1937 N BEVERLY DR 90210

Certificate Information: 1937 N BEVERLY DR 90210

Application / Permit
23014-10000-02263
Plan Check / Job No.
B23LA10541
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Interior remodel to (e) 2-story single family dwelling. Scope to include (n) windows, (n) doors, remove drop ceiling on first floor, and (n) partitions throughout, (n) awning, create more than 14' ceiling height space at entry hall, and enclose portion of (e) 69.77sf front porch. All work per engineer.
Permit Issued
Issued on 8/18/2023
Issuing Office
Metro
Current Status
Permit Finaled on 12/23/2024

Permit Application Status History

Submitted 6/7/2023 APPLICANT
Assigned to Plan Check Engineer 6/12/2023 KHUONG TRUONG
Corrections Issued 6/12/2023 KHUONG TRUONG
Building Plans Picked Up 6/21/2023 APPLICANT
Applicant returned to address corrections 7/12/2023 MICHAEL LANZONE
Applicant returned to address corrections 8/17/2023 VICTOR CHEN
Plan Check Approved 8/18/2023 SAMUEL GONZALEZ
Issued 8/18/2023 APPLICANT
Permit Finaled 12/20/2024 SEAN HAUPT

Permit Application Clearance Information

Grading Pre-Inspection Cleared 6/14/2023 ALEXANDER HELFER
Construction near power lines Cleared 6/27/2023 WALTER RAMIREZ
Eng Process Fee Ord 176,300 Cleared 6/29/2023 DARIN LAM
Roof/Waste drainage to street Cleared 6/29/2023 DARIN LAM
Sewer availability Cleared 6/29/2023 DARIN LAM
ZA Case Cleared 6/29/2023 JASON CHAN
Grading Pre-Inspection Cleared 8/18/2023 MICHAEL LANZONE

Contact Information

Contractor Owner-Builder       ,
Engineer Nazari,, Arthur; Lic. No.: C53497 PO BOX 7112      NORTHRIDGE, CA 91327

Inspector Information

CARLOS MATAMOROS, (310) 914-3878 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/7/2023 Approved BRENDAN LOONEY
PLUMBING-Rough 9/12/2023 Conditional Approval BRENDAN LOONEY
Deputy Reinf. Concrete 9/19/2023 Conditional Approval MICHAEL PELHAM
PLUMBING-Rough 9/25/2023 Partial Approval BRENDAN LOONEY
Footing/Foundation/Slab 12/12/2023 Approved MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 12/19/2023 Partial Approval BRENDAN LOONEY
Footing/Foundation/Slab 2/13/2024 Partial Approval SEAN HAUPT
Deputy Steel/Welding 3/4/2024 Partial Approval SEAN HAUPT
Deputy Drilled-In Anchors 4/22/2024 Conditional Approval MICHAEL PELHAM
BUILDING-Rough-Frame 5/10/2024 Corrections Issued SEAN HAUPT
HVAC-Rough 5/10/2024 Approved SEAN HAUPT
PLUMBING-Rough 5/10/2024 Approved SEAN HAUPT
BUILDING-Rough-Frame 5/24/2024 Not Ready for Inspection SEAN HAUPT
Drywall Nailing 5/24/2024 Not Ready for Inspection SEAN HAUPT
ELECTRICAL-Rough 5/24/2024 Not Ready for Inspection SEAN HAUPT
FLOOD-Proofing Certificate 5/24/2024 Corrections Issued SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 5/24/2024 Approved SEAN HAUPT
Green Building Rough 5/24/2024 Not Ready for Inspection SEAN HAUPT
Structural Steel Frame 5/24/2024 Not Ready for Inspection SEAN HAUPT
BUILDING-Rough-Frame 6/10/2024 Not Ready for Inspection MICHAEL PELHAM
ELECTRICAL-Rough 6/10/2024 Not Ready for Inspection MICHAEL PELHAM
FLOOD-Proofing Certificate 6/10/2024 Approved MICHAEL PELHAM
Green Building Rough 6/10/2024 Approved MICHAEL PELHAM
Interior/Exterior Lathing 6/10/2024 Partial Approval MICHAEL PELHAM
BUILDING-Rough-Frame 6/14/2024 Partial Approval SEAN HAUPT
ELECTRICAL-Rough 6/14/2024 Not Ready for Inspection SEAN HAUPT
Green Building Rough 6/14/2024 Approved SEAN HAUPT
Interior/Exterior Lathing 6/14/2024 Approved SEAN HAUPT
Structural Steel Frame 6/14/2024 Approved SEAN HAUPT
BUILDING-Rough-Frame 6/18/2024 Approved SEAN HAUPT
ELECTRICAL-Rough 6/18/2024 Approved SEAN HAUPT
Insulation 6/24/2024 Approved SEAN HAUPT
Drywall Nailing 7/1/2024 Approved SEAN HAUPT
Shower Pan 7/5/2024 Approved SEAN HAUPT
Interior/Exterior Lathing 7/26/2024 Approved SEAN HAUPT
ELECTRICAL-Final 12/17/2024 Approved SEAN HAUPT
Final 12/17/2024 Corrections Issued SEAN HAUPT
Green Building Final 12/17/2024 Approved SEAN HAUPT
HVAC-Final 12/17/2024 Approved SEAN HAUPT
PLUMBING-Final 12/17/2024 Approved SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 12/17/2024 SGSOV Approved SEAN HAUPT
Smoke Detectors 12/17/2024 Approved SEAN HAUPT
Final 12/20/2024 Permit Finaled SEAN HAUPT