6743 S 7TH AVE 90043
Certificate Information: 6743 S 7TH AVE 90043
- Application / Permit
- 23014-10000-02428
- Plan Check / Job No.
- B23LA11260
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN New addition 247 Sq.f. to existing duplex
- Permit Issued
- Issued on 6/11/2024
- Issuing Office
- Current Status
- Issued on 6/11/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/19/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/23/2023 | MOHAMMAD ESMAILI |
| Corrections Issued | 6/23/2023 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 10/11/2023 | GIOVANNY CHAVEZ |
| Applicant returned to address corrections | 10/20/2023 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 11/6/2023 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 12/7/2023 | MOHAMMAD ESMAILI |
| Plan Check Approved | 12/7/2023 | MOHAMMAD ESMAILI |
| No Progress | 12/7/2023 | MOHAMMAD ESMAILI |
| Plan Check Approved | 5/8/2024 | MOHAMMAD ESMAILI |
| Issued | 6/11/2024 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 8/9/2023 | NEIL TUANO |
| Eng Process Fee Ord 176,300 | Cleared | 8/14/2023 | NEIL TUANO |
| Sewer availability | Cleared | 8/14/2023 | NEIL TUANO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Chen,, Yeshen Jason; Lic. No.: C40169 | 20601 ALDA CT WALNUT, CA 91789 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/13/2024 | Corrections Issued | AMIR NAZARIAN |
| Excavation/Setback/Form/Re-Bar | 12/20/2024 | Not Ready for Inspection | JOHN QUINTANILLA |
| PLUMBING-Rough | 12/20/2024 | Not Ready for Inspection | JOHN QUINTANILLA |
| Excavation/Setback/Form/Re-Bar | 12/24/2024 | Approved | AMIR NAZARIAN |
| PLUMBING-Rough | 12/24/2024 | Partial Approval | AMIR NAZARIAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/24/2025 | Partial Approval | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 3/26/2025 | Partial Approval | MICHAEL LEWIS |
| Insulation | 3/26/2025 | Partial Approval | MICHAEL LEWIS |
| Wood Frame | 4/22/2025 | Approved | WAYNE REGESTER |
| ELECTRICAL-Rough | 9/30/2025 | Corrections Issued | SALVADOR MARTINEZ |
| HVAC-Rough | 9/30/2025 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Rough | 9/30/2025 | Corrections Issued | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 10/3/2025 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Rough | 10/3/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Special/Order Compliance | 10/3/2025 | Corrections Issued | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 2/5/2026 | Corrections Issued | SALVADOR MARTINEZ |
| HVAC-Rough | 2/5/2026 | Corrections Issued | SALVADOR MARTINEZ |
| Interior/Exterior Lathing | 2/5/2026 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Rough | 2/5/2026 | Corrections Issued | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 2/10/2026 | Corrections Issued | SALVADOR MARTINEZ |
| HVAC-Rough | 2/10/2026 | Corrections Issued | SALVADOR MARTINEZ |
| Interior/Exterior Lathing | 2/10/2026 | Partial Approval | SALVADOR MARTINEZ |
| PLUMBING-Rough | 2/10/2026 | Corrections Issued | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 2/17/2026 | Conditional Approval | SALVADOR MARTINEZ |
| HVAC-Rough | 2/17/2026 | Approved | SALVADOR MARTINEZ |
| PLUMBING-Rough | 2/17/2026 | Approved | SALVADOR MARTINEZ |
| Insulation | 2/27/2026 | Approved | SALVADOR MARTINEZ |
| Drywall Nailing | 3/6/2026 | Corrections Issued | GEM DE OCAMPO |
| Interior/Exterior Lathing | 3/6/2026 | Approved | GEM DE OCAMPO |