4449 N PETIT AVE 91436
Certificate Information: 4449 N PETIT AVE 91436
- Application / Permit
- 23014-10000-02548
- Plan Check / Job No.
- B23LA11791
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: New 2-Story Single Family Dwelling with Basement & 2-Car Attached Garage. Fire Sprinklers Per NFPA13D thruout.
- Permit Issued
- Issued on 3/23/2024
- Issuing Office
- Current Status
- CofO in Progress on 5/9/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/26/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/29/2023 | PRANITA SHAH |
| Corrections Issued | 8/1/2023 | PRANITA SHAH |
| Quality Review Completed | 8/17/2023 | GARO TELMI |
| Applicant returned to address corrections | 9/18/2023 | PRANITA SHAH |
| Applicant returned to address corrections | 9/28/2023 | PRANITA SHAH |
| Applicant returned to address corrections | 10/5/2023 | PRANITA SHAH |
| Applicant returned to address corrections | 11/22/2023 | PRANITA SHAH |
| Applicant returned to address corrections | 11/29/2023 | PRANITA SHAH |
| Applicant returned to address corrections | 1/9/2024 | PRANITA SHAH |
| Plan Check Approved | 3/22/2024 | PRANITA SHAH |
| Issued | 3/23/2024 | APPLICANT |
| CofO in Progress | 5/9/2025 | SEAN WIRCH |
Permit Application Clearance Information
| Address approval | Cleared | 7/25/2023 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 7/25/2023 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 7/25/2023 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 7/25/2023 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 7/25/2023 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 7/25/2023 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 7/25/2023 | LEE GUILBEAUX |
| Sewer availability | Cleared | 7/25/2023 | LEE GUILBEAUX |
| Hydrant and Access approval | Cleared | 8/25/2023 | JOHN CONNEALLY |
| Excavation more than 5-ft deep | Cleared | 9/18/2023 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 9/18/2023 | PRANITA SHAH |
| Grading Pre-Inspection | Cleared | 9/18/2023 | PRANITA SHAH |
| Low Impact Development (LID) | Cleared | 9/27/2023 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 9/27/2023 | LEE GUILBEAUX |
Contact Information
| Architect | Mccooey,, Yumiko M; Lic. No.: C36551 | 15021 VENTURA BLVD #1041 SHERMAN OAKS, CA 91403 |
| Contractor | Owner-Builder | , |
| Engineer | Castillo,, Margarito; Lic. No.: S4808 | 1205 PINE AVE SUITE 201 LONG BEACH, CA 90813 |
| Engineer | Rybak,, Richard; Lic. No.: GE2131 | 20312 TAU PLACE CHATSWORTH, CA 91311 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 3/28/2024 | Approved | VINCENT HANLEY |
| Pre-Inspection | 3/28/2024 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 5/9/2024 | Partial Approval | VINCENT HANLEY |
| Piling/Pier/Caisson | 5/9/2024 | Partial Approval | VINCENT HANLEY |
| Excavation/Setback/Form/Re-Bar | 5/20/2024 | Corrections Issued | THOMAS FINNILA |
| Deputy Drilled-In Anchors | 5/28/2024 | Partial Approval | SEAN WIRCH |
| PLUMBING-Rough | 5/28/2024 | Partial Approval | SEAN WIRCH |
| Excavation/Setback/Form/Re-Bar | 6/7/2024 | Not Ready for Inspection | THOMAS FINNILA |
| Footing/Foundation/Slab | 6/7/2024 | Corrections Issued | THOMAS FINNILA |
| Structural Steel Frame | 6/7/2024 | Not Ready for Inspection | THOMAS FINNILA |
| Deputy Reinf. Concrete | 6/17/2024 | Approved | THOMAS FINNILA |
| Excavation/Setback/Form/Re-Bar | 6/17/2024 | Partial Approval | THOMAS FINNILA |
| Footing/Foundation/Slab | 6/17/2024 | Partial Approval | THOMAS FINNILA |
| Deputy Shotcrete | 6/20/2024 | Conditional Approval | THOMAS FINNILA |
| Deputy Other (see comments) | 7/1/2024 | Conditional Approval | THOMAS FINNILA |
