613 E 116TH ST 90059
Certificate Information: 613 E 116TH ST 90059
- Application / Permit
- 23014-10000-02326
- Plan Check / Job No.
- B23LA10805
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan A new two-story accessory dwelling unit (ADU) per Ordinance LAMC 12.22 A.33(c)
- Permit Issued
- Issued on 3/26/2024
- Issuing Office
- Current Status
- CofO Issued on 9/25/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/13/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/29/2023 | YASHAR EMAMI |
| Corrections Issued | 7/5/2023 | YASHAR EMAMI |
| Quality Review Completed | 7/18/2023 | KAVIAN REFAHI |
| Applicant returned to address corrections | 2/8/2024 | YASHAR EMAMI |
| Plan Check Approved | 3/15/2024 | YASHAR EMAMI |
| Issued | 3/26/2024 | APPLICANT |
| CofO in Progress | 9/17/2025 | ANTHONY EGSON |
| Permit Finaled | 9/25/2025 | ANSON MAGLASANG |
| CofO Issued | 9/25/2025 | ANSON MAGLASANG |
| Permit Finaled | 9/25/2025 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 8/3/2023 | CHRISTINA BRACO |
| Eng Process Fee Ord 176,300 | Cleared | 10/24/2023 | CHRISTINA BRACO |
| Sewer availability | Cleared | 10/24/2023 | CHRISTINA BRACO |
| Low Impact Development (LID) | Cleared | 11/3/2023 | TOMMY YIN |
| Roof/Waste drainage to street | Cleared | 11/7/2023 | JUSTIN BICOL |
| "D" conditions | Cleared | 1/15/2024 | HELEN JADALI |
| Community Plan Implem. Overlay | Cleared | 1/15/2024 | HELEN JADALI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mangoli,, Arash; Lic. No.: C84319 | 1727 BENTLEY AVE APT 211 LOS ANGELES, CA 90025 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/31/2024 | Corrections Issued | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 12/19/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/29/2025 | Corrections Issued | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/31/2025 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/5/2025 | Corrections Issued | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/14/2025 | Partial Approval | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/27/2025 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/28/2025 | Approved | ANTHONY EGSON |
| Green Building Rough | 3/28/2025 | Approved | ANTHONY EGSON |
| Insulation | 4/2/2025 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Rough | 4/4/2025 | Corrections Issued | ANTHONY EGSON |
| Insulation | 4/4/2025 | Partial Approval | ANTHONY EGSON |
| Drywall Nailing | 4/7/2025 | Partial Approval | ANTHONY EGSON |
| HVAC-Rough | 4/7/2025 | Partial Approval | ANTHONY EGSON |
| Insulation | 4/8/2025 | Partial Approval | ANTHONY EGSON |
| BUILDING-Rough-Frame | 4/9/2025 | Corrections Issued | BEN MOLSTAD |
| ELECTRICAL-Rough | 4/9/2025 | Approved | BEN MOLSTAD |
| HVAC-Rough | 4/9/2025 | Not Ready for Inspection | BEN MOLSTAD |
| Insulation | 4/9/2025 | Not Ready for Inspection | BEN MOLSTAD |
| HVAC-Rough | 4/14/2025 | Corrections Issued | BEN MOLSTAD |
| BUILDING-Rough-Frame | 4/16/2025 | Approved | ANTHONY EGSON |
| HVAC-Rough | 4/16/2025 | Approved | ANTHONY EGSON |
| MERV13>=Rough | 4/16/2025 | Approved | ANTHONY EGSON |
| Insulation | 4/23/2025 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 4/23/2025 | Approved | ANTHONY EGSON |
| Drywall Nailing | 4/30/2025 | Approved | ANTHONY EGSON |
| Underground Mechanical | 6/16/2025 | Partial Approval | ANTHONY EGSON |
| Masonry Wall/Backfill | 7/16/2025 | Partial Inspection | JOHN KLARIN |
| ELECTRICAL-Final | 8/5/2025 | Corrections Issued | ANTHONY EGSON |
| HVAC-Final | 8/5/2025 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Final | 8/5/2025 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Final | 8/12/2025 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Final | 9/4/2025 | Approved | ANTHONY EGSON |
| Final | 9/4/2025 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 9/4/2025 | Approved | ANTHONY EGSON |
| MERV13>=Final | 9/4/2025 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Final | 9/4/2025 | Approved | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 9/4/2025 | SGSOV Not Required | ANTHONY EGSON |
| Smoke Detectors | 9/4/2025 | Approved | ANTHONY EGSON |
| HVAC-Final | 9/8/2025 | Approved | ANTHONY EGSON |
| Final | 9/17/2025 | OK to Issue CofO | ANTHONY EGSON |
| MERV13>=Final | 9/17/2025 | Approved | ANTHONY EGSON |