- Work Description
- Interior remodel to (e) 2-story single family dwelling. Scope to include (n) windows, (n) doors, remove drop ceiling on first floor, and (n) partitions throughout, (n) awning, create more than 14' ceiling height space at entry hall, and enclose portion of (e) 69.77sf front porch. All work per engineer.
- Permit Issued
- Issued on 8/18/2023
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 12/23/2024
Permit Application Status History
| Submitted | 6/7/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/12/2023 | KHUONG TRUONG |
| Corrections Issued | 6/12/2023 | KHUONG TRUONG |
| Building Plans Picked Up | 6/21/2023 | APPLICANT |
| Applicant returned to address corrections | 7/12/2023 | MICHAEL LANZONE |
| Applicant returned to address corrections | 8/17/2023 | VICTOR CHEN |
| Plan Check Approved | 8/18/2023 | SAMUEL GONZALEZ |
| Issued | 8/18/2023 | APPLICANT |
| Permit Finaled | 12/20/2024 | SEAN HAUPT |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 6/14/2023 | ALEXANDER HELFER |
| Construction near power lines | Cleared | 6/27/2023 | WALTER RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/29/2023 | DARIN LAM |
| Roof/Waste drainage to street | Cleared | 6/29/2023 | DARIN LAM |
| Sewer availability | Cleared | 6/29/2023 | DARIN LAM |
| ZA Case | Cleared | 6/29/2023 | JASON CHAN |
| Grading Pre-Inspection | Cleared | 8/18/2023 | MICHAEL LANZONE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Nazari,, Arthur; Lic. No.: C53497 | PO BOX 7112 NORTHRIDGE, CA 91327 |
Inspector Information
| CARLOS MATAMOROS, (310) 914-3878 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/7/2023 | Approved | BRENDAN LOONEY |
| PLUMBING-Rough | 9/12/2023 | Conditional Approval | BRENDAN LOONEY |
| Deputy Reinf. Concrete | 9/19/2023 | Conditional Approval | MICHAEL PELHAM |
| PLUMBING-Rough | 9/25/2023 | Partial Approval | BRENDAN LOONEY |
| Footing/Foundation/Slab | 12/12/2023 | Approved | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 12/19/2023 | Partial Approval | BRENDAN LOONEY |
| Footing/Foundation/Slab | 2/13/2024 | Partial Approval | SEAN HAUPT |
| Deputy Steel/Welding | 3/4/2024 | Partial Approval | SEAN HAUPT |
| Deputy Drilled-In Anchors | 4/22/2024 | Conditional Approval | MICHAEL PELHAM |
| BUILDING-Rough-Frame | 5/10/2024 | Corrections Issued | SEAN HAUPT |
| HVAC-Rough | 5/10/2024 | Approved | SEAN HAUPT |
| PLUMBING-Rough | 5/10/2024 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 5/24/2024 | Not Ready for Inspection | SEAN HAUPT |
| Drywall Nailing | 5/24/2024 | Not Ready for Inspection | SEAN HAUPT |
| ELECTRICAL-Rough | 5/24/2024 | Not Ready for Inspection | SEAN HAUPT |
| FLOOD-Proofing Certificate | 5/24/2024 | Corrections Issued | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 5/24/2024 | Approved | SEAN HAUPT |
| Green Building Rough | 5/24/2024 | Not Ready for Inspection | SEAN HAUPT |
| Structural Steel Frame | 5/24/2024 | Not Ready for Inspection | SEAN HAUPT |
| BUILDING-Rough-Frame | 6/10/2024 | Not Ready for Inspection | MICHAEL PELHAM |
| ELECTRICAL-Rough | 6/10/2024 | Not Ready for Inspection | MICHAEL PELHAM |
| FLOOD-Proofing Certificate | 6/10/2024 | Approved | MICHAEL PELHAM |
| Green Building Rough | 6/10/2024 | Approved | MICHAEL PELHAM |
| Interior/Exterior Lathing | 6/10/2024 | Partial Approval | MICHAEL PELHAM |
| BUILDING-Rough-Frame | 6/14/2024 | Partial Approval | SEAN HAUPT |
| ELECTRICAL-Rough | 6/14/2024 | Not Ready for Inspection | SEAN HAUPT |
| Green Building Rough | 6/14/2024 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 6/14/2024 | Approved | SEAN HAUPT |
| Structural Steel Frame | 6/14/2024 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 6/18/2024 | Approved | SEAN HAUPT |
| ELECTRICAL-Rough | 6/18/2024 | Approved | SEAN HAUPT |
| Insulation | 6/24/2024 | Approved | SEAN HAUPT |
| Drywall Nailing | 7/1/2024 | Approved | SEAN HAUPT |
| Shower Pan | 7/5/2024 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 7/26/2024 | Approved | SEAN HAUPT |
| ELECTRICAL-Final | 12/17/2024 | Approved | SEAN HAUPT |
| Final | 12/17/2024 | Corrections Issued | SEAN HAUPT |
| Green Building Final | 12/17/2024 | Approved | SEAN HAUPT |
| HVAC-Final | 12/17/2024 | Approved | SEAN HAUPT |
| PLUMBING-Final | 12/17/2024 | Approved | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 12/17/2024 | SGSOV Approved | SEAN HAUPT |
| Smoke Detectors | 12/17/2024 | Approved | SEAN HAUPT |
| Final | 12/20/2024 | Permit Finaled | SEAN HAUPT |