| Footing/Foundation/Slab | 7/2/2024 | Conditional Approval | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 7/16/2024 | Partial Approval | THOMAS FINNILA |
| Deputy Wood Construction | 7/17/2024 | Conditional Approval | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 7/30/2024 | Not Ready for Inspection | GEVORK IPCHYAN |
| Wood Frame | 7/30/2024 | Not Ready for Inspection | GEVORK IPCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/1/2024 | Partial Approval | THOMAS FINNILA |
| Footing/Foundation/Slab | 8/1/2024 | Not Ready for Inspection | THOMAS FINNILA |
| Wood Frame | 8/1/2024 | Not Ready for Inspection | THOMAS FINNILA |
| Excavation/Setback/Form/Re-Bar | 8/5/2024 | Corrections Issued | THOMAS FINNILA |
| Footing/Foundation/Slab | 8/9/2024 | Not Ready for Inspection | THOMAS FINNILA |
| Footing/Foundation/Slab | 8/16/2024 | Corrections Issued | THOMAS FINNILA |
| Pre-Inspection | 8/20/2024 | Partial Approval | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 9/5/2024 | Not Ready for Inspection | THOMAS FINNILA |
| Deputy Wood Construction | 9/6/2024 | Conditional Approval | THOMAS FINNILA |
| Wood Frame | 9/23/2024 | Corrections Issued | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 9/26/2024 | Corrections Issued | THOMAS FINNILA |
| Wood Frame | 9/26/2024 | Not Ready for Inspection | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 10/2/2024 | Partial Approval | KRISTEN CAUSEY |
| BUILDING-Rough-Frame | 10/10/2024 | Not Ready for Inspection | THOMAS FINNILA |
| ELECTRICAL-Rough | 10/10/2024 | Not Ready for Inspection | THOMAS FINNILA |
| HVAC-Rough | 10/10/2024 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Rough | 10/10/2024 | Not Ready for Inspection | THOMAS FINNILA |
| ELECTRICAL-Rough | 10/18/2024 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Rough | 10/18/2024 | Approved | THOMAS FINNILA |
| BUILDING-Rough-Frame | 10/23/2024 | Not Ready for Inspection | THOMAS FINNILA |
| ELECTRICAL-Rough | 10/23/2024 | Approved | THOMAS FINNILA |
| HVAC-Rough | 10/23/2024 | Conditional Approval | THOMAS FINNILA |
| Shower Pan | 10/29/2024 | Approved | THOMAS FINNILA |
| BUILDING-Rough-Frame | 10/31/2024 | Not Ready for Inspection | THOMAS FINNILA |
| Green Building Rough | 10/31/2024 | Not Ready for Inspection | THOMAS FINNILA |
| Interior/Exterior Lathing | 10/31/2024 | Not Ready for Inspection | THOMAS FINNILA |
| Verify Sprinkler Sign Off | 10/31/2024 | Not Ready for Inspection | THOMAS FINNILA |
| Gas Test | 11/5/2024 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 11/5/2024 | Approved | THOMAS FINNILA |
| Wood Frame | 11/5/2024 | Approved | THOMAS FINNILA |
| BUILDING-Rough-Frame | 11/12/2024 | Approved | THOMAS FINNILA |
| Green Building Rough | 11/12/2024 | Approved | THOMAS FINNILA |
| Insulation | 11/12/2024 | Approved | THOMAS FINNILA |
| Verify Sprinkler Sign Off | 11/12/2024 | Approved | THOMAS FINNILA |
| Drywall Nailing | 11/26/2024 | Approved | MORRIS JACKSON |
| Excavation/Setback/Form/Re-Bar | 1/8/2025 | Approved | THOMAS FINNILA |
| Deputy Drilled-In Anchors | 1/9/2025 | Partial Approval | SEAN WIRCH |
| PLUMBING-Final | 3/25/2025 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Final | 3/27/2025 | Approved | MORRIS JACKSON |
| ELECTRICAL-Final | 4/18/2025 | Approved | SEAN WIRCH |
| HVAC-Final | 4/18/2025 | Approved | SEAN WIRCH |
| Final | 5/8/2025 | OK to Issue CofO | SEAN WIRCH |
| Footing/Foundation/Slab | 5/8/2025 | Approved | SEAN WIRCH |
| Green Building Final | 5/8/2025 | Approved | SEAN WIRCH |
| SGSOV-Seismic Gas S/O Valve | 5/8/2025 | SGSOV Approved | SEAN WIRCH |
| Service/Power Release | 5/8/2025 | Approved | SEAN WIRCH |
| Smoke Detectors | 5/8/2025 | Approved | SEAN WIRCH |