4449 N PETIT AVE 91436

Certificate Information: 4449 N PETIT AVE 91436

Application / Permit
23014-10000-02548
Plan Check / Job No.
B23LA11791
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: New 2-Story Single Family Dwelling with Basement & 2-Car Attached Garage. Fire Sprinklers Per NFPA13D thruout.
Permit Issued
Issued on 3/23/2024
Issuing Office
Current Status
CofO in Progress on 5/9/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/26/2023 APPLICANT
Assigned to Plan Check Engineer 6/29/2023 PRANITA SHAH
Corrections Issued 8/1/2023 PRANITA SHAH
Quality Review Completed 8/17/2023 GARO TELMI
Applicant returned to address corrections 9/18/2023 PRANITA SHAH
Applicant returned to address corrections 9/28/2023 PRANITA SHAH
Applicant returned to address corrections 10/5/2023 PRANITA SHAH
Applicant returned to address corrections 11/22/2023 PRANITA SHAH
Applicant returned to address corrections 11/29/2023 PRANITA SHAH
Applicant returned to address corrections 1/9/2024 PRANITA SHAH
Plan Check Approved 3/22/2024 PRANITA SHAH
Issued 3/23/2024 APPLICANT
CofO in Progress 5/9/2025 SEAN WIRCH

Permit Application Clearance Information

Address approval Cleared 7/25/2023 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 7/25/2023 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 7/25/2023 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 7/25/2023 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 7/25/2023 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 7/25/2023 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 7/25/2023 LEE GUILBEAUX
Sewer availability Cleared 7/25/2023 LEE GUILBEAUX
Hydrant and Access approval Cleared 8/25/2023 JOHN CONNEALLY
Excavation more than 5-ft deep Cleared 9/18/2023 CALOSHA APPROVED
GPI Written Notices Cleared 9/18/2023 PRANITA SHAH
Grading Pre-Inspection Cleared 9/18/2023 PRANITA SHAH
Low Impact Development (LID) Cleared 9/27/2023 ERNEST TSE
Roof/Waste drainage to street Cleared 9/27/2023 LEE GUILBEAUX

Contact Information

Architect Mccooey,, Yumiko M; Lic. No.: C36551 15021 VENTURA BLVD #1041      SHERMAN OAKS, CA 91403
Contractor Owner-Builder       ,
Engineer Castillo,, Margarito; Lic. No.: S4808 1205 PINE AVE   SUITE 201    LONG BEACH, CA 90813
Engineer Rybak,, Richard; Lic. No.: GE2131 20312 TAU PLACE      CHATSWORTH, CA 91311

