1125 N HARTZELL ST 90272
Certificate Information: 1125 N HARTZELL ST 90272
- Application / Permit
- 23014-10000-02627
- Plan Check / Job No.
- B23LA12149
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED STORAGE BUILDING TO (N) DETACHED ADU WITH ADDITION
- Permit Issued
- Issued on 10/3/2023
- Issuing Office
- Current Status
- CofO Issued on 6/15/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/30/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/3/2023 | JOSEPH RAFOLS |
| Corrections Issued | 7/3/2023 | JOSEPH RAFOLS |
| Building Plans Picked Up | 7/7/2023 | APPLICANT |
| Applicant returned to address corrections | 8/29/2023 | JOSEPH RAFOLS |
| Applicant returned to address corrections | 9/1/2023 | FERNANDO FLORES |
| Applicant returned to address corrections | 9/21/2023 | LUKE GONZALES |
| Plan Check Approved | 9/28/2023 | JOSEPH RAFOLS |
| Issued | 10/3/2023 | APPLICANT |
| CofO in Progress | 6/13/2024 | CARLOS MATAMOROS |
| Permit Finaled | 6/15/2024 | DANIEL ORRANTE |
| CofO Issued | 6/15/2024 | DANIEL ORRANTE |
| Permit Finaled | 6/15/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 7/26/2023 | ANTHONY MAINEZ |
| Roof/Waste drainage to street | Cleared | 7/26/2023 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 7/27/2023 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 7/27/2023 | ANTHONY MAINEZ |
| Grading Pre-Inspection | Cleared | 8/29/2023 | JOSEPH RAFOLS |
Contact Information
| Contractor | N C C Construction & Development Inc; Lic. No.: 1021608-B | 2346 SHELBY AVE LOS ANGELES, CA 90064 |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 60 VIA CARATAMA SAN CLEMENTE, CA 92673 |
Inspector Information
| TEMISTOCLES CAAL, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
| JESUS PINEDA, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/15/2023 | Partial Approval | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 11/20/2023 | Conditional Approval | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/1/2023 | Partial Approval | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 12/15/2023 | Approved | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/15/2023 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 12/15/2023 | Not Ready for Inspection | ARAM AVEDISIAN |
| PLUMBING-Rough | 12/15/2023 | Approved | ARAM AVEDISIAN |
| HVAC-Rough | 1/10/2024 | Not Ready for Inspection | ARAM AVEDISIAN |
| Wood Frame | 1/10/2024 | Not Ready for Inspection | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 1/12/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Green Building Rough | 1/12/2024 | Not Ready for Inspection | JESUS RODRIGUEZ |
| HVAC-Rough | 1/12/2024 | Conditional Approval | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 1/12/2024 | Corrections Issued | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 1/25/2024 | Conditional Approval | ARAM AVEDISIAN |
| Green Building Rough | 1/25/2024 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 1/25/2024 | Partial Approval | ARAM AVEDISIAN |
| Insulation | 2/2/2024 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 2/2/2024 | Partial Approval | ARAM AVEDISIAN |
| Shower Pan | 2/2/2024 | Approved | ARAM AVEDISIAN |
| Underground Mechanical | 2/2/2024 | Partial Approval | ARAM AVEDISIAN |
| Drywall Nailing | 2/12/2024 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 2/12/2024 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 4/22/2024 | Approved | ARAM AVEDISIAN |
| Final | 4/22/2024 | Corrections Issued | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 4/22/2024 | Approved | ARAM AVEDISIAN |
| Green Building Final | 4/22/2024 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 4/22/2024 | SGSOV Not Required | ARAM AVEDISIAN |
| Smoke Detectors | 4/22/2024 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Final | 6/13/2024 | Approved | CARLOS MATAMOROS |
| Final | 6/13/2024 | OK to Issue CofO | CARLOS MATAMOROS |
| HVAC-Final | 6/13/2024 | Approved | CARLOS MATAMOROS |
| PLUMBING-Final | 6/13/2024 | Approved | CARLOS MATAMOROS |