6008-6010 N HAZELHURST PL 91606
Certificate Information: 6008-6010 N HAZELHURST PL 91606
- Application / Permit
- 23014-10000-02232
- Plan Check / Job No.
- B23LA10383
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 18'x23' ATTACHED ONE STORY ADU W/ ROOF DECK ADDTIONTO EXISTING 1 STORY SINGLE FAMILY DEWLLING PER ENGINEER DESIGN (Attached ADU per Ordinance, LAMC 12.22 A.33(c) and (e))
- Permit Issued
- Issued on 11/13/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 9/5/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/5/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/8/2023 | AUNG SOE |
| Corrections Issued | 6/12/2023 | AUNG SOE |
| Building Plans Picked Up | 6/15/2023 | APPLICANT |
| Plan Check Approved | 9/18/2023 | JOSEPH RAFOLS |
| Issued | 11/13/2024 | APPLICANT |
| CofO in Progress | 8/26/2025 | JOSE AVILA |
| Permit Finaled | 9/5/2025 | RUBEN SALAS |
| CofO Issued | 9/5/2025 | RUBEN SALAS |
| Permit Finaled | 9/5/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 7/12/2023 | NIKKI ZULUETA |
| Roof/Waste drainage to street | Cleared | 7/12/2023 | NIKKI ZULUETA |
| Eng Process Fee Ord 176,300 | Cleared | 7/19/2023 | NIKKI ZULUETA |
| Sewer availability | Cleared | 7/19/2023 | NIKKI ZULUETA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Cooke,, Conway Cecil; Lic. No.: S5524 | 34658 LINDA ROSEA RD TEMECULA, CA 92592 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/20/2025 | Conditional Approval | RAUL OLAGI |
| Excavation/Setback/Form/Re-Bar | 3/21/2025 | Corrections Issued | JOSE AVILA |
| Footing/Foundation/Slab | 3/21/2025 | Corrections Issued | JOSE AVILA |
| Sewer | 3/21/2025 | Partial Approval | JOSE AVILA |
| Footing/Foundation/Slab | 3/26/2025 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 4/7/2025 | Partial Approval | JOSE AVILA |
| PLUMBING-Rough | 4/7/2025 | Partial Approval | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 4/10/2025 | Approved | JOSE AVILA |
| Insulation | 4/10/2025 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 5/2/2025 | Corrections Issued | JOSE AVILA |
| Deputy Wood Construction | 5/15/2025 | Conditional Approval | JUAN VALENZUELA |
| ELECTRICAL-Rough | 5/15/2025 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 5/15/2025 | Corrections Issued | JOSE AVILA |
| HVAC-Rough | 5/15/2025 | Corrections Issued | JOSE AVILA |
| PLUMBING-Rough | 5/15/2025 | Corrections Issued | JOSE AVILA |
| BUILDING-Rough-Frame | 5/30/2025 | Approved | JOSE AVILA |
| Green Building Rough | 5/30/2025 | Approved | JOSE AVILA |
| HVAC-Rough | 5/30/2025 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 5/30/2025 | Approved | JOSE AVILA |
| PLUMBING-Rough | 5/30/2025 | Approved | JOSE AVILA |
| Insulation | 6/5/2025 | Approved | JOSE AVILA |
| Drywall Nailing | 6/10/2025 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 6/10/2025 | Partial Approval | JOSE AVILA |
| Interior/Exterior Lathing | 6/13/2025 | Approved | JOSE AVILA |
| Special/Order Compliance | 7/21/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Special/Order Compliance | 7/28/2025 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Final | 8/12/2025 | Approved | JOSE AVILA |
| Final | 8/12/2025 | Corrections Issued | JOSE AVILA |
| Green Building Final | 8/12/2025 | Not Ready for Inspection | JOSE AVILA |
| HVAC-Final | 8/12/2025 | Corrections Issued | JOSE AVILA |
| PLUMBING-Final | 8/12/2025 | Approved | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 8/12/2025 | SGSOV Approved | JOSE AVILA |
| Service/Power Release | 8/12/2025 | Approved | JOSE AVILA |
| Smoke Detectors | 8/12/2025 | Approved | JOSE AVILA |
| Final | 8/25/2025 | OK to Issue CofO | JOSE AVILA |
| Green Building Final | 8/25/2025 | Approved | JOSE AVILA |