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 3/28/2024 Approved VINCENT HANLEY
Pre-Inspection 3/28/2024 Approved VINCENT HANLEY
Footing/Foundation/Slab 5/9/2024 Partial Approval VINCENT HANLEY
Piling/Pier/Caisson 5/9/2024 Partial Approval VINCENT HANLEY
Excavation/Setback/Form/Re-Bar 5/20/2024 Corrections Issued THOMAS FINNILA
Deputy Drilled-In Anchors 5/28/2024 Partial Approval SEAN WIRCH
PLUMBING-Rough 5/28/2024 Partial Approval SEAN WIRCH
Excavation/Setback/Form/Re-Bar 6/7/2024 Not Ready for Inspection THOMAS FINNILA
Footing/Foundation/Slab 6/7/2024 Corrections Issued THOMAS FINNILA
Structural Steel Frame 6/7/2024 Not Ready for Inspection THOMAS FINNILA
Deputy Reinf. Concrete 6/17/2024 Approved THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 6/17/2024 Partial Approval THOMAS FINNILA
Footing/Foundation/Slab 6/17/2024 Partial Approval THOMAS FINNILA
Deputy Shotcrete 6/20/2024 Conditional Approval THOMAS FINNILA
Deputy Other (see comments) 7/1/2024 Conditional Approval THOMAS FINNILA
Footing/Foundation/Slab 7/2/2024 Conditional Approval THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 7/16/2024 Partial Approval THOMAS FINNILA
Deputy Wood Construction 7/17/2024 Conditional Approval THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 7/30/2024 Not Ready for Inspection GEVORK IPCHYAN
Wood Frame 7/30/2024 Not Ready for Inspection GEVORK IPCHYAN
Floor/Roof Diaphrgm/Shear Wall 8/1/2024 Partial Approval THOMAS FINNILA
Footing/Foundation/Slab 8/1/2024 Not Ready for Inspection THOMAS FINNILA
Wood Frame 8/1/2024 Not Ready for Inspection THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 8/5/2024 Corrections Issued THOMAS FINNILA
Footing/Foundation/Slab 8/9/2024 Not Ready for Inspection THOMAS FINNILA
Footing/Foundation/Slab 8/16/2024 Corrections Issued THOMAS FINNILA
Pre-Inspection 8/20/2024 Partial Approval THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 9/5/2024 Not Ready for Inspection THOMAS FINNILA
Deputy Wood Construction 9/6/2024 Conditional Approval THOMAS FINNILA
Wood Frame 9/23/2024 Corrections Issued THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 9/26/2024 Corrections Issued THOMAS FINNILA
Wood Frame 9/26/2024 Not Ready for Inspection THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 10/2/2024 Partial Approval KRISTEN CAUSEY
BUILDING-Rough-Frame 10/10/2024 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Rough 10/10/2024 Not Ready for Inspection THOMAS FINNILA
HVAC-Rough 10/10/2024 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 10/10/2024 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Rough 10/18/2024 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 10/18/2024 Approved THOMAS FINNILA
BUILDING-Rough-Frame 10/23/2024 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Rough 10/23/2024 Approved THOMAS FINNILA
HVAC-Rough 10/23/2024 Conditional Approval THOMAS FINNILA
Shower Pan 10/29/2024 Approved THOMAS FINNILA
BUILDING-Rough-Frame 10/31/2024 Not Ready for Inspection THOMAS FINNILA
Green Building Rough 10/31/2024 Not Ready for Inspection THOMAS FINNILA
Interior/Exterior Lathing 10/31/2024 Not Ready for Inspection THOMAS FINNILA
Verify Sprinkler Sign Off 10/31/2024 Not Ready for Inspection THOMAS FINNILA
Gas Test 11/5/2024 Approved THOMAS FINNILA
Interior/Exterior Lathing 11/5/2024 Approved THOMAS FINNILA
Wood Frame 11/5/2024 Approved THOMAS FINNILA
BUILDING-Rough-Frame 11/12/2024 Approved THOMAS FINNILA
Green Building Rough 11/12/2024 Approved THOMAS FINNILA
Insulation 11/12/2024 Approved THOMAS FINNILA
Verify Sprinkler Sign Off 11/12/2024 Approved THOMAS FINNILA
Drywall Nailing 11/26/2024 Approved MORRIS JACKSON
Excavation/Setback/Form/Re-Bar 1/8/2025 Approved THOMAS FINNILA
Deputy Drilled-In Anchors 1/9/2025 Partial Approval SEAN WIRCH
PLUMBING-Final 3/25/2025 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Final 3/27/2025 Approved MORRIS JACKSON
ELECTRICAL-Final 4/18/2025 Approved SEAN WIRCH
HVAC-Final 4/18/2025 Approved SEAN WIRCH
Final 5/8/2025 OK to Issue CofO SEAN WIRCH
Footing/Foundation/Slab 5/8/2025 Approved SEAN WIRCH
Green Building Final 5/8/2025 Approved SEAN WIRCH
SGSOV-Seismic Gas S/O Valve 5/8/2025 SGSOV Approved SEAN WIRCH
Service/Power Release 5/8/2025 Approved SEAN WIRCH
Smoke Detectors 5/8/2025 Approved SEAN WIRCH