3715 S MOORE ST 90066

Certificate Information: 3715 S MOORE ST 90066

Application / Permit
23014-10000-02382
Plan Check / Job No.
B23LA11053
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Remodel to (E) Dwelling with rear addition. Remodel existing kitchen, bathrooms and bedrooms. Porch addition at front.
Permit Issued
Issued on 7/13/2023
Issuing Office
South Los Angeles
Current Status
CofO Issued on 1/30/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/14/2023 APPLICANT
Assigned to Plan Check Engineer 6/23/2023 MICHAEL LANZONE
Corrections Issued 6/26/2023 MICHAEL LANZONE
Building Plans Picked Up 6/28/2023 APPLICANT
Applicant returned to address corrections 7/3/2023 CRISTINA SALAZAR
Issued 7/13/2023 APPLICANT
CofO in Progress 1/29/2024 RICHARD STEINBACH
Permit Finaled 1/30/2024 DANIEL ORRANTE
CofO Issued 1/30/2024 DANIEL ORRANTE
Permit Finaled 1/30/2024 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/29/2023 DARIN LAM
Grading Pre-Inspection Cleared 7/5/2023 ROBERT HUGHES
Roof/Waste drainage to street Cleared 7/5/2023 ANTHONY MAINEZ
Specific Plan Cleared 7/13/2023 FREDDY GARCIA

Contact Information

Contractor Rebuilt Homes Inc; Lic. No.: 1063540-B 2201 N LAKEWOOD BLVD STE D643      LONG BEACH, CA 90815
Engineer Saleh,, Zouheir Toufic; Lic. No.: C42881 1304 CORTE MALTERA      COSTA MESA, CA 92626

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/17/2023 Partial Approval HERBERT GIRON
Footing/Foundation/Slab 7/17/2023 Partial Approval HERBERT GIRON
Excavation/Setback/Form/Re-Bar 7/21/2023 Approved JESUS RODRIGUEZ
Footing/Foundation/Slab 7/21/2023 Approved JESUS RODRIGUEZ
Special/Order Compliance 7/21/2023 Corrections Issued JESUS RODRIGUEZ
Excavation/Setback/Form/Re-Bar 8/2/2023 Approved JESUS RODRIGUEZ
Footing/Foundation/Slab 8/2/2023 Approved JESUS RODRIGUEZ
Special/Order Compliance 8/2/2023 Corrections Issued JESUS RODRIGUEZ
BUILDING-Rough-Frame 8/10/2023 Not Ready for Inspection EVAN COOPER
ELECTRICAL-Rough 8/10/2023 Not Ready for Inspection EVAN COOPER
Green Building Rough 8/10/2023 Not Ready for Inspection EVAN COOPER
BUILDING-Rough-Frame 8/15/2023 Corrections Issued OGANES TARAKHCHYAN
ELECTRICAL-Rough 8/15/2023 Corrections Issued OGANES TARAKHCHYAN
Insulation 8/21/2023 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 8/21/2023 Approved JESUS RODRIGUEZ
Rough-Elec/Plmb/HVAC 8/21/2023 Approved JESUS RODRIGUEZ
Special/Order Compliance 8/21/2023 Partial Inspection BEN MOLSTAD
Wood Frame 8/21/2023 Approved JESUS RODRIGUEZ
Deputy Wood Construction 8/25/2023 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 8/25/2023 Corrections Issued JESUS RODRIGUEZ
Interior/Exterior Lathing 9/11/2023 Partial Approval TEMISTOCLES CAAL
BUILDING-Rough-Frame 11/1/2023 Approved HERBERT GIRON
Drywall Nailing 11/1/2023 Approved HERBERT GIRON
ELECTRICAL-Final 11/1/2023 Corrections Issued HERBERT GIRON
Final 11/1/2023 Not Ready for Inspection HERBERT GIRON
Green Building Final 11/1/2023 Approved HERBERT GIRON
Green Building Rough 11/1/2023 Approved HERBERT GIRON
PLUMBING-Final 11/1/2023 Corrections Issued HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 11/1/2023 SGSOV Approved HERBERT GIRON
Smoke Detectors 11/1/2023 Corrections Issued HERBERT GIRON
ELECTRICAL-Final 1/26/2024 Approved JESUS RODRIGUEZ
Final 1/26/2024 OK to Issue CofO JESUS RODRIGUEZ
HVAC-Final 1/26/2024 Approved JESUS RODRIGUEZ
PLUMBING-Final 1/26/2024 Approved JESUS RODRIGUEZ
Smoke Detectors 1/26/2024 Approved JESUS RODRIGUEZ