1125 N HARTZELL ST 90272

Certificate Information: 1125 N HARTZELL ST 90272

Application / Permit
23014-10000-02627
Plan Check / Job No.
B23LA12149
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED STORAGE BUILDING TO (N) DETACHED ADU WITH ADDITION
Permit Issued
Issued on 10/3/2023
Issuing Office
Current Status
CofO Issued on 6/15/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/30/2023 APPLICANT
Assigned to Plan Check Engineer 7/3/2023 JOSEPH RAFOLS
Corrections Issued 7/3/2023 JOSEPH RAFOLS
Building Plans Picked Up 7/7/2023 APPLICANT
Applicant returned to address corrections 8/29/2023 JOSEPH RAFOLS
Applicant returned to address corrections 9/1/2023 FERNANDO FLORES
Applicant returned to address corrections 9/21/2023 LUKE GONZALES
Plan Check Approved 9/28/2023 JOSEPH RAFOLS
Issued 10/3/2023 APPLICANT
CofO in Progress 6/13/2024 CARLOS MATAMOROS
Permit Finaled 6/15/2024 DANIEL ORRANTE
CofO Issued 6/15/2024 DANIEL ORRANTE
Permit Finaled 6/15/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 7/26/2023 ANTHONY MAINEZ
Roof/Waste drainage to street Cleared 7/26/2023 ANTHONY MAINEZ
Eng Process Fee Ord 176,300 Cleared 7/27/2023 ANTHONY MAINEZ
Sewer availability Cleared 7/27/2023 ANTHONY MAINEZ
Grading Pre-Inspection Cleared 8/29/2023 JOSEPH RAFOLS

Contact Information

Contractor N C C Construction & Development Inc; Lic. No.: 1021608-B 2346 SHELBY AVE      LOS ANGELES, CA 90064
Engineer Standley,, Craig Erick; Lic. No.: C87675 60 VIA CARATAMA      SAN CLEMENTE, CA 92673

Inspector Information

TEMISTOCLES CAAL, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI
JESUS PINEDA, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/15/2023 Partial Approval ARAM AVEDISIAN
Footing/Foundation/Slab 11/20/2023 Conditional Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 12/1/2023 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Rough 12/15/2023 Approved ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 12/15/2023 Approved ARAM AVEDISIAN
Green Building Rough 12/15/2023 Not Ready for Inspection ARAM AVEDISIAN
PLUMBING-Rough 12/15/2023 Approved ARAM AVEDISIAN
HVAC-Rough 1/10/2024 Not Ready for Inspection ARAM AVEDISIAN
Wood Frame 1/10/2024 Not Ready for Inspection ARAM AVEDISIAN
BUILDING-Rough-Frame 1/12/2024 Corrections Issued JESUS RODRIGUEZ
Green Building Rough 1/12/2024 Not Ready for Inspection JESUS RODRIGUEZ
HVAC-Rough 1/12/2024 Conditional Approval JESUS RODRIGUEZ
Interior/Exterior Lathing 1/12/2024 Corrections Issued JESUS RODRIGUEZ
BUILDING-Rough-Frame 1/25/2024 Conditional Approval ARAM AVEDISIAN
Green Building Rough 1/25/2024 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 1/25/2024 Partial Approval ARAM AVEDISIAN
Insulation 2/2/2024 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 2/2/2024 Partial Approval ARAM AVEDISIAN
Shower Pan 2/2/2024 Approved ARAM AVEDISIAN
Underground Mechanical 2/2/2024 Partial Approval ARAM AVEDISIAN
Drywall Nailing 2/12/2024 Approved EVAN COOPER
Interior/Exterior Lathing 2/12/2024 Approved EVAN COOPER
BUILDING-Rough-Frame 4/22/2024 Approved ARAM AVEDISIAN
Final 4/22/2024 Corrections Issued ARAM AVEDISIAN
Footing/Foundation/Slab 4/22/2024 Approved ARAM AVEDISIAN
Green Building Final 4/22/2024 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 4/22/2024 SGSOV Not Required ARAM AVEDISIAN
Smoke Detectors 4/22/2024 Approved ARAM AVEDISIAN
ELECTRICAL-Final 6/13/2024 Approved CARLOS MATAMOROS
Final 6/13/2024 OK to Issue CofO CARLOS MATAMOROS
HVAC-Final 6/13/2024 Approved CARLOS MATAMOROS
PLUMBING-Final 6/13/2024 Approved CARLOS MATAMOROS