1070 N SOMERA ROAD 90077

Certificate Information: 1070 N SOMERA ROAD 90077

Application / Permit
23014-10000-02394
Plan Check / Job No.
B23LA11110
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
*EPLAN* GROUND FLOOR ADDTION AND INTERIOR REMODEL TO (E) 1-STORY SFD WITH ATTACHED 2-CAR GARAGE AND COVERED PATIO.
Permit Issued
Issued on 3/11/2024
Issuing Office
Current Status
Issued on 3/11/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/18/2023 APPLICANT
Assigned to Plan Check Engineer 7/6/2023 VIVIAN LAO
Corrections Issued 7/13/2023 VIVIAN LAO
Quality Review Completed 7/13/2023 GARO TELMI
Applicant returned to address corrections 8/25/2023 VIVIAN LAO
Applicant returned to address corrections 9/28/2023 VIVIAN LAO
Plan Check Approved 11/27/2023 VIVIAN LAO
Issued 3/11/2024 APPLICANT

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 7/26/2023 DARIN LAM
BHO/Hillside ordinance Cleared 7/26/2023 DARIN LAM
BHO/Hillside ordinance Cleared 7/26/2023 DARIN LAM
BHO/Hillside ordinance Cleared 8/4/2023 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 8/16/2023 DARIN LAM
Sewer availability Cleared 8/16/2023 DARIN LAM
BHO/Hillside ordinance Cleared 11/7/2023 DINAH GARIN
Roof/Waste drainage to street Cleared 11/13/2023 DARIN LAM
Grading Pre-Inspection Cleared 11/20/2023 ROBERT HUGHES

Contact Information

Architect , ; Lic. No.: C40202       ,
Contractor Canan Development Inc; Lic. No.: 891167-B       ,
Engineer Youm,, Moung Han; Lic. No.: C74086 309 S BERENDO ST APT 6      LOS ANGELES, CA 90020

Inspector Information

RYAN SALAZAR, (310) 914-3862 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/4/2024 Corrections Issued CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 4/10/2024 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 4/17/2024 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 4/17/2024 Partial Approval CHRISTOPHER WILSON
Deputy Drilled-In Anchors 6/13/2024 Conditional Approval CHRISTOPHER WILSON
Deputy Steel/Welding 6/13/2024 Conditional Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 6/28/2024 Approved CHRISTOPHER WILSON
PLUMBING-Rough 3/25/2025 Corrections Issued CHRISTOPHER WILSON
PLUMBING-Rough 7/24/2025 Approved EVAN COOPER
ELECTRICAL-Rough 7/25/2025 Corrections Issued CHRISTOPHER WILSON
HVAC-Rough 7/31/2025 Corrections Issued TEMISTOCLES CAAL
ELECTRICAL-Rough 8/15/2025 Approved CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 8/15/2025 Corrections Issued CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 8/19/2025 Partial Approval CHRISTOPHER WILSON
HVAC-Rough 9/16/2025 Not Ready for Inspection CHRISTOPHER WILSON
BUILDING-Rough-Frame 10/3/2025 Corrections Issued CARLOS MATAMOROS
Green Building Rough 10/3/2025 Not Ready for Inspection CARLOS MATAMOROS
HVAC-Rough 10/3/2025 Corrections Issued CARLOS MATAMOROS
Green Building Rough 10/20/2025 Not Ready for Inspection CARLOS MATAMOROS
HVAC-Rough 10/20/2025 Corrections Issued CARLOS MATAMOROS
BUILDING-Rough-Frame 10/29/2025 Approved CARLOS MATAMOROS
Green Building Rough 10/29/2025 Approved CARLOS MATAMOROS
HVAC-Rough 10/29/2025 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 10/29/2025 Partial Approval CARLOS MATAMOROS
Insulation 11/14/2025 Approved SEAN HAUPT
Shower Pan 11/14/2025 Not Ready for Inspection SEAN HAUPT
Drywall Nailing 1/13/2026 Approved CHRISTOPHER WILSON
Shower Pan 3/24/2026 Approved CHRISTOPHER WILSON
Gas Test 6/9/2026 Approved RYAN SALAZAR
Interior/Exterior Lathing 6/9/2026 Partial Approval RYAN SALAZAR