3844 W VALLEYBRINK ROAD 90039

Certificate Information: 3844 W VALLEYBRINK ROAD 90039

Application / Permit
23014-10000-02322
Plan Check / Job No.
B23LA08820
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN: Addition and Remodel of (E) one story SFD at front of Lot. 2 OF 2
Permit Issued
Issued on 8/15/2024
Issuing Office
Current Status
CofO Issued on 4/10/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/12/2023 APPLICANT
Assigned to Plan Check Engineer 6/1/2023 TSE MING HUANG
Corrections Issued 6/12/2023 TSE MING HUANG
Quality Review Completed 6/14/2023 EUGENE BARBEAU
Applicant returned to address corrections 1/17/2024 TSE MING HUANG
Plan Check Approved 7/12/2024 TSE MING HUANG
No Progress 8/13/2024 TSE MING HUANG
Plan Check Approved 8/13/2024 TSE MING HUANG
Plan Check Approved 8/14/2024 TSE MING HUANG
Issued 8/15/2024 APPLICANT
CofO in Progress 4/9/2026 NICHOLAS LOPEZ
Permit Finaled 4/10/2026 DEROLD HAUFF
CofO Issued 4/10/2026 DEROLD HAUFF
Permit Finaled 4/10/2026 DEROLD HAUFF

Permit Application Clearance Information

Sewer availability Cleared 8/9/2023 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 10/3/2023 WALLIE JONG
ZI Cleared 10/18/2023 DAVID URITA
Low Impact Development (LID) Cleared 2/20/2024 MITESH PATEL
Tenant Habitability Plan Cleared 6/12/2024 RICARDO BOHORQUEZ
Roof/Waste drainage to street Cleared 7/9/2024 CHRISTINA BRACO

Contact Information

Contractor Owner-Builder       ,
Engineer Mccullum,, Eric William; Lic. No.: C68850 727 2ND ST STE 104      HERMOSA BEACH, CA 90254

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/5/2024 Partial Inspection THOMAS LOGRASSO
Excavation/Setback/Form/Re-Bar 11/22/2024 Not Ready for Inspection THOMAS LOGRASSO
Excavation/Setback/Form/Re-Bar 12/17/2024 Approved THOMAS LOGRASSO
Footing/Foundation/Slab 12/17/2024 Partial Inspection THOMAS LOGRASSO
Underground Mechanical 1/16/2025 Not Ready for Inspection THOMAS LOGRASSO
Drywall Nailing 1/22/2025 Partial Approval THOMAS LOGRASSO
Deputy Wood Construction 1/31/2025 Conditional Approval THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 2/5/2025 Corrections Issued THOMAS LOGRASSO
PLUMBING-Rough 3/12/2025 Corrections Issued NICHOLAS LOPEZ
PLUMBING-Rough 4/2/2025 Approved NICHOLAS LOPEZ
Underground Mechanical 4/2/2025 Partial Approval NICHOLAS LOPEZ
HVAC-Rough 5/13/2025 Corrections Issued NICHOLAS LOPEZ
PLUMBING-Rough 5/13/2025 Approved NICHOLAS LOPEZ
Sewer 5/28/2025 Approved NICHOLAS LOPEZ
ELECTRICAL-Rough 6/17/2025 Approved NICHOLAS LOPEZ
HVAC-Rough 6/24/2025 Approved REGINA MENDEZ
BUILDING-Rough-Frame 7/2/2025 Approved NICHOLAS LOPEZ
Green Building Rough 7/2/2025 Approved NICHOLAS LOPEZ
MERV13>=Rough 7/2/2025 Approved NICHOLAS LOPEZ
Insulation 7/16/2025 Approved NICHOLAS LOPEZ
Shower Pan 8/26/2025 Approved REGINA MENDEZ
Drywall Nailing 9/5/2025 Approved NICHOLAS LOPEZ
Drywall Nailing 9/8/2025 Approved NICHOLAS LOPEZ
Interior/Exterior Lathing 9/12/2025 Approved ANTHONY RAMOS
Pre-Inspection 11/17/2025 Partial Inspection NICHOLAS LOPEZ
Service/Power Release 11/17/2025 Corrections Issued NICHOLAS LOPEZ
ELECTRICAL-Final 2/12/2026 Corrections Issued NICHOLAS LOPEZ
Gas Test 2/12/2026 Approved NICHOLAS LOPEZ
PLUMBING-Final 2/12/2026 Approved NICHOLAS LOPEZ
ELECTRICAL-Final 3/25/2026 Approved NICHOLAS LOPEZ
Final 3/25/2026 Corrections Issued NICHOLAS LOPEZ
Footing/Foundation/Slab 3/25/2026 Approved NICHOLAS LOPEZ
Green Building Final 3/25/2026 Not Ready for Inspection NICHOLAS LOPEZ
HVAC-Final 3/25/2026 Corrections Issued NICHOLAS LOPEZ
MERV13>=Final 3/25/2026 Approved NICHOLAS LOPEZ
SGSOV-Seismic Gas S/O Valve 3/25/2026 SGSOV Not Ready NICHOLAS LOPEZ
Smoke Detectors 3/25/2026 Approved NICHOLAS LOPEZ
Final 4/8/2026 OK to Issue CofO NICHOLAS LOPEZ
Green Building Final 4/8/2026 Approved NICHOLAS LOPEZ
HVAC-Final 4/8/2026 Approved NICHOLAS LOPEZ
SGSOV-Seismic Gas S/O Valve 4/8/2026 SGSOV Approved NICHOLAS LOPEZ