5919 S MADDEN AVE 90043
Certificate Information: 5919 S MADDEN AVE 90043
- Application / Permit
- 23014-10000-02280
- Plan Check / Job No.
- B23LA10652
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REAR ADDITION, ENCLOUSE (E) FRONT PORCH TO LIVING AREA AND ADDING NEW PORCH AT FRONT OF (E) SFD. INTERIOR REMODEL. ADD NEW GABLE ROOF OVER EXISTING FLAT ROOF
- Permit Issued
- Issued on 6/21/2023
- Issuing Office
- Current Status
- CofO Issued on 4/29/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/8/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/8/2023 | JOSEPH RAFOLS |
| Corrections Issued | 6/8/2023 | JOSEPH RAFOLS |
| Issued | 6/21/2023 | APPLICANT |
| CofO in Progress | 4/22/2024 | JOSE MACIAS |
| CofO Issued | 4/29/2024 | DEROLD HAUFF |
| Permit Finaled | 4/29/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/21/2023 | CINDY QI |
| Roof/Waste drainage to street | Cleared | 6/21/2023 | CINDY QI |
Contact Information
| Contractor | Builder Point Construction; Lic. No.: 1059885-B | 11445 PARAMOUNT BLVD SUITE H DOWNEY, CA 90241 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/18/2023 | Approved | ENRIQUE MIRELES |
| Underground Mechanical | 8/7/2023 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 9/13/2023 | Partial Approval | JUSTIN HAWLEY |
| ELECTRICAL-Rough | 9/20/2023 | Approved | STUART CHAPMAN |
| HVAC-Rough | 9/20/2023 | Corrections Issued | STUART CHAPMAN |
| PLUMBING-Rough | 9/20/2023 | Approved | STUART CHAPMAN |
| Insulation | 10/2/2023 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 10/2/2023 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 10/10/2023 | Approved | ENRIQUE MIRELES |
| Shower Pan | 10/10/2023 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 10/16/2023 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 4/12/2024 | Approved | JOSE MACIAS |
| Final | 4/12/2024 | Corrections Issued | JOSE MACIAS |
| Green Building Final | 4/12/2024 | Corrections Issued | JOSE MACIAS |
| Green Building Rough | 4/12/2024 | Approved | JOSE MACIAS |
| SGSOV-Seismic Gas S/O Valve | 4/12/2024 | SGSOV Approved | JOSE MACIAS |
| Smoke Detectors | 4/12/2024 | Corrections Issued | JOSE MACIAS |
| Final | 4/18/2024 | OK to Issue CofO | JOSE MACIAS |
| Green Building Final | 4/18/2024 | Approved | JOSE MACIAS |
| Smoke Detectors | 4/18/2024 | Approved | JOSE MACIAS |