8338 S WINSFORD AVE 90045
Certificate Information: 8338 S WINSFORD AVE 90045
- Application / Permit
- 23014-10000-02576
- Plan Check / Job No.
- B23LA11890
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: (N) BATHROOM ADDITION TO (E) SFD. ALL WORK DONE PER WFPP
- Permit Issued
- Issued on 10/18/2023
- Issuing Office
- Current Status
- Issued on 10/18/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/28/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/28/2023 | KHUONG TRUONG |
| Corrections Issued | 6/29/2023 | KHUONG TRUONG |
| Plan Check Approved | 10/4/2023 | RICARDO RAMIREZ |
| Issued | 10/18/2023 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 8/8/2023 | KIMBERLY HERNANDEZ |
| Sewer availability | Cleared | 8/8/2023 | KIMBERLY HERNANDEZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/16/2023 | KIMBERLY HERNANDEZ |
| Specific Plan | Cleared | 9/11/2023 | EDUARDO HERMOSO |
| Grading Pre-Inspection | Cleared | 10/3/2023 | KHUONG TRUONG |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/16/2024 | Conditional Approval | BOBBY KEY |
| Footing/Foundation/Slab | 1/17/2024 | Conditional Approval | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/9/2024 | Corrections Issued | BOBBY KEY |
| PLUMBING-Rough | 5/9/2024 | Partial Approval | BOBBY KEY |
| BUILDING-Rough-Frame | 8/8/2024 | Corrections Issued | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 8/8/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Green Building Rough | 8/8/2024 | Corrections Issued | TEMISTOCLES CAAL |
| HVAC-Rough | 8/8/2024 | Corrections Issued | TEMISTOCLES CAAL |
| PLUMBING-Rough | 8/8/2024 | Corrections Issued | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 8/12/2024 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 8/12/2024 | Partial Approval | BOBBY KEY |
| Footing/Foundation/Slab | 8/12/2024 | Approved | BOBBY KEY |
| HVAC-Rough | 8/12/2024 | Approved | BOBBY KEY |
| PLUMBING-Rough | 8/12/2024 | Not Ready for Inspection | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 8/13/2024 | Not Ready for Inspection | BOBBY KEY |
| PLUMBING-Rough | 8/13/2024 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 8/20/2024 | Approved | BOBBY KEY |
| Green Building Rough | 8/20/2024 | Approved | BOBBY KEY |
| Insulation | 8/20/2024 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 8/20/2024 | Partial Approval | BOBBY KEY |
| Drywall Nailing | 12/20/2024 | Approved | TEMISTOCLES CAAL |
| Drywall Nailing | 12/23/2024 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 1/31/2025 | No Access for Inspection | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 2/7/2025 | Not Ready for Inspection | MICHAEL ALLEN |
| Interior/Exterior Lathing | 5/19/2025 | Not Ready for Inspection | RUBEN RIVAS |
| Interior/Exterior Lathing | 9/4/2025 | Corrections Issued | RUBEN RIVAS |
| Interior/Exterior Lathing | 1/13/2026 | Approved | JESUS PINEDA |
| Shower Pan | 1/13/2026 | Approved | JESUS PINEDA |