4431 S 11TH AVE 90043
Certificate Information: 4431 S 11TH AVE 90043
- Application / Permit
- 23014-10000-02449
- Plan Check / Job No.
- B23LA11318
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED MASTER BEDROOM / CLOSET/ BATHROOM ADDITION AT REAR OF (E) SFD. CONSTRUCTION PER W.F.P.P.
- Permit Issued
- Issued on 12/1/2023
- Issuing Office
- Metro
- Current Status
- Issued on 12/1/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/20/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/26/2023 | LAWRENCE QUIRANTE |
| Corrections Issued | 6/27/2023 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 6/30/2023 | APPLICANT |
| Applicant returned to address corrections | 11/28/2023 | WEIJIAN HUANG |
| Plan Check Approved | 11/30/2023 | ADAM HEGAZI |
| Issued | 12/1/2023 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 7/24/2023 | NEIL TUANO |
| Sewer availability | Cleared | 7/24/2023 | NEIL TUANO |
| Low Impact Development (LID) | Cleared | 8/21/2023 | SAMUEL LINN |
| Eng Process Fee Ord 176,300 | Cleared | 9/19/2023 | NEIL TUANO |
| Construction near power lines | Cleared | 9/27/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/4/2023 | Partial Inspection | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 1/2/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Footing/Foundation/Slab | 1/2/2024 | Corrections Issued | ANTHONY EGSON |
| Deputy Drilled-In Anchors | 1/5/2024 | Approved | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 1/9/2024 | Approved | ANTHONY EGSON |
| Footing/Foundation/Slab | 1/9/2024 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/26/2024 | Corrections Issued | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/31/2024 | Partial Approval | ANTHONY EGSON |
| Insulation | 2/2/2024 | Partial Approval | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/7/2024 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 2/27/2024 | Corrections Issued | ANTHONY EGSON |
| FLOOD-Proofing Certificate | 2/27/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/27/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Rough | 2/27/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Wood Frame | 2/27/2024 | Not Ready for Inspection | ANTHONY EGSON |
| BUILDING-Rough-Frame | 4/1/2024 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Rough | 4/1/2024 | Corrections Issued | ANTHONY EGSON |
| FLOOD-Proofing Certificate | 4/1/2024 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 4/1/2024 | Approved | ANTHONY EGSON |
| Green Building Rough | 4/1/2024 | Not Ready for Inspection | ANTHONY EGSON |
| HVAC-Rough | 4/1/2024 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Rough | 4/1/2024 | Partial Approval | ANTHONY EGSON |
| BUILDING-Rough-Frame | 4/19/2024 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Rough | 4/19/2024 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 4/19/2024 | Partial Approval | ANTHONY EGSON |
| Green Building Rough | 4/19/2024 | Approved | ANTHONY EGSON |
| PLUMBING-Rough | 4/19/2024 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 5/7/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/7/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Wood Frame | 5/7/2024 | Partial Approval | ANTHONY EGSON |
| BUILDING-Rough-Frame | 5/14/2024 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/14/2024 | Approved | ANTHONY EGSON |
| HVAC-Rough | 5/14/2024 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 5/20/2024 | Partial Approval | JOSH MEISTER |
| Insulation | 5/24/2024 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 5/24/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Shower Pan | 5/24/2024 | Approved | ANTHONY EGSON |
| Drywall Nailing | 6/5/2024 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 6/5/2024 | Approved | ANTHONY EGSON |