Work Description
ePlan FIRE DAMAGE REPAIR. RELOCATE EXISTING KITCHEN TO REAR. ADD BATHROOM AT SECOND FLOOR. SMALL ADDITION AT MASTER BEDROOM ON SECOND FLOOR. REPLACE ALL WINDOWS AND DOORS, ALL NEW FIXTURES, ALL NEW APPLIANCES. NEW TRELLIS ATTACHED TO SFD
Permit Issued
Issued on 10/31/2023
Issuing Office
Current Status
Issued on 10/31/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/14/2023 APPLICANT
Assigned to Plan Check Engineer 7/6/2023 JAD BASMA
Corrections Issued 7/14/2023 JAD BASMA
Quality Review Completed 7/20/2023 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 8/2/2023 JAD BASMA
Applicant returned to address corrections 8/3/2023 JAD BASMA
Plan Check Approved 8/3/2023 JAD BASMA
Issued 10/31/2023 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 7/22/2023 CELINA MORENO
Sewer availability Cleared 7/22/2023 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 7/25/2023 CELINA MORENO
HPOZ Cleared 7/25/2023 DANIEL MATA

Contact Information

Contractor Owner-Builder       ,
Engineer Rhee,, Kyle; Lic. No.: NA78215       ,

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/26/2024 Partial Inspection SABAS ALONSO
Deputy Drilled-In Anchors 8/29/2024 Conditional Approval SABAS ALONSO
Deputy Drilled-In Anchors 3/28/2025 Approved SABAS ALONSO
Footing/Foundation/Slab 3/28/2025 Approved SABAS ALONSO
Special/Order Compliance 12/29/2025 Corrections Issued SABAS ALONSO
ELECTRICAL-Rough 2/26/2026 Approved SABAS ALONSO
HVAC-Rough 2/26/2026 Corrections Issued SABAS ALONSO
PLUMBING-Rough 2/26/2026 Approved SABAS ALONSO
HVAC-Rough 4/14/2026 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 4/28/2026 Approved SABAS ALONSO
Green Building Rough 4/28/2026 Approved SABAS ALONSO
Interior/Exterior Lathing 4/28/2026 Partial Approval SABAS ALONSO
BUILDING-Rough-Frame 5/26/2026 Approved ALIZAH MAYAGOITIA
Drywall Nailing 6/2/2026 Approved SABAS ALONSO