smoke Detectors 11/13/2025 Approved MICHAEL SERETTI