14618 S ORCHARD AVE 90247
Certificate Information: 14618 S ORCHARD AVE 90247
- Application / Permit
- 23014-10000-02461
- Plan Check / Job No.
- B23LA11374
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Proposed to add 540 sq.ft. consisting in two bedrooms, one 3/4 bath, new Water Heater, new Wall Furnace, new Laundry Room, Relocate (E) kitchen, convert (E) kitchen into Dining Area. Extend (E) Porch 32 sq.ft.
- Permit Issued
- Issued on 4/18/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/20/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/21/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/26/2023 | ALFREDO JARA |
| Corrections Issued | 6/27/2023 | ALFREDO JARA |
| Applicant returned to address corrections | 3/26/2024 | KHUONG TRUONG |
| Plan Check Approved | 4/8/2024 | NGHI SU |
| Issued | 4/18/2024 | APPLICANT |
| CofO in Progress | 3/19/2025 | EUGENE CASSIDY |
| Permit Finaled | 3/20/2025 | ANSON MAGLASANG |
| CofO Issued | 3/20/2025 | ANSON MAGLASANG |
| Permit Finaled | 3/20/2025 | ANSON MAGLASANG |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/5/2023 | ERIK BEASLEY |
| Low Impact Development (LID) | Cleared | 1/22/2024 | LUIS CRUZ |
| Roof/Waste drainage to street | Cleared | 1/24/2024 | ERIK BEASLEY |
| Sewer availability | Cleared | 2/26/2024 | ERIK BEASLEY |
Contact Information
| Contractor | A A C R General Construction Inc; Lic. No.: 1067064-B | 8060 E FLORENCE AVE STE 211 DOWNEY, CA 90241 |
| Engineer | Abarquez,, Jose Munoz; Lic. No.: C51994 | 18 EL CORZO RANCHO SANTA MARGARITA, CA 92688 |
| Engineer | Abarquez,, Jose Munoz; Lic. No.: NA51994 | , |
Inspector Information
| BEN MOLSTAD, (310) 732-4557 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/14/2024 | Corrections Issued | JAMES CHAVEZ |
| METHANE-Barrier | 5/14/2024 | Approved | JAMES CHAVEZ |
| METHANE-Subgrade | 5/14/2024 | Approved | JAMES CHAVEZ |
| Footing/Foundation/Slab | 5/17/2024 | Corrections Issued | JAMES CHAVEZ |
| Footing/Foundation/Slab | 5/22/2024 | Approved | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/13/2024 | Partial Approval | JAMES CHAVEZ |
| Insulation | 6/13/2024 | Partial Approval | JAMES CHAVEZ |
| PLUMBING-Rough | 6/13/2024 | Partial Approval | JAMES CHAVEZ |
| Service/Power Release | 7/8/2024 | Approved | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 8/5/2024 | Partial Approval | JOSEPH MCGARRY |
| Green Building Rough | 8/5/2024 | Not Ready for Inspection | JOSEPH MCGARRY |
| MERV13>=Rough | 8/5/2024 | Not Ready for Inspection | JOSEPH MCGARRY |
| METHANE-Rough | 8/5/2024 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 8/16/2024 | Partial Approval | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 8/16/2024 | Approved | JOSEPH MCGARRY |
| Green Building Rough | 8/16/2024 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 8/16/2024 | Approved | JOSEPH MCGARRY |
| MERV13>=Rough | 8/16/2024 | Approved | JOSEPH MCGARRY |
| PLUMBING-Rough | 8/16/2024 | Conditional Approval | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 8/29/2024 | Approved | JOSEPH MCGARRY |
| Insulation | 8/29/2024 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 8/29/2024 | Partial Approval | JOSEPH MCGARRY |
| Drywall Nailing | 9/12/2024 | Approved | BEN MOLSTAD |
| Final | 12/18/2024 | Corrections Issued | BEN MOLSTAD |
| Green Building Final | 12/18/2024 | Approved | BEN MOLSTAD |
| MERV13>=Final | 12/18/2024 | Approved | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 12/18/2024 | SGSOV Not Ready | BEN MOLSTAD |
| Smoke Detectors | 12/18/2024 | Corrections Issued | BEN MOLSTAD |
| Final | 12/24/2024 | Corrections Issued | ANSON MAGLASANG |
| SGSOV-Seismic Gas S/O Valve | 12/24/2024 | SGSOV Approved | ANSON MAGLASANG |
| Smoke Detectors | 12/24/2024 | Approved | ANSON MAGLASANG |
| Final | 3/10/2025 | Corrections Issued | BEN MOLSTAD |
| Final | 3/13/2025 | Not Ready for Inspection | BEN MOLSTAD |
| ELECTRICAL-Final | 3/18/2025 | Approved | EUGENE CASSIDY |
| Final | 3/18/2025 | OK to Issue CofO | EUGENE CASSIDY |
| HVAC-Final | 3/18/2025 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 3/18/2025 | Approved | EUGENE CASSIDY |