1367 W YOSEMITE DR 90041
Certificate Information: 1367 W YOSEMITE DR 90041
- Application / Permit
- 23014-10000-02305
- Plan Check / Job No.
- B23LA10713
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 7'-10"x20'-4" ADDITION TO SINGLE FAMILY DWELLING UNIT. WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 9/22/2023
- Issuing Office
- Current Status
- CofO Issued on 4/1/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/9/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/12/2023 | KAMYAR EMAMI |
| Corrections Issued | 6/29/2023 | KAMYAR EMAMI |
| Quality Review Completed | 7/13/2023 | OMID HEDAYAT |
| Plan Check Approved | 8/21/2023 | KAMYAR EMAMI |
| No Progress | 8/29/2023 | OMID HEDAYAT |
| Plan Check Approved | 8/30/2023 | KAMYAR EMAMI |
| Issued | 9/22/2023 | APPLICANT |
| CofO in Progress | 3/29/2024 | CRAIG VAUGHAN |
| Permit Finaled | 4/1/2024 | DEROLD HAUFF |
| CofO Issued | 4/1/2024 | DEROLD HAUFF |
| Permit Finaled | 4/1/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 7/14/2023 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 7/15/2023 | AHMED AMARRAGY |
| Watercourse | Cleared | 7/16/2023 | JOSEPH RHYU |
| Grading Pre-Inspection | Cleared | 7/21/2023 | SERGIO VALENZUELA |
Contact Information
| Contractor | Golden Point Construction; Lic. No.: 965193-B | , |
| Engineer | Warling,, Jeffrey Paul; Lic. No.: C43743 | 1792 PEREGRINE CT SIMI VALLEY, CA 93065 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/25/2023 | Approved | ROY SPAULDING |
| Footing/Foundation/Slab | 9/25/2023 | Corrections Issued | ROY SPAULDING |
| Deputy Drilled-In Anchors | 9/27/2023 | Conditional Approval | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 11/14/2023 | Approved | ROY SPAULDING |
| ELECTRICAL-Rough | 11/14/2023 | Approved | ROY SPAULDING |
| Green Building Rough | 11/14/2023 | Approved | ROY SPAULDING |
| Insulation | 11/22/2023 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 11/22/2023 | Approved | CRAIG VAUGHAN |
| Drywall Nailing | 12/18/2023 | Approved | CHARLES BOGHOSKHAN |
| Drywall Nailing | 12/21/2023 | Approved | ROY SPAULDING |
| Final | 3/7/2024 | Conditional Approval | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 3/7/2024 | Approved | CRAIG VAUGHAN |
| Green Building Final | 3/7/2024 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 3/7/2024 | SGSOV Approved | CRAIG VAUGHAN |
| Smoke Detectors | 3/7/2024 | Approved | CRAIG VAUGHAN |
| Final | 3/28/2024 | OK to Issue CofO | CRAIG VAUGHAN |