2927 S RIDGELEY DR 90016

Certificate Information: 2927 S RIDGELEY DR 90016

Application / Permit
23014-10000-02567
Plan Check / Job No.
B23LA11847
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Addition to (E) 1-story SFD. All work per WFPP. "COMPLY WITH DEPARTMENT ORDER effective date 03/06/2023. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 12/19/2023
Issuing Office
Metro
Current Status
Issued on 12/19/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/28/2023 APPLICANT
Assigned to Plan Check Engineer 6/30/2023 MICHAEL LANZONE
Corrections Issued 7/2/2023 MICHAEL LANZONE
Building Plans Picked Up 9/11/2023 APPLICANT
Applicant returned to address corrections 12/4/2023 CRISTINA SALAZAR
Plan Check Approved 12/19/2023 CRISTINA SALAZAR
Issued 12/19/2023 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/30/2023 DAVID LOPEZ
Roof/Waste drainage to street Cleared 10/30/2023 DAVID LOPEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

LUIS CORRAL, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
DONALD WONG, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
KIM DOEPPING, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM MICHALAK, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/23/2024 Approved EUSEBIO GUZMAN
Footing/Foundation/Slab 3/12/2024 Not Ready for Inspection EUSEBIO GUZMAN
Footing/Foundation/Slab 3/18/2024 Not Ready for Inspection WILLIAM MICHALAK
BUILDING-Rough-Frame 4/3/2024 Not Ready for Inspection ENRIQUE PREZA
Footing/Foundation/Slab 4/3/2024 Corrections Issued ENRIQUE PREZA
Floor/Roof Diaphrgm/Shear Wall 4/23/2024 Not Ready for Inspection ENRIQUE PREZA
Interior/Exterior Lathing 4/23/2024 Not Ready for Inspection ENRIQUE PREZA
Deputy Drilled-In Anchors 4/25/2024 Partial Approval ENRIQUE PREZA
Footing/Foundation/Slab 4/26/2024 Approved ENRIQUE PREZA
BUILDING-Rough-Frame 5/22/2024 Not Ready for Inspection WILLIAM MICHALAK
Green Building Rough 5/22/2024 Partial Approval WILLIAM MICHALAK
PLUMBING-Rough 5/22/2024 Partial Approval WILLIAM MICHALAK
Insulation 5/24/2024 Partial Approval ENRIQUE PREZA
BUILDING-Rough-Frame 11/6/2024 Not Ready for Inspection WILLIAM MICHALAK
ELECTRICAL-Rough 11/6/2024 Approved WILLIAM MICHALAK
Green Building Rough 11/6/2024 Not Ready for Inspection WILLIAM MICHALAK
Insulation 11/18/2024 Approved LUIS CORRAL
Drywall Nailing 12/12/2024 Not Ready for Inspection WILLIAM MICHALAK
Floor/Roof Diaphrgm/Shear Wall 12/12/2024 Approved WILLIAM MICHALAK
Green Building Rough 12/12/2024 Not Ready for Inspection WILLIAM MICHALAK
Drywall Nailing 12/27/2024 Conditional Approval LUIS CORRAL
Green Building Rough 12/27/2024 Not Ready for Inspection LUIS CORRAL
Interior/Exterior Lathing 2/11/2025 Approved LUIS CORRAL
Shower Pan 4/3/2025 Approved LUIS CORRAL
Drywall Nailing 5/1/2025 Approved LUIS CORRAL
Final 5/1/2025 Corrections Issued LUIS CORRAL
Green Building Rough 5/1/2025 Approved LUIS CORRAL
Smoke Detectors 5/1/2025 Approved LUIS CORRAL
BUILDING-Rough-Frame 5/13/2025 Approved LUIS CORRAL
Final 5/13/2025 Not Ready for Inspection LUIS CORRAL
Green Building Final 5/13/2025 Corrections Issued LUIS CORRAL
SGSOV-Seismic Gas S/O Valve 5/13/2025 SGSOV Approved LUIS CORRAL