3766 S ROSEWOOD AVE 90066

Certificate Information: 3766 S ROSEWOOD AVE 90066

Application / Permit
23014-10000-02241
Plan Check / Job No.
B23LA10416
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
**ePlan** Conversion of (E) dettached garage at rear of the lot with an addition to create an ADU per LAMC 12.22 A.33 (c) & (d).
Permit Issued
Issued on 1/18/2024
Issuing Office
Current Status
CofO Issued on 2/11/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/6/2023 APPLICANT
Assigned to Plan Check Engineer 6/9/2023 EDWIN ESPIN
Corrections Issued 6/10/2023 EDWIN ESPIN
Applicant returned to address corrections 7/28/2023 JAHANSHAH POURHASSAN
Applicant returned to address corrections 8/7/2023 ALFREDO JARA
Plan Check Approved 12/2/2023 ALFREDO JARA
Issued 1/18/2024 APPLICANT
CofO in Progress 2/5/2025 JESUS PINEDA
Permit Finaled 2/11/2025 RICHARD STEINBACH
CofO Issued 2/11/2025 RICHARD STEINBACH
Permit Finaled 2/11/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 6/12/2023 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 6/13/2023 DINAH GARIN
Sewer availability Cleared 6/13/2023 DINAH GARIN
Specific Plan Cleared 6/14/2023 ALESSANDRO MERCURI
Grading Pre-Inspection Cleared 7/12/2023 ALEXANDER HELFER
Roof/Waste drainage to street Cleared 7/25/2023 DINAH GARIN
Construction near power lines Cleared 11/29/2023 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Xi,, Wang; Lic. No.: NA85148       ,

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/3/2024 Not Ready for Inspection JESUS RODRIGUEZ
PLUMBING-Rough 6/3/2024 Partial Approval JESUS RODRIGUEZ
Deputy Drilled-In Anchors 6/24/2024 Conditional Approval MICHAEL PELHAM
Excavation/Setback/Form/Re-Bar 6/24/2024 Corrections Issued HERBERT GIRON
Footing/Foundation/Slab 6/24/2024 Corrections Issued HERBERT GIRON
PLUMBING-Rough 6/24/2024 Partial Approval HERBERT GIRON
Excavation/Setback/Form/Re-Bar 6/26/2024 Partial Approval TEMISTOCLES CAAL
PLUMBING-Rough 6/26/2024 Partial Approval TEMISTOCLES CAAL
Excavation/Setback/Form/Re-Bar 7/1/2024 Approved JESUS RODRIGUEZ
Footing/Foundation/Slab 7/1/2024 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 8/13/2024 Corrections Issued HERBERT GIRON
Green Building Rough 8/13/2024 Not Ready for Inspection HERBERT GIRON
Deputy Wood Construction 8/15/2024 Conditional Approval JESUS RODRIGUEZ
ELECTRICAL-Rough 9/4/2024 Approved JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 9/4/2024 Partial Approval JESUS PINEDA
HVAC-Rough 9/4/2024 Approved JESUS PINEDA
PLUMBING-Rough 9/4/2024 Approved JESUS PINEDA
BUILDING-Rough-Frame 10/2/2024 Approved JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 10/2/2024 Approved JESUS PINEDA
Green Building Rough 10/2/2024 Approved JESUS PINEDA
Interior/Exterior Lathing 10/2/2024 Partial Approval JESUS PINEDA
Insulation 10/7/2024 Approved REGINA MENDEZ
Shower Pan 10/7/2024 Approved REGINA MENDEZ
Drywall Nailing 10/21/2024 Approved MICHAEL ALLEN
Interior/Exterior Lathing 10/21/2024 Approved MICHAEL ALLEN
Sewer 11/22/2024 Approved REGINA MENDEZ
Pre-Inspection 12/12/2024 Partial Inspection JESUS PINEDA
Underground Mechanical 12/20/2024 Approved REGINA MENDEZ
ELECTRICAL-Final 1/24/2025 Corrections Issued JESUS PINEDA
Final 1/24/2025 Corrections Issued JESUS PINEDA
Green Building Final 1/24/2025 Corrections Issued JESUS PINEDA
HVAC-Final 1/24/2025 Approved JESUS PINEDA
PLUMBING-Final 1/24/2025 Corrections Issued JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 1/24/2025 SGSOV Not Ready JESUS PINEDA
Smoke Detectors 1/24/2025 Approved JESUS PINEDA
ELECTRICAL-Final 1/30/2025 Corrections Issued HERBERT GIRON
Final 1/30/2025 Corrections Issued HERBERT GIRON
Gas Test 1/30/2025 Approved HERBERT GIRON
Green Building Final 1/30/2025 Approved HERBERT GIRON
PLUMBING-Final 1/30/2025 Approved HERBERT GIRON
ELECTRICAL-Final 2/4/2025 Approved JESUS PINEDA
Final 2/4/2025 OK to Issue CofO JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 2/4/2025 SGSOV Approved JESUS PINEDA