5055 E BUCHANAN ST 90042

Certificate Information: 5055 E BUCHANAN ST 90042

Application / Permit
23014-10000-02358
Plan Check / Job No.
B23LA10981
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan: one story ADU addition to existing detached garage per engineer design (1,200 SF max per Ordinance, LAMC 12.22 A.33 (c)-(d))
Permit Issued
Issued on 3/25/2024
Issuing Office
Current Status
CofO Issued on 9/19/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/14/2023 APPLICANT
Assigned to Plan Check Engineer 6/20/2023 SHANGQIN XIE
Corrections Issued 6/21/2023 SHANGQIN XIE
Applicant returned to address corrections 2/1/2024 NGHI SU
Applicant returned to address corrections 3/1/2024 AUNG SOE
Plan Check Approved 3/3/2024 AUNG SOE
Issued 3/25/2024 APPLICANT
CofO in Progress 9/19/2025 DAVID WILLIAMS
Permit Finaled 9/19/2025 DEROLD HAUFF
CofO Issued 9/19/2025 DEROLD HAUFF
Permit Finaled 9/19/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/14/2023 ARNULFO CHAMU
Eng Process Fee Ord 176,300 Cleared 12/20/2023 ARNULFO CHAMU
Sewer availability Cleared 12/20/2023 ARNULFO CHAMU
Grading Pre-Inspection Cleared 1/22/2024 VASIL MIHALEV
Low Impact Development (LID) Cleared 2/2/2024 LUIS CRUZ
Roof/Waste drainage to street Cleared 2/7/2024 ARNULFO CHAMU
GPI Written Notices Cleared 3/3/2024 SHANGQIN XIE

Contact Information

Contractor Owner-Builder       ,
Engineer Yi, Lu; Lic. No.: NA5678 P O BOX 2754      PALOS VERDES PENINSULA, CA 90274

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/3/2024 Partial Approval ALIZAH MAYAGOITIA
Deputy Drilled-In Anchors 5/16/2024 Conditional Approval ALIZAH MAYAGOITIA
Footing/Foundation/Slab 5/17/2024 Approved ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 6/11/2024 Partial Approval ALIZAH MAYAGOITIA
Green Building Rough 6/11/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
ELECTRICAL-Rough 1/14/2025 Corrections Issued OSVALDO PARAMO
PLUMBING-Rough 1/14/2025 Corrections Issued OSVALDO PARAMO
ELECTRICAL-Rough 2/6/2025 Corrections Issued CRAIG DAVIS
PLUMBING-Rough 2/6/2025 Corrections Issued CRAIG DAVIS
ELECTRICAL-Rough 2/20/2025 Approved CRAIG DAVIS
PLUMBING-Rough 2/20/2025 Approved CRAIG DAVIS
Interior/Exterior Lathing 3/7/2025 Approved DAVID WILLIAMS
Insulation 3/12/2025 Corrections Issued REGINA MENDEZ
Insulation 3/17/2025 Approved DAVID WILLIAMS
Drywall Nailing 3/26/2025 Approved REGINA MENDEZ
Green Building Rough 3/26/2025 Approved REGINA MENDEZ
BUILDING-Rough-Frame 6/3/2025 Approved DAVID WILLIAMS
Final 6/3/2025 Corrections Issued DAVID WILLIAMS
Green Building Final 6/3/2025 Approved DAVID WILLIAMS
SGSOV-Seismic Gas S/O Valve 6/3/2025 SGSOV Not Required DAVID WILLIAMS
Smoke Detectors 6/3/2025 Approved DAVID WILLIAMS
Final 6/13/2025 Not Ready for Inspection DAVID WILLIAMS
Final 9/19/2025 OK to Issue CofO DAVID WILLIAMS