- ePlan FIRE DAMAGE REPAIR. RELOCATE EXISTING KITCHEN TO REAR. ADD BATHROOM AT SECOND FLOOR. SMALL ADDITION AT MASTER BEDROOM ON SECOND FLOOR. REPLACE ALL WINDOWS AND DOORS, ALL NEW FIXTURES, ALL NEW APPLIANCES. NEW TRELLIS ATTACHED TO SFD
- Permit Issued
- Issued on 10/31/2023
- Issuing Office
- Current Status
- Issued on 10/31/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/14/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/6/2023 | JAD BASMA |
| Corrections Issued | 7/14/2023 | JAD BASMA |
| Quality Review Completed | 7/20/2023 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 8/2/2023 | JAD BASMA |
| Applicant returned to address corrections | 8/3/2023 | JAD BASMA |
| Plan Check Approved | 8/3/2023 | JAD BASMA |
| Issued | 10/31/2023 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 7/22/2023 | CELINA MORENO |
| Sewer availability | Cleared | 7/22/2023 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 7/25/2023 | CELINA MORENO |
| HPOZ | Cleared | 7/25/2023 | DANIEL MATA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Rhee,, Kyle; Lic. No.: NA78215 | , |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/26/2024 | Partial Inspection | SABAS ALONSO |
| Deputy Drilled-In Anchors | 8/29/2024 | Conditional Approval | SABAS ALONSO |
| Deputy Drilled-In Anchors | 3/28/2025 | Approved | SABAS ALONSO |
| Footing/Foundation/Slab | 3/28/2025 | Approved | SABAS ALONSO |
| Special/Order Compliance | 12/29/2025 | Corrections Issued | SABAS ALONSO |
| ELECTRICAL-Rough | 2/26/2026 | Approved | SABAS ALONSO |
| HVAC-Rough | 2/26/2026 | Corrections Issued | SABAS ALONSO |
| PLUMBING-Rough | 2/26/2026 | Approved | SABAS ALONSO |
| HVAC-Rough | 4/14/2026 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 4/28/2026 | Approved | SABAS ALONSO |
| Green Building Rough | 4/28/2026 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 4/28/2026 | Partial Approval | SABAS ALONSO |
| BUILDING-Rough-Frame | 5/26/2026 | Approved | ALIZAH MAYAGOITIA |
| Drywall Nailing | 6/2/2026 | Approved | SABAS ALONSO |
| Insulation | 6/2/2026 | Approved | SABAS ALONSO |