5605 S CIMARRON ST 90062
Certificate Information: 5605 S CIMARRON ST 90062
- Application / Permit
- 23014-10000-02464
- Plan Check / Job No.
- B23LA11381
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan: CONVERT (E) DETACHED 20' x 20' GARAGE WITH IRREG.SHAPED 36'-6" x 18' ADDITION INTO A NEW DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d).
- Permit Issued
- Issued on 1/17/2024
- Issuing Office
- Current Status
- CofO Issued on 10/23/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/21/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/26/2023 | JOHNPAUL ISIP |
| Corrections Issued | 6/27/2023 | JOHNPAUL ISIP |
| Applicant returned to address corrections | 12/13/2023 | JOHNPAUL ISIP |
| Applicant returned to address corrections | 12/14/2023 | MIROOSH KHACHATOORIAN |
| Applicant returned to address corrections | 12/18/2023 | MIROOSH KHACHATOORIAN |
| Plan Check Approved | 12/29/2023 | MIROOSH KHACHATOORIAN |
| Issued | 1/17/2024 | APPLICANT |
| CofO in Progress | 10/20/2025 | RAUL BARAJAS |
| Permit Finaled | 10/23/2025 | DEROLD HAUFF |
| CofO Issued | 10/23/2025 | DEROLD HAUFF |
| Permit Finaled | 10/23/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/14/2023 | JESSICA OPINION |
| Construction near power lines | Cleared | 9/27/2023 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 11/14/2023 | JESSICA OPINION |
| Sewer availability | Cleared | 11/14/2023 | JESSICA OPINION |
| Low Impact Development (LID) | Cleared | 12/5/2023 | SAMUEL LINN |
| Roof/Waste drainage to street | Cleared | 12/7/2023 | JESSICA OPINION |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/16/2024 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Rough | 5/20/2024 | Corrections Issued | CRAIG DAVIS |
| Footing/Foundation/Slab | 7/3/2024 | Corrections Issued | CRAIG DAVIS |
| Footing/Foundation/Slab | 7/9/2024 | Approved | CRAIG DAVIS |
| ELECTRICAL-Rough | 10/1/2024 | Corrections Issued | CRAIG DAVIS |
| PLUMBING-Rough | 10/1/2024 | Not Ready for Inspection | CRAIG DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 12/6/2024 | Approved | JOSE MACIAS |
| HVAC-Rough | 12/6/2024 | Corrections Issued | JOSE MACIAS |
| ELECTRICAL-Rough | 12/17/2024 | Corrections Issued | BARRY HACHE |
| HVAC-Rough | 12/17/2024 | Corrections Issued | BARRY HACHE |
| PLUMBING-Rough | 12/17/2024 | Corrections Issued | BARRY HACHE |
| ELECTRICAL-Rough | 1/14/2025 | No Access for Inspection | BARRY HACHE |
| HVAC-Rough | 1/14/2025 | No Access for Inspection | BARRY HACHE |
| ELECTRICAL-Rough | 1/17/2025 | Corrections Issued | BARRY HACHE |
| HVAC-Rough | 1/17/2025 | Corrections Issued | BARRY HACHE |
| PLUMBING-Rough | 1/17/2025 | Corrections Issued | BARRY HACHE |
| Floor/Roof Diaphrgm/Shear Wall | 2/21/2025 | Approved | MICHAEL LEWIS |
| Interior/Exterior Lathing | 2/28/2025 | Approved | BARRY HACHE |
| ELECTRICAL-Rough | 4/15/2025 | Not Ready for Inspection | BARRY HACHE |
| HVAC-Rough | 4/15/2025 | Approved | BARRY HACHE |
| PLUMBING-Rough | 4/15/2025 | Not Ready for Inspection | BARRY HACHE |
| Deputy Drilled-In Anchors | 4/25/2025 | Conditional Approval | ANTHONY RAMOS |
| Rough-Elec/Plmb/HVAC | 6/6/2025 | Not Ready for Inspection | BARRY HACHE |
| Rough-Elec/Plmb/HVAC | 6/10/2025 | Approved | BARRY HACHE |
| BUILDING-Rough-Frame | 6/11/2025 | Corrections Issued | BARRY HACHE |
| Green Building Rough | 6/11/2025 | Approved | BARRY HACHE |
| BUILDING-Rough-Frame | 6/12/2025 | Corrections Issued | BARRY HACHE |
| Insulation | 6/12/2025 | Not Ready for Inspection | BARRY HACHE |
| BUILDING-Rough-Frame | 6/16/2025 | Approved | BARRY HACHE |
| Green Building Rough | 6/16/2025 | Approved | BARRY HACHE |
| Insulation | 6/16/2025 | Approved | BARRY HACHE |
| Drywall Nailing | 6/20/2025 | Corrections Issued | ANTHONY RAMOS |
| Drywall Nailing | 6/26/2025 | Approved | RONNIE MEDINA |
| SGSOV-Seismic Gas S/O Valve | 7/30/2025 | SGSOV Not Ready | BARRY HACHE |
| Final | 7/31/2025 | Corrections Issued | BARRY HACHE |
| Final | 8/21/2025 | Corrections Issued | BARRY HACHE |
| ELECTRICAL-Final | 9/23/2025 | Corrections Issued | BARRY HACHE |
| Green Building Final | 9/23/2025 | Corrections Issued | BARRY HACHE |
| ELECTRICAL-Final | 9/26/2025 | Corrections Issued | BARRY HACHE |
| Green Building Final | 9/26/2025 | Corrections Issued | BARRY HACHE |
| HVAC-Final | 9/26/2025 | Corrections Issued | BARRY HACHE |
| PLUMBING-Final | 9/26/2025 | Approved | BARRY HACHE |
| ELECTRICAL-Final | 9/30/2025 | Not Ready for Inspection | BARRY HACHE |
| HVAC-Final | 9/30/2025 | Corrections Issued | BARRY HACHE |
| SGSOV-Seismic Gas S/O Valve | 9/30/2025 | SGSOV Approved | BARRY HACHE |
| Smoke Detectors | 9/30/2025 | Approved | BARRY HACHE |
| Final | 10/2/2025 | Corrections Issued | BARRY HACHE |
| Green Building Final | 10/2/2025 | Approved | BARRY HACHE |
| HVAC-Final | 10/2/2025 | Approved | BARRY HACHE |
| Final | 10/8/2025 | Conditional Approval | BARRY HACHE |
| Final | 10/16/2025 | OK to Issue CofO | RAUL BARAJAS |