5116 E WILLIAMS PL 90032

Certificate Information: 5116 E WILLIAMS PL 90032

Application / Permit
23014-10000-02349
Plan Check / Job No.
B23LA10921
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan: REMODEL , GROUND AND 2-STORY ADDITION TO EXISTING 1-STORY SINGLE-FAMILY DWELLING (Fire Sprinkler NFPA 13D)
Permit Issued
Issued on 10/15/2024
Issuing Office
Current Status
CofO Issued on 11/20/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/13/2023 APPLICANT
Assigned to Plan Check Engineer 6/29/2023 KHEDER ALRAZAA
Corrections Issued 7/6/2023 KHEDER ALRAZAA
Quality Review Completed 7/14/2023 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 7/10/2024 KHEDER ALRAZAA
Applicant returned to address corrections 7/31/2024 KHEDER ALRAZAA
Plan Check Approved 10/2/2024 KHEDER ALRAZAA
Plan Check Approved 10/11/2024 KHEDER ALRAZAA
No Progress 10/11/2024 KHEDER ALRAZAA
Plan Check Approved 10/11/2024 KHEDER ALRAZAA
Issued 10/15/2024 APPLICANT
CofO in Progress 11/19/2025 LILIANA PORTILLO
Permit Finaled 11/20/2025 DEROLD HAUFF
CofO Issued 11/20/2025 DEROLD HAUFF
Permit Finaled 11/20/2025 DEROLD HAUFF

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 9/5/2023 WALLIE JONG
BHO/Hillside ordinance Cleared 9/5/2023 WALLIE JONG
BHO/Hillside ordinance Cleared 9/5/2023 WALLIE JONG
BHO/Hillside ordinance Cleared 9/5/2023 WALLIE JONG
ZI Cleared 9/28/2023 GEORGIA SMITH
"D" conditions Cleared 11/1/2023 JASON CHAN
"Q" conditions Cleared 11/1/2023 JASON CHAN
Sewer availability Cleared 7/2/2024 JEANIE LAM
GPI Written Notices Cleared 7/31/2024 KHEDER ALRAZAA
Grading Pre-Inspection Cleared 7/31/2024 KHEDER ALRAZAA
BHO/Hillside ordinance Cleared 8/1/2024 ALBERT TAM
Low Impact Development (LID) Cleared 8/9/2024 ERNEST TSE
Eng Process Fee Ord 176,300 Cleared 8/12/2024 ADRIAN SANCHEZ
Roof/Waste drainage to street Cleared 8/12/2024 ADRIAN SANCHEZ
Disturb/Remove Protected Trees Cleared 8/21/2024 RICHARD SANCHEZ

Contact Information

Contractor The Master Of Construction Brothers Inc; Lic. No.: 1044368-B       ,
Engineer Alatorre-Y-Barroso,, Alejandro Javier; Lic. No.: C32761 7411 FLORENCE AVE      DOWNEY, CA 90240
Engineer Castillo,, Margarito; Lic. No.: S4808 1205 PINE AVE   SUITE 201    LONG BEACH, CA 90813
Engineer Tucker,, Keith D; Lic. No.: GE841 PO BOX 8133      HUNTINGTON BEACH, CA 92615

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/5/2024 Conditional Approval BRENDAN MORELLI
Footing/Foundation/Slab 12/10/2024 Approved LUIS CASTRO
PLUMBING-Rough 12/10/2024 Partial Approval LUIS CASTRO
Masonry Wall/Backfill 12/24/2024 Partial Approval BRENDAN MORELLI
Masonry Wall/Backfill 1/3/2025 Partial Approval BRENDAN MORELLI
Masonry Wall/Backfill 1/7/2025 Partial Approval BRENDAN MORELLI
Masonry Wall/Backfill 1/14/2025 Approved LILIANA PORTILLO
Masonry Wall/Backfill 1/27/2025 Approved LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 3/18/2025 Corrections Issued LILIANA PORTILLO
PLUMBING-Rough 3/18/2025 Approved LILIANA PORTILLO
Shower Pan 3/18/2025 Approved LILIANA PORTILLO
ELECTRICAL-Rough 5/27/2025 Corrections Issued LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 5/27/2025 Approved LILIANA PORTILLO
HVAC-Rough 5/27/2025 Corrections Issued LILIANA PORTILLO
Interior/Exterior Lathing 5/27/2025 Partial Approval LILIANA PORTILLO
BUILDING-Rough-Frame 6/3/2025 Conditional Approval LILIANA PORTILLO
ELECTRICAL-Rough 6/3/2025 Approved LILIANA PORTILLO
HVAC-Rough 6/3/2025 Approved LILIANA PORTILLO
Interior/Exterior Lathing 6/3/2025 Approved LILIANA PORTILLO
Verify Sprinkler Sign Off 6/3/2025 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 6/10/2025 Approved ANTHONY RAMOS
Green Building Rough 6/10/2025 Approved ANTHONY RAMOS
Insulation 6/10/2025 Approved ANTHONY RAMOS
Drywall Nailing 6/17/2025 Approved BRENDAN MORELLI
Service/Power Release 7/28/2025 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Final 7/31/2025 Approved LILIANA PORTILLO
Final 7/31/2025 Corrections Issued LILIANA PORTILLO
HVAC-Final 7/31/2025 Approved LILIANA PORTILLO
PLUMBING-Final 7/31/2025 Approved LILIANA PORTILLO
Final 11/18/2025 OK to Issue CofO LILIANA PORTILLO
Green Building Final 11/18/2025 Approved LILIANA PORTILLO
Reinforced Concrete Frame 11/18/2025 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 11/18/2025 SGSOV Approved LILIANA PORTILLO
Smoke Detectors 11/18/2025 Approved LILIANA PORTILLO