8423 W 4TH ST 90048

Certificate Information: 8423 W 4TH ST 90048

Application / Permit
23014-10000-02216
Plan Check / Job No.
B23LA10323
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
ADD (N) 167SQFT LAUNDRY ROOM AND STAIRS TO (E) SFD WITH A DECK ON TOP . WORK DONE PER ENGINEERING. SEE COMMENTS
Permit Issued
Issued on 9/8/2023
Issuing Office
Current Status
CofO Issued on 5/6/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/5/2023 APPLICANT
Assigned to Plan Check Engineer 6/9/2023 MIROOSH KHACHATOORIAN
Corrections Issued 6/12/2023 MIROOSH KHACHATOORIAN
Applicant returned to address corrections 6/22/2023 MIROOSH KHACHATOORIAN
Applicant returned to address corrections 7/11/2023 KHUONG TRUONG
Applicant returned to address corrections 7/25/2023 KHUONG TRUONG
Applicant returned to address corrections 8/27/2023 KHUONG TRUONG
Plan Check Approved 9/5/2023 KHUONG TRUONG
Issued 9/8/2023 APPLICANT
CofO in Progress 5/2/2025 EVAN COOPER
Permit Finaled 5/6/2025 RICHARD STEINBACH
CofO Issued 5/6/2025 RICHARD STEINBACH
Permit Finaled 5/6/2025 RICHARD STEINBACH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/22/2023 ADRIAN SANCHEZ
Roof/Waste drainage to street Cleared 6/22/2023 ADRIAN SANCHEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/4/2023 Corrections Issued MEL KHACHATOURIAN
METHANE-Barrier 10/4/2023 Approved MEL KHACHATOURIAN
METHANE-Subgrade 10/4/2023 Approved MEL KHACHATOURIAN
PLUMBING-Rough 10/4/2023 Corrections Issued MEL KHACHATOURIAN
Underground Mechanical 10/4/2023 Not Ready for Inspection MEL KHACHATOURIAN
PLUMBING-Rough 10/6/2023 Corrections Issued MEL KHACHATOURIAN
PLUMBING-Rough 10/12/2023 Not Ready for Inspection MEL KHACHATOURIAN
Underground Mechanical 10/12/2023 Not Ready for Inspection MEL KHACHATOURIAN
Footing/Foundation/Slab 10/19/2023 Approved MEL KHACHATOURIAN
PLUMBING-Rough 10/19/2023 Partial Approval MEL KHACHATOURIAN
Pre-Inspection 11/2/2023 Not Ready for Inspection MEL KHACHATOURIAN
Special/Order Compliance 11/2/2023 Not Ready for Inspection MEL KHACHATOURIAN
ELECTRICAL-Rough 5/9/2024 Partial Approval MEL KHACHATOURIAN
Wood Frame 5/9/2024 Partial Approval MEL KHACHATOURIAN
ELECTRICAL-Rough 5/21/2024 Not Ready for Inspection MEL KHACHATOURIAN
Wood Frame 5/21/2024 Not Ready for Inspection MEL KHACHATOURIAN
ELECTRICAL-Rough 6/10/2024 Approved TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 6/10/2024 Corrections Issued TEMISTOCLES CAAL
PLUMBING-Rough 6/10/2024 Approved TEMISTOCLES CAAL
BUILDING-Rough-Frame 6/14/2024 Approved SEAN HAUPT
Deputy Wood Construction 6/14/2024 Partial Approval SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 6/14/2024 Approved SEAN HAUPT
Green Building Rough 6/14/2024 Partial Approval SEAN HAUPT
METHANE-Rough 6/14/2024 Approved SEAN HAUPT
Insulation 6/21/2024 Approved MEL KHACHATOURIAN
Interior/Exterior Lathing 6/21/2024 Partial Approval MEL KHACHATOURIAN
Drywall Nailing 6/27/2024 Approved MEL KHACHATOURIAN
Insulation 6/27/2024 Approved MEL KHACHATOURIAN
Interior/Exterior Lathing 6/27/2024 Approved MEL KHACHATOURIAN
Pre-Inspection 12/11/2024 Approved MEL KHACHATOURIAN
BUILDING-Rough-Frame 4/29/2025 Approved EVAN COOPER
Final 4/29/2025 Corrections Issued EVAN COOPER
Green Building Final 4/29/2025 Approved EVAN COOPER
Green Building Rough 4/29/2025 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 4/29/2025 SGSOV Not Ready EVAN COOPER
Smoke Detectors 4/29/2025 Approved EVAN COOPER
ELECTRICAL-Final 5/2/2025 Approved EVAN COOPER
Final 5/2/2025 OK to Issue CofO EVAN COOPER
HVAC-Final 5/2/2025 Approved EVAN COOPER
PLUMBING-Final 5/2/2025 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 5/2/2025 SGSOV Approved EVAN COOPER