8222 S OSAGE AVE 90045

Certificate Information: 8222 S OSAGE AVE 90045

Application / Permit
23014-10000-02601
Plan Check / Job No.
B23LA12021
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED PATIO WITH 13' X 11' ADDITION TO CREATE (N) DETACHED ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33 (c), (d) AND (g)
Permit Issued
Issued on 12/20/2023
Issuing Office
Current Status
CofO Issued on 12/24/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/29/2023 APPLICANT
Assigned to Plan Check Engineer 7/7/2023 LUISANGEL VALENZUELA
Corrections Issued 7/7/2023 LUISANGEL VALENZUELA
Applicant returned to address corrections 8/1/2023 MADISON ODELL
Plan Check Approved 10/20/2023 ALEC MOUSAKHANIAN
Issued 12/20/2023 APPLICANT
CofO in Progress 12/20/2024 TEMISTOCLES CAAL
Permit Finaled 12/24/2024 RICHARD STEINBACH
CofO Issued 12/24/2024 RICHARD STEINBACH
Permit Finaled 12/24/2024 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 8/7/2023 HISASHI KOBAYAKAWA
Roof/Waste drainage to street Cleared 8/7/2023 HISASHI KOBAYAKAWA
Eng Process Fee Ord 176,300 Cleared 8/8/2023 HISASHI KOBAYAKAWA
Sewer availability Cleared 8/8/2023 HISASHI KOBAYAKAWA
Grading Pre-Inspection Cleared 8/9/2023 SERGIO VALENZUELA
Construction near power lines Cleared 10/2/2023 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

METHANE-Subgrade 4/12/2024 Approved BOBBY KEY
PLUMBING-Rough 4/12/2024 Partial Approval BOBBY KEY
Deputy Drilled-In Anchors 4/22/2024 Approved BOBBY KEY
Footing/Foundation/Slab 4/22/2024 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 6/12/2024 Partial Approval BOBBY KEY
PLUMBING-Rough 6/12/2024 Approved BOBBY KEY
Sewer 6/12/2024 Approved BOBBY KEY
Underground Mechanical 6/12/2024 Partial Approval BOBBY KEY
ELECTRICAL-Rough 6/14/2024 Partial Approval TEMISTOCLES CAAL
HVAC-Rough 6/14/2024 Corrections Issued TEMISTOCLES CAAL
Deputy Wood Construction 6/17/2024 Conditional Approval BOBBY KEY
ELECTRICAL-Rough 6/21/2024 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 6/21/2024 Approved BOBBY KEY
HVAC-Rough 6/21/2024 Approved BOBBY KEY
BUILDING-Rough-Frame 7/2/2024 Approved BOBBY KEY
Insulation 7/2/2024 Corrections Issued BOBBY KEY
Interior/Exterior Lathing 7/2/2024 Approved BOBBY KEY
Insulation 8/14/2024 Approved BOBBY KEY
Drywall Nailing 8/22/2024 Approved BOBBY KEY
Shower Pan 8/27/2024 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 8/30/2024 Approved BOBBY KEY
Service/Power Release 11/12/2024 Not Ready for Inspection TEMISTOCLES CAAL
ELECTRICAL-Final 12/17/2024 Corrections Issued TEMISTOCLES CAAL
HVAC-Final 12/17/2024 Approved TEMISTOCLES CAAL
PLUMBING-Final 12/17/2024 Corrections Issued TEMISTOCLES CAAL
Special/Order Compliance 12/17/2024 Partial Inspection JAYLIN GRAVITTE
ELECTRICAL-Final 12/19/2024 Approved TEMISTOCLES CAAL
Final 12/19/2024 OK to Issue CofO TEMISTOCLES CAAL
HVAC-Final 12/19/2024 Approved TEMISTOCLES CAAL
PLUMBING-Final 12/19/2024 Approved TEMISTOCLES CAAL
SGSOV-Seismic Gas S/O Valve 12/19/2024 SGSOV Approved TEMISTOCLES CAAL
Service/Power Release 12/19/2024 Approved TEMISTOCLES CAAL
Smoke Detectors 12/19/2024 Approved TEMISTOCLES CAAL