3817 W BRUNSWICK AVE 90039

Certificate Information: 3817 W BRUNSWICK AVE 90039

Application / Permit
23014-10000-02603
Plan Check / Job No.
B23LA12024
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePLAN. NEW ADDITION TO (E) SINGLE FAMILY DWELLING. INTERIOR REMODEL. NEW ATTACHED TRELLIS. KITCHEN REMODEL.
Permit Issued
Issued on 8/4/2023
Issuing Office
Current Status
Issued on 8/4/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/29/2023 APPLICANT
Assigned to Plan Check Engineer 7/7/2023 JOHNPAUL ISIP
Corrections Issued 7/10/2023 JOHNPAUL ISIP
Applicant returned to address corrections 7/22/2023 JOHNPAUL ISIP
Plan Check Approved 7/27/2023 KEVIN MORALES
Issued 8/4/2023 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 7/10/2023 JESSICA OPINION
Sewer availability Cleared 7/10/2023 JESSICA OPINION
ZI Cleared 7/10/2023 JASON CHAN
Eng Process Fee Ord 176,300 Cleared 7/11/2023 JESSICA OPINION

Contact Information

Contractor Dezign Construction Inc; Lic. No.: 1107522-B       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/28/2023 Corrections Issued HAMIK HARTOUNIAN
Footing/Foundation/Slab 8/31/2023 Approved HAMIK HARTOUNIAN
ELECTRICAL-Rough 10/18/2023 Corrections Issued HAMIK HARTOUNIAN
HVAC-Rough 10/18/2023 Not Ready for Inspection HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 10/24/2023 Conditional Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 10/24/2023 Conditional Approval HAMIK HARTOUNIAN
PLUMBING-Rough 10/24/2023 Corrections Issued HAMIK HARTOUNIAN
PLUMBING-Rough 11/6/2023 Corrections Issued HAMIK HARTOUNIAN
ELECTRICAL-Rough 11/8/2023 Partial Approval HAMIK HARTOUNIAN
PLUMBING-Rough 11/8/2023 Partial Approval HAMIK HARTOUNIAN
BUILDING-Rough-Frame 11/13/2023 Approved HAMIK HARTOUNIAN
Green Building Rough 11/13/2023 Approved HAMIK HARTOUNIAN
Rough-Elec/Plmb/HVAC 11/13/2023 Approved HAMIK HARTOUNIAN
Shower Pan 11/13/2023 Not Ready for Inspection HAMIK HARTOUNIAN
Insulation 11/17/2023 Corrections Issued HAMIK HARTOUNIAN
Shower Pan 11/17/2023 Conditional Approval HAMIK HARTOUNIAN
Insulation 12/4/2023 Corrections Issued HAMIK HARTOUNIAN
Insulation 12/6/2023 Not Ready for Inspection HAMIK HARTOUNIAN
Interior/Exterior Lathing 12/6/2023 Approved HAMIK HARTOUNIAN
Drywall Nailing 12/12/2023 Corrections Issued HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 6/26/2024 SGSOV Not Ready WILLIAM KUEHN
Final 6/28/2024 No Access for Inspection BRENDAN MORELLI
Special/Order Compliance 6/28/2024 No Access for Inspection BRENDAN MORELLI
SGSOV-Seismic Gas S/O Valve 7/5/2024 SGSOV Not Ready JOSEPH MCGARRY
Pre-Inspection 7/8/2024 Not Ready for Inspection THOMAS LOGRASSO
Drywall Nailing 7/11/2024 Approved THOMAS LOGRASSO
Final 7/11/2024 Corrections Issued THOMAS LOGRASSO
Footing/Foundation/Slab 7/11/2024 Approved THOMAS LOGRASSO
Green Building Final 7/11/2024 Not Ready for Inspection THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 7/11/2024 SGSOV Gas Company THOMAS LOGRASSO
Smoke Detectors 7/11/2024 Approved THOMAS LOGRASSO
Special/Order Compliance 12/24/2025 Corrections Issued NICHOLAS LOPEZ