1130 N BUNDY DR 90049
Certificate Information: 1130 N BUNDY DR 90049
- Application / Permit
- 23014-10000-02524
- Plan Check / Job No.
- B23LA11709
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan** GROUND FLOOR ADDITION TO (E) 2-STORY SFD WITH INTERIOR STR. REMODEL.
- Permit Issued
- Issued on 10/16/2023
- Issuing Office
- Current Status
- CofO Issued on 6/3/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/24/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/29/2023 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 7/9/2023 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 7/14/2023 | GARO TELMI |
| Plan Check Approved | 10/12/2023 | MAHNAZ NOURHASHEMI |
| Issued | 10/16/2023 | APPLICANT |
| CofO in Progress | 5/27/2025 | CARLOS MATAMOROS |
| Permit Finaled | 6/3/2025 | RICHARD STEINBACH |
| CofO Issued | 6/3/2025 | RICHARD STEINBACH |
| Permit Finaled | 6/3/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| ZA Case | Cleared | 8/8/2023 | KENTON TRINH |
| Eng Process Fee Ord 176,300 | Cleared | 8/15/2023 | DARIN LAM |
| Low Impact Development (LID) | Cleared | 8/17/2023 | SHAHIN KHAZEY |
| Roof/Waste drainage to street | Cleared | 9/3/2023 | AHMED AMARRAGY |
| Grading Pre-Inspection | Cleared | 9/29/2023 | MAHNAZ NOURHASHEMI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khanlou,, Amir; Lic. No.: C87550 | 2603 BASIL LN LOS ANGELES, CA 90077 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/13/2023 | Approved | RICHARD STEINBACH |
| FLOOD-Proofing Certificate | 2/13/2024 | Approved | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 2/13/2024 | Approved | CARLOS MATAMOROS |
| PLUMBING-Rough | 2/13/2024 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 3/11/2024 | Corrections Issued | CARLOS MATAMOROS |
| HVAC-Rough | 3/11/2024 | Corrections Issued | CARLOS MATAMOROS |
| PLUMBING-Rough | 3/13/2024 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 3/18/2024 | Approved | CARLOS MATAMOROS |
| HVAC-Rough | 3/18/2024 | Approved | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 3/21/2024 | Approved | CARLOS MATAMOROS |
| Green Building Rough | 3/21/2024 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 4/5/2024 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Final | 8/19/2024 | Corrections Issued | CARLOS MATAMOROS |
| HVAC-Final | 8/19/2024 | Corrections Issued | CARLOS MATAMOROS |
| PLUMBING-Final | 8/19/2024 | Corrections Issued | CARLOS MATAMOROS |
| Final | 9/9/2024 | Corrections Issued | CARLOS MATAMOROS |
| Green Building Final | 9/9/2024 | Not Ready for Inspection | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 9/9/2024 | SGSOV Approved | CARLOS MATAMOROS |
| Smoke Detectors | 9/9/2024 | Not Ready for Inspection | CARLOS MATAMOROS |
| Final | 2/3/2025 | Corrections Issued | CARLOS MATAMOROS |
| Green Building Final | 2/3/2025 | Approved | CARLOS MATAMOROS |
| Smoke Detectors | 2/3/2025 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Final | 3/24/2025 | Approved | CARLOS MATAMOROS |
| Final | 3/24/2025 | Corrections Issued | CARLOS MATAMOROS |
| HVAC-Final | 3/24/2025 | Approved | CARLOS MATAMOROS |
| PLUMBING-Final | 3/24/2025 | Approved | CARLOS MATAMOROS |
| Final | 5/27/2025 | OK to Issue CofO | CARLOS MATAMOROS |