8423 W 4TH ST 90048
Certificate Information: 8423 W 4TH ST 90048
- Application / Permit
- 23014-10000-02216
- Plan Check / Job No.
- B23LA10323
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- ADD (N) 167SQFT LAUNDRY ROOM AND STAIRS TO (E) SFD WITH A DECK ON TOP . WORK DONE PER ENGINEERING. SEE COMMENTS
- Permit Issued
- Issued on 9/8/2023
- Issuing Office
- Current Status
- CofO Issued on 5/6/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/5/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/9/2023 | MIROOSH KHACHATOORIAN |
| Corrections Issued | 6/12/2023 | MIROOSH KHACHATOORIAN |
| Applicant returned to address corrections | 6/22/2023 | MIROOSH KHACHATOORIAN |
| Applicant returned to address corrections | 7/11/2023 | KHUONG TRUONG |
| Applicant returned to address corrections | 7/25/2023 | KHUONG TRUONG |
| Applicant returned to address corrections | 8/27/2023 | KHUONG TRUONG |
| Plan Check Approved | 9/5/2023 | KHUONG TRUONG |
| Issued | 9/8/2023 | APPLICANT |
| CofO in Progress | 5/2/2025 | EVAN COOPER |
| Permit Finaled | 5/6/2025 | RICHARD STEINBACH |
| CofO Issued | 5/6/2025 | RICHARD STEINBACH |
| Permit Finaled | 5/6/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/22/2023 | ADRIAN SANCHEZ |
| Roof/Waste drainage to street | Cleared | 6/22/2023 | ADRIAN SANCHEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/4/2023 | Corrections Issued | MEL KHACHATOURIAN |
| METHANE-Barrier | 10/4/2023 | Approved | MEL KHACHATOURIAN |
| METHANE-Subgrade | 10/4/2023 | Approved | MEL KHACHATOURIAN |
| PLUMBING-Rough | 10/4/2023 | Corrections Issued | MEL KHACHATOURIAN |
| Underground Mechanical | 10/4/2023 | Not Ready for Inspection | MEL KHACHATOURIAN |
| PLUMBING-Rough | 10/6/2023 | Corrections Issued | MEL KHACHATOURIAN |
| PLUMBING-Rough | 10/12/2023 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Underground Mechanical | 10/12/2023 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Footing/Foundation/Slab | 10/19/2023 | Approved | MEL KHACHATOURIAN |
| PLUMBING-Rough | 10/19/2023 | Partial Approval | MEL KHACHATOURIAN |
| Pre-Inspection | 11/2/2023 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Special/Order Compliance | 11/2/2023 | Not Ready for Inspection | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 5/9/2024 | Partial Approval | MEL KHACHATOURIAN |
| Wood Frame | 5/9/2024 | Partial Approval | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 5/21/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Wood Frame | 5/21/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 6/10/2024 | Approved | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 6/10/2024 | Corrections Issued | TEMISTOCLES CAAL |
| PLUMBING-Rough | 6/10/2024 | Approved | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 6/14/2024 | Approved | SEAN HAUPT |
| Deputy Wood Construction | 6/14/2024 | Partial Approval | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 6/14/2024 | Approved | SEAN HAUPT |
| Green Building Rough | 6/14/2024 | Partial Approval | SEAN HAUPT |
| METHANE-Rough | 6/14/2024 | Approved | SEAN HAUPT |
| Insulation | 6/21/2024 | Approved | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 6/21/2024 | Partial Approval | MEL KHACHATOURIAN |
| Drywall Nailing | 6/27/2024 | Approved | MEL KHACHATOURIAN |
| Insulation | 6/27/2024 | Approved | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 6/27/2024 | Approved | MEL KHACHATOURIAN |
| Pre-Inspection | 12/11/2024 | Approved | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 4/29/2025 | Approved | EVAN COOPER |
| Final | 4/29/2025 | Corrections Issued | EVAN COOPER |
| Green Building Final | 4/29/2025 | Approved | EVAN COOPER |
| Green Building Rough | 4/29/2025 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 4/29/2025 | SGSOV Not Ready | EVAN COOPER |
| Smoke Detectors | 4/29/2025 | Approved | EVAN COOPER |
| ELECTRICAL-Final | 5/2/2025 | Approved | EVAN COOPER |
| Final | 5/2/2025 | OK to Issue CofO | EVAN COOPER |
| HVAC-Final | 5/2/2025 | Approved | EVAN COOPER |
| PLUMBING-Final | 5/2/2025 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 5/2/2025 | SGSOV Approved | EVAN COOPER |